Topic 12_Dipan

download Topic 12_Dipan

of 26

Transcript of Topic 12_Dipan

  • 8/7/2019 Topic 12_Dipan

    1/26

    Progress and

    PerformanceMeasurementand Evaluation

    CHAPTER THIRTEEN

    Copyright 2011 by The McGraw-Hill Companies, Inc. All

    rights reserved.

    McGraw-Hill/Irwin

  • 8/7/2019 Topic 12_Dipan

    2/26

    132

    WhereWe Are NowWhereWe Are Now

    Monitoring progress & performance is the most neglected function in projects Control is basically measuring actual situation against plansWhen not monitored, projects may get delayed and over the budget

  • 8/7/2019 Topic 12_Dipan

    3/26

    133

    Structure of a Project MonitoringStructure of a Project MonitoringInformation SystemInformation System

    Creating a project monitoring systeminvolves determining:

    What data to collect Time, Cost, Resource.

    How, when, and who will collect the data

    How to analyze the data

    How to report current progress to management

    Actual Time Planned Time

    Actual Costs Budget Costs

    Resource Usage Planned Resource

  • 8/7/2019 Topic 12_Dipan

    4/26

    134

    Project Monitoring Information SystemProject Monitoring Information System

    Information System StructureWhat data are collected?

    Current status of project (schedule and cost)

    Remaining cost to compete project. Budget remaining

    Date that project will be complete

    Potential problems to be addressed now

    Out-of-control activities requiring intervention

    Cost and/or schedule overruns and the reasons for them Forecast of overruns at time of project completion

  • 8/7/2019 Topic 12_Dipan

    5/26

    135

    Project Monitoring System (contd)Project Monitoring System (contd)

    Information System Structure (contd)

    Collecting data and analysis

    Who will collect project data? PM, Member, Contractor?

    How will data be collected? Normally thru MIS

    When will the data be collected? Weekly, Milestones

    Who will compile and analyze the data? Normally PM

    Reports and reporting

    Who will receive the reports? Eg. Snr Management How will the reports be transmitted? Email, Memo

    When will the reports be distributed? Management first, thencustomer

  • 8/7/2019 Topic 12_Dipan

    6/26

    136

    Project Progress Report FormatProject Progress Report Format

    Progress since last report Current status of project

    1. Schedule

    2. Cost

    3. Scope

    Cumulative trends

    Problems and issues since last report

    1. Actions and resolution of earlier problems2. New variances and problems identified

    Corrective action planned

  • 8/7/2019 Topic 12_Dipan

    7/26

    137

    The Project Control ProcessThe Project Control Process

    Control The process of comparing actual performance against plan to

    identify deviations, evaluate courses of action, and takeappropriate corrective action.

    Project Control Steps1. Setting a baseline plan. Cost from WBS, Time from Network Diag.

    2. Measuring progress and performance. Costs & works completed now

    3. Comparing plan against actual. Extent of the deviation

    4. Taking action. Bringing costs & time back to track according to planned

    Tools Tracking and baseline Gantt charts

    Control charts

  • 8/7/2019 Topic 12_Dipan

    8/26

    138

    Baseline and Tracking Gantt ChartsBaseline and Tracking Gantt Charts

    FIGURE 13.1

  • 8/7/2019 Topic 12_Dipan

    9/26

    139

    Project Schedule Control ChartProject Schedule Control Chart

    FIGURE 13.2

  • 8/7/2019 Topic 12_Dipan

    10/26

    1310

    Disparity Among Monitoring SystemsDisparity Among Monitoring Systems

    Time-Phase Baseline PlanCorrects the failure of most monitoring systems to

    connect a projects actual performance to its scheduleand forecast budget.

    Systems that measure only cost variances do not identifyresource and project cost problems associated with fallingbehind or progressing ahead of schedule.

    Earned Value Cost/Schedule System

    An integrated project management system based onthe earned value concept that uses a time-phasedbudget baseline to compare actual and plannedschedule and costs.

  • 8/7/2019 Topic 12_Dipan

    11/26

    1311

    Glossary of TermsGlossary of Terms

    TABLE 13.1

    EV Earned value for a task is simply the percent complete times its original budget. Stated differently,EV is the percent of the original budget that has been earned by actual work completed.

    PV The planned time-phased baseline of the value of the work scheduled. An approved cost estimateof the resources scheduled in a time-phased cumulative baseline [BCWSbudgeted cost of the

    work scheduled].

    AC Actual cost of the work completed. The sum of the costs incurred in accomplishing work.[ACWPactual cost of the work performed].

    CV Cost variance is the difference between the earned value and the actual costs for the workcompleted to date where CV = EV AC.

    SV Schedule variance is the difference between the earned value and the baseline line to date whereSV = EV PV.

    BAC Budgeted cost at completion. Total budgeted cost of the baseline or project cost accounts.

    EAC Estimated cost at completion.

    ETC Estimated cost to complete remaining work.

    VAC Cost variance at completion. VAC indicates expected actual over- or under-run cost at completion.

  • 8/7/2019 Topic 12_Dipan

    12/26

    1312

    Developing an Integrated Cost/Schedule SystemDeveloping an Integrated Cost/Schedule System

    1. Define the work using a WBS.a. Scope

    b. Work packages

    c. Deliverables

    d. Organization units

    e. Resources

    f. Budgets

    2. Develop work andresource schedules.

    a. Schedule resourcesto activities

    b. Time-phase work packagesinto a network

    3. Develop a time-phasedbudget using work packagesincluded in an activity.

    Accumulate budgets (PV).

    4. At the work package level,

    collect the actual costs forthe work performed (AC).Multiply percent completetimes original budget (EV).`

    5. Compute the schedule

    variance (EV-PV) and thecost variance (EV-AC).

