Nejat Murat Erkan Dinamikler 2016

32

Transcript of Nejat Murat Erkan Dinamikler 2016

Page 1: Nejat Murat Erkan Dinamikler 2016
Page 2: Nejat Murat Erkan Dinamikler 2016

Is it worth of using EVM for troubled

projects?

NEJAT MURAT ERKAN, MBA, PMP, ITIL

14 Nisan 2016İstanbul

Page 3: Nejat Murat Erkan Dinamikler 2016

Nejat Murat Erkan, MBA, PMP, EVM, ITIL, CPCC, ACCMr. Erkan started out his career as a business consultant in USA. In the following years, he continued his career in pharmaceutical industry. Initially, he worked as a Project Leader in Health Marketing at GlaxoSmithKline and later on, he worked as a Project Manager in the field of allergy and immunology at Greer Laboratories in North Carolina. After spending 7 years in USA, he moved back to Turkey in 2000. After his return, he continued his career in the telecommunication industry at Vodafone Turkey. In 2005, he started to work at the leading GSM operator Turkcell, as Program Manager and he managed multinational/multi-million dollar Telco/IT projects. In April 2011, he started to work as ICT Key Account Manager for Turkcell Group Companies Best in Belarus and Astelit in Ukraine. Since August 2014, he is working as Turkcell Technology Sales & Marketing Manager.Mr. Erkan holds a Bachelor of Science degree (BSChE) from Yildiz Technical University, Istanbul and a Master ofBusiness Administration (MBA) degree from Campbell University, USA. He is a member of Project Management Institute and currently he is serving as the VP of Marketing & PR & Sponsorship and Outreach of PMI Turkey Chapter and he is the College of Performance Management-Global Advisory Committee representative and first PMI EVM Certified person in Turkey.He gained his PMP certification in September 2005. He is the past president of IPYD (Istanbul Project Management Association). He also lectures project management courses at Istanbul Technical University. In August 2014, he gained his CPCC «Certified Professional Co-Active Coach» certificate and coaches young professionals.Mr. Erkan was born in 1970 in Istanbul. He speaks fluent Turkish, English, French and speaks basic Spanish and basic Russian. He believes in “life time learning”.

Earned Value Management

Page 4: Nejat Murat Erkan Dinamikler 2016

GOALWhat is EVM and how it is associated with risks?

What is the value of EVM for troubled projects?

Is it really worth of using it?

Earned Value Management

Page 5: Nejat Murat Erkan Dinamikler 2016

AGENDA

EVM Basics?EVM Practices in Turkey and US?EVM Tools?Cultural Impacts and Legislations?How Can We Benefit From EVM?

Earned Value Management

Page 6: Nejat Murat Erkan Dinamikler 2016

PROJECT

1. EVM Basics?2. EVM Practices in Turkey and US?3. EVM Tools?4. Cultural Impacts and Legislations?5. How Can We Benefit From EVM?

Earned Value Management

Page 7: Nejat Murat Erkan Dinamikler 2016

PROJECT EQUILIBRIUM

Earned Value Management

Page 8: Nejat Murat Erkan Dinamikler 2016

PROJECT SUPERHERO

Earned Value Management

Page 9: Nejat Murat Erkan Dinamikler 2016

PROJECT BASIC PROCESSES

Earned Value Management

Page 10: Nejat Murat Erkan Dinamikler 2016

PROJECT BASIC PROCESSES

Earned Value Management

Page 11: Nejat Murat Erkan Dinamikler 2016

PROJECT KNOWLEDGE AREAS

Earned Value Management

Page 12: Nejat Murat Erkan Dinamikler 2016

RISK

Earned Value Management

…likely impact or amount at stake should it occur.

it has a likelihood / probabilityof occurring, and a…

RISK EVENT

Page 13: Nejat Murat Erkan Dinamikler 2016

RISK PLANNING

Earned Value Management

Early risk management and mitigation builds better valued projects

Page 14: Nejat Murat Erkan Dinamikler 2016

RISK RESPONSE PLANNINGAvoid

Mitigate

Transfer

Earned Value Management

Avoid

Mitigate

Transfer

Accept (Workaround)

Page 15: Nejat Murat Erkan Dinamikler 2016

FOR A GOOD START

Earned Value Management

Kervan Yolda Düzülür…..!

Page 16: Nejat Murat Erkan Dinamikler 2016

BASELINING

Earned Value Management

To measure,

you need a

referance point!

