© 2013 www.intuio.at Agile UX: Lessons Learned IA Konferenz 2013 Thomas Zahler

description

My talk at the 2013 IA Konferenz in Berlin. Contains two case studies highlighting some problems and issues we encountered when integrating UX work in agile/lean project environments.

Transcript of IAK13 slideshare

Page 1: IAK13 slideshare

© 2013 www.intuio.at

Agile UX:Lessons Learned

IA Konferenz 2013 Thomas Zahler

Page 2: IAK13 slideshare

© 2013 www.intuio.at

Thomas ZahlerCEO @ intuio

[email protected]

Webwww.intuio.at

Twitter@intuio

Page 3: IAK13 slideshare

© 2013 www.intuio.at

Page 4: IAK13 slideshare

© 2013 www.intuio.at

“Hot food served fast”

“Are we shippingthe right software?”

Deliverables before experience

Page 5: IAK13 slideshare

© 2013 www.intuio.at

Case Study 1Call Center

Page 6: IAK13 slideshare

© 2013 www.intuio.at

ProblemHigh staff costLow customer satisfactionHeterogeneous application landscape

SolutionHarmonise the call center UIAgile project setup with UX integration

GoalsReduce staff costImprove customer service

Page 7: IAK13 slideshare

© 2013 www.intuio.at

Iteration Zero

Page 8: IAK13 slideshare

© 2013 www.intuio.at

i1 i2 i3 i4Start Release

d1 d2 d3 d4

Too late.

Page 9: IAK13 slideshare

© 2013 www.intuio.at

i1 i2 i3 i4Start Release

d1 d2 d3 d4

i0

Page 10: IAK13 slideshare

© 2013 www.intuio.at

Iteration Planning

Page 11: IAK13 slideshare

© 2013 www.intuio.at

Project Iteration n-1 Project Iteration n+1

Design Iteration n+1Design Iteration n-1 TransitionPufferQADetaildesignGrobdesignTestDesign Iteration n

SetupAnalyseDesignImplementierungQATestPufferTransitionProject Iteration n Project Iteration n+2

Design Iteration n+2

Projekt-Iteration n-2

Design Iteration n+3

Page 12: IAK13 slideshare

© 2013 www.intuio.at

TransitionTestQAFine designConcept

Setup Analysis Design Implement QA Test

Buffer

Projekt Iteration n-1

Design Iteration n+1Design-Iteration n-1 Design Iteration n+2

Synchronisation Zone

Page 13: IAK13 slideshare

© 2013 www.intuio.at

TransitionTestQAFine design

Setup Analysis Design Implement QA Test Buffer Transition

Buffer

Projekt-Iteration n-1

Design Iteration n+1 Design Iteration n+2

Project Iteration n+1

Page 14: IAK13 slideshare

© 2013 www.intuio.at

TransitionTestQAFine design Buffer

Synchronisation Point

Setup Analyse Design Implement QA Buffer Transitionn-1 Test

QAFine designConcept PufferTest

Setup Design ImplementAnalyse

Page 15: IAK13 slideshare

© 2013 www.intuio.at

Big Picture

Page 16: IAK13 slideshare

© 2013 www.intuio.at

Start i1 i2 i3 i4 Releasei0

d3 d4d1 d2 d3 d4

Page 17: IAK13 slideshare

© 2013 www.intuio.at

Start i1 i2 i3 i4 Releasei0Setup

d3 d4d1 d2 d3 d4big pic

RequirementsLo-Fi Wireframes“Big picture” concept

Page 18: IAK13 slideshare

© 2013 www.intuio.at

Ideation

Page 19: IAK13 slideshare

© 2013 www.intuio.at

before39 steps

after8 steps

Page 20: IAK13 slideshare

© 2013 www.intuio.at

intuio's innovative design solution helped us reduce the average handling time for customer enquiries in our call centre by up to 75%.

Sebastian Reiner Project management CRM

− 30 steps per case− 1,500,000 min

working time in 2009

Page 21: IAK13 slideshare

© 2013 www.intuio.at

Case Study 2Engineering Tool

Page 22: IAK13 slideshare

© 2013 www.intuio.at

Problem20 yrs old expert system2 wks training requiredDifficult to maintain, extend

SolutionImplement as web application in a lean project

GoalsReduce training effortEfficient workflows

Page 23: IAK13 slideshare

© 2013 www.intuio.at

Customer Needs

Page 24: IAK13 slideshare

© 2013 www.intuio.at

Go Low-Fi

Page 25: IAK13 slideshare

© 2013 www.intuio.at

Page 26: IAK13 slideshare

© 2013 www.intuio.at

Page 27: IAK13 slideshare

© 2013 www.intuio.at

Page 28: IAK13 slideshare

© 2013 www.intuio.at

Design in the Browser

Page 29: IAK13 slideshare

© 2013 www.intuio.at

Cultural Change

Page 30: IAK13 slideshare

© 2013 www.intuio.at

Team Structure

Page 31: IAK13 slideshare

© 2013 www.intuio.at

User Research

Page 32: IAK13 slideshare

© 2013 www.intuio.at

Individual team level

Projectlevel

Organisationlevel

Internal forces

Clear goals

Group dynamics

Group commitment

Schedule management

Management complexity

Organisational forces

Leadership

Experience

Group indepency/autonomy/power

Schedule management

Change management

Communication

Performance

Teaming

Design behaviour

Customer characteristics

Critical events/conflicts

Members’ competence

Meeting efficiency

Organisational communication

Organisational behaviour

Management commitment

External forces

Customer satisfaction

Task switching

Resourcing

Organisational behaviour

A Framework for Project Success, Marko Ikonen

Page 33: IAK13 slideshare

© 2013 www.intuio.at

@xon1c@tpir ibauer @intuio

Say hi.

Page 34: IAK13 slideshare

© 2013 www.intuio.at

Danke.

Pre

senta

tion S

lides

Sleeping Audience Members© Jessica Hagy

Page 35: IAK13 slideshare

© 2013 www.intuio.at

...

Image Creditshttp://world-beautifulwallpapers.blogspot.co.at/2013/03/waterfall-wallpapers.html

http://www.andersramsay.com/wp-content/uploads/2012/04/lean-agile-traditional.013-sm.png

http://www.extremetech.com/extreme/137521-the-tech-behind-felix-baumgartners-stratospheric-skydive

http://taicarmen.files.wordpress.com/2011/05/earth-from-space-1.jpg

http://www.flickr.com/photos/library_of_congress/2179910918/sizes/o/

http://www.njhotair.com/images/abq2002/oct05/Dscn0419.jpg

http://mode.galerijacentrs.lv/2013/03/holi-jeb-krasu-festivals-indija/

https://helda.helsinki.fi/bitstream/handle/10138/28453/leanthin.pdf?sequence=1