    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    REQUIREMENTS AND SOLUTIONS FORDYNAMIC VOLTAGE RESTORER

    A CASE STUDY

    REQUIREMENTS AND SOLUTIONS FORDYNAMIC VOLTAGE RESTORER

    A CASE STUDY

    P. Dhler, R. Affolter, O. ApeldoornABB Industrie AG

    5300 Turgi, Switzerland

  • 8/3/2019 0002_apeldoorn

    2/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    CONTENTSCONTENTS INTRODUCTION

    MARKET REQUIRMENTS OF THE DVR

    OPERATING PRINCIPLE OF A DVR

    SAG COMPENSATION CAPABILITY

    RELIABILITY AND AVAILABILITY

    LOSSES

    CONTROL AND PROTECTION

    HARMONICS

    MONITORING CONCLUSION

  • 8/3/2019 0002_apeldoorn

    3/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    IntroductionIntroduction

    Turgi

    www.abb.com/powerelectronics

    ABB Industrie AG, SwitzerlandPower Electronics Systems

  • 8/3/2019 0002_apeldoorn

    4/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    Market requirementsMarket requirements

    Sag & Swell compensation capability Reliability and Availability Losses Control and Protection Harmonics Monitoring

    Market requirements determine:

  • 8/3/2019 0002_apeldoorn

    5/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    Operating PrincipleOperating PrincipleBooster Transformer

    Converter

    EnergyStorage

    Distrib.Bus Load

  • 8/3/2019 0002_apeldoorn

    6/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    Operating PrincipleOperating Principle

    V B V L

    xm

    xt2

    C o n v e r t e r

    V G = 0

    xt2

    I L

    Standby Boost

    shorted CT !

    I L

    xm

    xt2

    C o n v e r t e r

    |V G | > 0

    xt2

    V B

    V L

  • 8/3/2019 0002_apeldoorn

    7/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    TopologyTopology

    DistributionBus

    LoadBus

    Filter

    Charger

    Q1 Q2

    Q3

    T 1 TL

    Control

    V G

    V L

    DVR

    I B

    = I G

  • 8/3/2019 0002_apeldoorn

    8/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    TopologyTopology

    -+ 0

    Short circuit operation (SCO-Mode)

    No switching duringSCO - Mode

    No switching losses

    No harmonics

  • 8/3/2019 0002_apeldoorn

    9/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    TopologyTopology

  • 8/3/2019 0002_apeldoorn

    10/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    Compensation RequirementsCompensation Requirements

    ms100 200 300 400 5000

    0.25

    0.35

    0.45

    0.55

    0.65

    Voltage sag [%]

  • 8/3/2019 0002_apeldoorn

    11/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    0.65

    0.35

    0.7

    00 100 200 300 400

    Compensation CapabilityCompensation Capability

    ABB

    othersmax. three phase

    sag capability0.35

    0.45

    0.55

    0.65

    Voltage sag [%]

    ms100 200 300 4000

    0.3

  • 8/3/2019 0002_apeldoorn

    12/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    Reliability AvailabilityReliability Availability

    An Availability of > 98,5% can be achieved

    This is reached by4 Simple Design4 Low number of Parts4 Implementation of the robust IGCT4 Overcurrent capability

  • 8/3/2019 0002_apeldoorn

    13/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    Reliability AvailabilityReliability Availability

    4 MVA load In operation

    since 1.5 years no IGCT

    failure(~200FIT)

    thyristortechnology isat 100 FIT

  • 8/3/2019 0002_apeldoorn

    14/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    LossesLosses

    Definition at SCO-Mode (Standby) Transformer losses (measured) Converter (calculated)

    Energy storage (calculated) Auxiliaries (measured)

    Goal = 98,5%

  • 8/3/2019 0002_apeldoorn

    15/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    LossesLosses

    Feature IGBT GTO IGCT

    device turn-off loss 100 % 100 % 100 %device turn-on loss 100 % 30 % 5 %

    gate drive power 1 % 100 % 50 %short-circuit current self limited (= f(t)) external (choke) external (choke)dv/dt snubber no yes nodi/dt snubber no yes yes

    chip mount solder pressure pressure

    switch chip discrete monolithic monolithicdiode chip discrete monolithic monolithic

    device on-state loss 100 % 70 % 50 %

  • 8/3/2019 0002_apeldoorn

    16/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    Control and ProtectionControl and Protection a ,b Transformation, eliminate zero sequence

    Parks Transformation

    Low pass filter

    DC Voltage compensation, state of charge

    Reproduce phasors

    Create 3-phase signals

    Generate boost voltage

    A,B,C

    d,q

    a,b

    a,b

    PLL

    freeze

    VDC

    Vbus

    Vin

    e j t w

    Fault

    Trigger

    Pulse Logic

    dq in

    dq filtdq out

    A,B,C

    d,q

    a,b

    a,b

    e j t w

    Pulse Width Modulator PWM

    Voltage recovery< 1 ms to 100%

  • 8/3/2019 0002_apeldoorn

    17/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    HarmonicsHarmonics

    DistributionBus

    LoadBus

    Filter

    Charger

    Q1 Q2

    Q 3

    T1TL

    Control

    V G

    V L

    DVR

    I B

    = I G

  • 8/3/2019 0002_apeldoorn

    18/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    HarmonicsHarmonics

    Spectrum of DVR Output Voltage

    Order n of harmonics

    UGN [%]

    160 2008000

    0,51

    0

    0,2

    0,4

    0,6

    Ust

    40 120

    No harmonics duringSCO - Mode

  • 8/3/2019 0002_apeldoorn

    19/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    MonitoringMonitoring

    automatic dataacquisition andlogging

    remote online access

    remote data transfer PC-based interface

    RS232 or RS485

    remote diagnosticsand softwarechanges

  • 8/3/2019 0002_apeldoorn

    20/20

    IEEE PES 2000

    ABB AutomationABB Industrie AG, Schweiz

    Design ParametersDesign Parameters

    Load & Power Factor which has to be protected Voltage to be connected Maximum single phase sag [%] or Maximum three phase sag [%] Length of Sag [ms] to protect Area to be protected Recovery time for DC Link Voltage to 100% Overcurrent capability without going in bypass