Page 17: Nejat Murat Erkan Dinamikler 2016

GENERAL EVM TERMS

Earned Value Management

PV: Planned ValueEV: Earned ValueAC: Actual Cost BAC: Budget At CompletionEAC: Estimated Actual CostETC: Estmated Termination Budget VAC: Variance Actual CostCV: Cost VarianceSV: Schedule VarianceCPI: Cost Performance IndexSPI: Schedule Performance Index

CV=EV-ACSV=EV-PVCPI=EV/ACSPI=EV/PVEAC=BAC/CPIETC=EAC-ACVAC=BAC-EAC

Page 18: Nejat Murat Erkan Dinamikler 2016

GENERAL EVM TERMS

Earned Value Management

Page 19: Nejat Murat Erkan Dinamikler 2016

GENERAL EVM TERMS

Earned Value Management

PV= 800 USDEV= 600 USDAC= 900 USD

CV=EV-AC=600-900 = -300 SV=EV-PV=600-800 = -100

CPI=EV/AC=600/900 = 0,67SPI=EV/PV=600/800 = 0,75

Page 20: Nejat Murat Erkan Dinamikler 2016

PROJECT STATUS ANALYSIS

Earned Value Management

Page 21: Nejat Murat Erkan Dinamikler 2016

EVM is USA

Earned Value Management

Page 22: Nejat Murat Erkan Dinamikler 2016

EVM in Turkey Theoretical knowledge is widely spread in:

- Universities offering certificates in PM - PM training and consulting companies- And of course PMPs in Turkey

But when it comes to industry practices, it is not commonly used due to…

Earned Value Management

Page 23: Nejat Murat Erkan Dinamikler 2016

IMPLEMENTATION of EVMIn Turkey:

Turkish DoD (Subcontracting companies), Construction, Telcommunication and Banking

In other Parts of the World:Aerospace, DoD, Construction, Shipbuilding, IT, Telecommunication, Pharmaceutical, Railroad Infrastructure, Maintenance, Safety, Social Security, Euro 2004, Expo 98, Paper mill etc…

Earned Value Management

Page 24: Nejat Murat Erkan Dinamikler 2016

EVM APPLICATIONS & TOOLSIn Turkey:

- MS Project- MS Excel- In-house developed softwares- SAP Project System

In other Parts of the World:- Cobra & OpenPlan & Winsight- Welcomhome- Planview- Primavera- Systalex etc…

Earned Value Management

Page 25: Nejat Murat Erkan Dinamikler 2016

CULTURAL EFFECTS on EVM and RISK Turkish people will love to take risks with minimal

calculations We believe, we are protected by God and we

believe bad things won’t happen We are not willing to pay/reserve money for risk

allocated issues As a project manager, we need to be more

convincing on EVM and Risk Plan implementation

Earned Value Management

Page 26: Nejat Murat Erkan Dinamikler 2016

LEGISLATIONS and SANCTIONS in TURKEY Turkish Way:

-As a first step, second step and third step PMs try to solve the conflicts with subcontractors internally-As a last step PMs try to solve conflicts by taking to the courts, or make them pay penalties

Courts Lateness:-Taking to the court takes too long, not efficient laws

Few Contractors:-Very few contractors/subcontractors are in the market place

Earned Value Management

Page 27: Nejat Murat Erkan Dinamikler 2016

EVM SYSTEMS

Earned Value Management

Page 28: Nejat Murat Erkan Dinamikler 2016

HOW CAN WE BENEFIT FROM EVMS?

Earned Value Management

EVMS is the dashboard of your project...!

Page 29: Nejat Murat Erkan Dinamikler 2016

HOW CAN WE BENEFIT FROM EVMS? To be aware of the pitfalls of the project early in the life

cycle, so we can take the corrective actions sooner. Resulting time and money saving

To measure project and teams performance, so we can change the pace of the project to meet the objectives

To be able to predict the future of the project in advance, so we can have better control over the project

Earned Value Management

Page 30: Nejat Murat Erkan Dinamikler 2016

LAST WORDS

If you don’t measure it precisely, you can’t manage it properly…!!!

Earned Value Management

Page 31: Nejat Murat Erkan Dinamikler 2016

GOALWhat is EVM and how it is associated with risks?

What is the value of EVM for troubled projects?

Is it really worth of using it?

Earned Value Management

Page 32: Nejat Murat Erkan Dinamikler 2016

Q & A

Earned Value Management

N. Murat [email protected]

+90 532 210 2437

Thank You….