Fay, Spofford & Thorndike TOWN OF BELMONT WINN’S BROOK SEWER OVERFLOW MITIGATON Presentation to...

27
Fay, Spofford & Thorndike TOWN OF BELMONT WINN’S BROOK SEWER OVERFLOW MITIGATON Presentation to the BOARD OF SELECTMAN December 7, 2009

Transcript of Fay, Spofford & Thorndike TOWN OF BELMONT WINN’S BROOK SEWER OVERFLOW MITIGATON Presentation to...

Fay, Spofford & Thorndike

TOWN OF BELMONT

WINN’S BROOK SEWER OVERFLOW MITIGATON

Presentation to the

BOARD OF SELECTMAN

December 7, 2009

Fay, Spofford & Thorndike

Presentation Objectives

• Project background

• Causes of sewer overflows

• Conceptual design and modeling

• Final Design

• Opinion of probable construction cost

• Funding

• Schedule

Fay, Spofford & Thorndike

Winn’s Brook Area

• Low lying area in Northeast Belmont

• Close proximity to MWRA connection on Flanders Road

• 85% of Belmont tributary to Flanders Road

• Extensive upstream sewer system

• Two different sewer subsystems

Fay, Spofford & Thorndike

The Problem

Periodic sanitary sewer overflows and backups into basements of

homes in the Winn’s Brook Area

Fay, Spofford & Thorndike

Fay, Spofford & Thorndike

Reported Backups

Dates Number Rainfall (inches)

October 1996 29 10

June 1998 42 8

March 2001 32 7

May 2006 11 12

Increased Hydraulic Grade Line Creates Sewer Backups

HGL

Fay, Spofford & Thorndike

Causes of an IncreasedHydraulic Grade Line (HGL)

• System Capacity Constraints

• Infiltration/Inflow in Belmont– 2007 Flow Monitoring Program

• Elevated downstream HGL– Flanders Road Connection to the MWRA

Fay, Spofford & Thorndike

Project Timeline

• 2005 – Geographical Information System (GIS)

– InfoWorks Sewer Model• Used by Cambridge & MWRA

• 2006 – Winn’s Brook Area Study

• 2007 – State (SRF) Loan Application

• 2009 – Final Design

Fay, Spofford & Thorndike

Solution Constraints

• No transference of the problem to Cambridge or significant increase in flow to MWRA interceptor

• No transference of problem within Belmont

• Continued I/I reduction will be required– 2009 Sewer System Evaluation Survey

Fay, Spofford & Thorndike

Mitigation Concepts

• Increase sewer capacity

• Flow diversion

• Storage

• Isolation and Pumping

• I/I Removal

• 13 Mitigation Alternatives Modeled

Fay, Spofford & Thorndike

Collaboration with the City of Cambridge

• Cambridge integrated Belmont’s model into the complete downstream system model

• Key in refining the selected Alternative

• NO ADVERSE IMPACT TO CAMBRIDGE

• NO INCREASED CSO RELEASE (MWRA)

Fay, Spofford & Thorndike

Selected Alternative No. 12

• Isolate Winn’s Book Area during elevated HGL conditions– New sewers and diversion structures– Divert flow to an off-line pumping station

• Divert upstream flow– Dean Street– Leonard Street & Alexander Ave.

• In-line storage conduit (Dean St)– Restricted discharge

• 15% Townwide I/I reduction

Fay, Spofford & Thorndike

Fay, Spofford & Thorndike

Fay, Spofford & Thorndike

Fay, Spofford & Thorndike

Predicted Impact at Key Manholes Outside Winn’s Brook Area

(MH rim to HGL)

Hamilton Baker Oliver Channing

Baseline

(May 2006)0.07 0.23 0.25 0.37

Alt. 12

(15 % I/I red)0.10 0.23 0.34 0.10

Fay, Spofford & Thorndike

Flanders RoadPredicted Discharge

May 2006

Mother’s Day Storm

Peak Discharge

MGD

24-Hour Volume

MG

Baseline 16.53 15.34

Alternative 12 16.84 14.90

Difference 1.98% -2.84%

Fay, Spofford & Thorndike

Fay, Spofford & Thorndike

Fay, Spofford & Thorndike

Fay, Spofford & Thorndike

Fay, Spofford & Thorndike

Opinion of Probable Construction Cost - Contract 3

Base Bid

Winn’s Brook Sewer Overflow Mitigation Facilities

$6.6 Million

Additive Alternates

Townwide I/I Removal

$1.4 Million

TOTAL $8.0 Million

Fay, Spofford & Thorndike

Project Funding

• $11.6 M State Revolving Loan (SRF)– ARRA “Shovel Ready” Projects

• Contract 1 – Wellington Brook Area Sewer and Storm Drain Improvements

• Contract 2 – Stony Brook Road and Woodbine Road Pump Station Replacement

• Contract 3 – Winn’s Brook Area Sewer Overflow Mitigation

Fay, Spofford & Thorndike

Winn’s Brook – Contract 3Construction Schedule

11/25/2009 - Advertised for Bid

12/21/2009 - Bids Received

01/15/2010 - Contract Execution

02/01/2010 - Notice to Proceed

07/31/2011 - Construction Complete

(18 months)

Questions?

Justin Gould, P.E.Fay, Spofford & Thorndike