Challenges on Implementation of Multi

modal integration in Chennai City  –

Chennai Metro Rail Perspective

N.K.Kumar Chief General Manager (PF)

Chennai Metro Rail Limited

Page 2: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 2/25

Chennai Today

0

500

1000

1500

2000

2500

3000Growth in Vehicle Population

Two wheelers Cars Total Vehicles

35.0446.01

58.1870.41

82.6

125.82

0

20

40

60

80

100

120

140

1971 1981 1991 2001 2008 2026

   P  e  r  s  o  n  s   i  n    L

  a   k   h  s

Population Growth in CMA • Total vehicle population : 33.75lakhs

(2011)

• Registered vehicles increased 5 times

during last 16 years

• Around 2 lakh vehicle registration per 

year 

Compound Annual Average GrowthRate (CAAGR) 12.5%

Page 3: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 3/25

Public Transport

• Bus/ Lakh Population remained almost

stagnant (1981-2008 )

• Metropolitan Transport Corporation

(MTC) Operates

Bus Routes - 640Fleet Size - 3300

• PT Share Drastically reduced from 54%

(1970) to 31% (2008)

• Bus – 58 lakhs trips/day

• Sub urban Rail – 9 lakhs trips/day

• MRTS – 1 lakhs trips/day0

10

20

30

40

50

60

1970 1984 1993 2008

       S       h     a     r     e       (       %       )

Year

Public Transport Share(%)

Page 4: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 4/25

Modal Share  – Other Metro Cities

Source: MoUD,Traffic & Transportation Policies and Strategies in Urban Areas in Indi a

CityPublic

Transport

Mumbai 45%

Kolkata 54%

Delhi 43%

Bangalore 35%

Hyderabad 35%

Chennai 31%

City Walk CycleTwo

Wheeler Car IPT

Mumbai 27% 6% 7% 8% 7%

Kolkata 19% 11% 4% 8% 4%

Delhi 21% 12% 5% 14% 6%

Bangalore 26% 7% 17% 8% 7%

Hyderabad 22% 9% 19% 9% 7%

Chennai 22% 9% 20% 10% 8%

Page 5: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 5/25

• Chennai Metro Rail - Improve the Public

Transport Share With the Mission Convenient,

Fast, Economical, Reliable

• Total Length  – 45.1 Km

• Corridor 1  – 23.1 Km

• Corridor 2  – 22.0 Km

• No of Stations  – 32 Nos

No of Interchanges –

2 Nos

• It is running along the major arterial roads

and connecting important places such as

 Airport, Chennai Central station, Ignore station,

Chennai Mofusill Bus Terminus (CMBT),etc.

•  About 55% of the corridors in Phase I is

underground and the remaining elevated

CMRL Network

Page 6: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 6/25

• Washermenpet  – Link with Washermenpet sub

urban station & Mini Bus Station

• Central  – Interchange with Central SR, Moore

Market Suburban, Park Station and MRTS

station

• High Court  – with Broadway bus stand

• Egmore  – Intercity and Suburban

• CMBT  – Intercity Bus Terminus

•  Alandur & Central  – Interchange

• St.Thomas Mount  – with MRTS, Suburban

•  Airport

Inter Modal Integration with Public Transport

Page 7: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 7/25

• Integrating various available modes of transport to make it complementary to each

other modes so as to ensure the optimal functioning of the existing transportation

system

• Providing easy access across various modes at the Metro stations –Seamless

Travel

MMI - Concept

Page 8: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 8/25

8

Physical Integration

Integrating Various Modes throughPhysical structures

System Integration

Integrating Various Modes through

System such as Common Ticketing

System, unlimited passes

MMI - Types

Page 9: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 9/25

Physical Integration

System Integration

Page 10: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 10/25

10

• Identification of Station Influence Area

Pedestrian access/dispersal proposal

• Public Transportation pick up & drop off facility

• Intermediate Public Transportation pick up & drop off facility

• Identification of Feeder routes

• Parking Demand Assessment

• Enhance existing connectivity

• Identification of Missing Links

• Preparation of Concept Plan

MMI - Components

Page 11: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 11/25

11

Metro Station Influence Area

 –  Immediate Influence area - 500 m around the station

 –  Broader Influence area - 2.5 Km and 5.0 Km on either side

Page 12: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 12/25

12

Pedestrian & PT/IPT Pick up & Drop off 

• Predominant Metro Users - by Walk

• Mapping Pedestrian Generation/Attraction locations

• Assess existing pedestrian demand and supply

• Pedestrian Infrastructures  – Footpath/FOB

Access Mode Share

Walk 40%

IPT 21%

Bus/Feeder Bus 19%

TW 15%

Others 5%

Page 13: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 13/25

13

Feeder ServicesTwo Stages:• MTC Route rationalization• Metro Feeder Services – Mini Buses/TATA Magic

S.

No.Distance

Number of 

Routes Services

1 0.5 to 3 Km 112 367

2 3 to 6 Km 43 107

3 6 to 9 Km 19 59

4 More than 9 Km 55 174

Total 229 707

Page 14: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 14/25

14

• Stakeholders Involvements and ownership

• Coordination activity between various Stakeholders

• Institutional/Regulatory Setup

• Land availability  – Provision of facility within available land

• Implementation of various schemes/proposals

• Rationalization of existing Public Transport Systems

Common Ticketing Solutions and Revenue Sharing Mechanisms

Challenges

Page 15: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 15/25

Existing Condition

15

Page 16: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 16/25

16

Existing Condition

Page 17: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 17/25

17

 Alandur Station

Page 18: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 18/25

 Alandur – Station Location

18

Corridor 2 Corridor 1

CMRL Land

LEGEND

Road

Station

Alignment

Page 19: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 19/25

19

 Alandur – Concept 

Pedestrian Connectivity

Pedestrian Movement

Walk Trips- 3,674

Missing Pedestrian Link

Bicycle – 168 2 Wheeler- 629 4 Wheeler -168

Two/four wheeler Connectivity

Two/Four wheeler Movement

Page 20: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 20/25

20

 Alandur – Concept 

MTC  – Bus connectivityFeeder Connectivity

Bus - 1,653

Bus stop

Bus RouteFeeder Route

IPT - 1,745

Median opening required

Page 21: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 21/25

21

 Alandur – Concept 

6

Green area

Station

Plaza & landscape

Property development

Bus Bays

IPT Station

IPT Station

Multistory parking

Proposed Subway

Bicycle parking

Pedestrian connectivity

Landscape/plazas

Parking – 2 wheelers /Bicycl

Proposed Road

Feeder Bays

Page 22: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 22/25

22

 Alandur – Concept 

EB Substation

MultistoriedParking

RSS land

Propertydevelopment

Plaza

Bicycleparking

IPT stop

Subway

IPTstop

MTC stop

MTC stop

IPT

stop

PedestrianConnectivity

Pedestrian connectivity

Landscape/plazas

Parking – 2 wheelers /Bicycle

Proposed Road

Feeder Bays

Service Road

Page 23: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 23/25

23

 Alandur – Existing Condition

Page 24: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 24/25

24

 Alandur – No intervention Scenario

Page 25: 3a5MMI - IITM.pdf

7/27/2019 3a5MMI - IITM.pdf

http://slidepdf.com/reader/full/3a5mmi-iitmpdf 25/25

Thank You