  • 8/7/2019 Topic 12_Dipan

    13/26

    1313

    Development of Project BaselinesDevelopment of Project Baselines

    Purposes of a Baseline (PV)An anchor point for measuring performance

    A planned cost and expected schedule againstwhich actual cost and schedule are measured.

    A basis for cash flows and awarding progress payments.

    A summation of time-phased budgets (cost accounts assummed work packages) along a project timeline.

    What Costs Are Included in Baselines?

    Labor, equipment, materials, project direct overheadcosts (DOC)

  • 8/7/2019 Topic 12_Dipan

    14/26

    1314

    Development of Project Baselines (contd)Development of Project Baselines (contd)

    Rules for Placing Costs in BaselinesCosts are placed exactly as they are expected to be

    earned in order to track them to their point of origin.

    Percent Complete Rule

    Costs are periodically assigned to a baseline as units of workare completed over the duration of a work package.

  • 8/7/2019 Topic 12_Dipan

    15/26

    1315

    Methods of Variance AnalysisMethods of Variance Analysis

    Comparing Earned ValueWith the expected schedule value.

    With the actual costs.

    Assessing Status of a Project

    Required data elements

    Data Budgeted cost of the work scheduled (PV)

    Budgeted cost of the work completed (EV)

    Actual cost of the work completed (AC)

    Calculate schedule and cost variances A positive variance indicates a desirable condition,

    while a negative variance suggests problems orchanges that have taken place.

  • 8/7/2019 Topic 12_Dipan

    16/26

    1316

    Methods of Variance AnalysisMethods of Variance Analysis

    Cost Variance (CV)Indicates if the work accomplished using labor

    and materials costs more or less than wasplanned at any point in the project.

    Schedule Variance (SV)Presents an overall assessment in dollar terms

    of the progress of all work packages in the projectscheduled to date.

  • 8/7/2019 Topic 12_Dipan

    17/26

    1317

    Cost/ScheduleCost/Schedule Graph ExampleGraph Example

    FIGURE 13.4

    Mon Tue Wed Thu Fri

    A $50

    B $100

    C $200

    D $100

    PV = $50+$100+$100 = $250

    100%

    80%

    20%

    EV = $50+$80+$40= $170

    $60

    $110

    $30

    AC = $60+$110+$30= $200

    CV = EV AC = $170-$200 = -$30

    SV = EV PV = $170-$250 = -$80

  • 8/7/2019 Topic 12_Dipan

    18/26

    1318

    Cost/Schedule GraphCost/Schedule Graph

    FIGURE 13.4

  • 8/7/2019 Topic 12_Dipan

    19/26

    1319

    EarnedEarned--Value Review ExerciseValue Review Exercise

    FIGURE 13.5

  • 8/7/2019 Topic 12_Dipan

    20/26

    1320

    Developing A Status Report:Developing A Status Report:A Hypothetical ExampleA Hypothetical Example

    Assumptions

    Each cost account has only one work package, and

    each

    cost account will be represented as an activityon the network.

    The project network early start times will serve asthe basis for assigning the baseline values.

    From the moment work an activity begins, someactual costs will be incurred each period until the

    activity is completed.

  • 8/7/2019 Topic 12_Dipan

    21/26

    1321

    Indexes to Monitor ProgressIndexes to Monitor Progress

    Performance IndexesCost Performance Index (CPI)

    Measures the cost efficiency of work accomplished to date.

    CPI = EV/AC

    Scheduling Performance Index (SPI) Measures scheduling efficiency

    SPI = EV/PV

    Percent Complete Indexes

    Indicates how much of the work accomplished represents ofthe total budgeted (BAC) and actual (AC) dollars to date.

    PCIB = EV/BAC

    PCIC = AC/EAC

    CPI = EV / AC = $170/$200 = 0.85

    SPI = EV / PV = $170/$250 = 0.68

  • 8/7/2019 Topic 12_Dipan

    22/26

    1322

    Interpretation of IndexesInterpretation of Indexes

    TABLE 13.3

    Index Cost (CPI) Schedule (SPI)

    >1.00 Under cost Ahead of schedule

    =1.00 On cost On schedule

  • 8/7/2019 Topic 12_Dipan

    23/26

    1323

    Additional Earned Value RulesAdditional Earned Value Rules

    Rules applied to short-duration activities and/orsmall-cost activities

    0/100 percent rule

    Assumes 100 % of budget credit is earned at once and only

    when the work is completed.

    50/50 rule

    Allows for 50% of the value of the work package budget tobe earned when it is started and 50% to be earned when thepackage is completed.

    Percent complete with weighted monitoring gates

    Uses subjective estimated percent complete in combinationwith hard, tangible monitoring points.

  • 8/7/2019 Topic 12_Dipan

    24/26

    1324

    Other Control IssuesOther Control Issues

    Issues In Maintaining Control Of Projects

    Scope Creep

    Baseline Changes

    Data AcquisitionCosts and Problems

  • 8/7/2019 Topic 12_Dipan

    25/26

    1325

    Scope Changes to a BaselineScope Changes to a Baseline

    FIGURE 13.13

  • 8/7/2019 Topic 12_Dipan

    26/26

    1326

    Key TermsKey Terms

    Baseline budget

    Control chart

    Cost performance index (CPI)

    Cost variance (CV)

    Earned value (EV)

    Estimated Cost at CompletionForecasted (EACf)Estimated Cost at CompletionRevised Estimates (EACre)

    Percent complete indexbudget costs (PCIB)

    Percent complete indexactual costs (PCIC)

    Schedule performance index (SPI)

    Schedule variance (SV)Scope creep

    To complete performance index (TCPI)

    Tracking Gantt chart

    Variance at completion (VAC)