Circuit Breaker
-
Upload
anoop-dikshit -
Category
Documents
-
view
8 -
download
3
description
Transcript of Circuit Breaker
Part II
Circuit Breaker
Contents
Circuit breaker
Operating Principle
Interrupting principles for high-voltage circuit-breakers
Property of SF6
Advantages of SF6 breaker
Constructional design and operation
Major Supplier
Standards
Circuit breaker
In a simpler way a circuit breaker can be defined as an automatically-operated electrical switch designed to protect an electrical circuit from damage caused by overload or short circuit.
In electrical network a circuit breaker is defined as an mechanical switch device, capable of making, carrying and breaking currents under normal circuit conditions. Also capable of making and carrying current for a specified time and breaking currents under specified abnormal circuit conditions, such as those of a short circuit, without damage to itself.
Operating Principle
Electrical power transmission networks are protected and controlled by high-voltage breakers. The definition of "high voltage" varies but in power transmission work is usually thought to be 72,500 V or higher, according to a recent definition by the International Electro technical Commission (IEC). High-voltage breakers are nearly always solenoid-operated, with current sensing protective relays operated through current transformers. In substations the protection relay scheme can be complex, protecting equipment and busses from various types of overload or ground/earth fault.
High-voltage breakers are broadly classified by the medium used to extinguish the arc.
Oil-filled (dead tank and live tank)Oil-filled, minimum oil volume
Air blastSulfur hexafluoride
High voltage breakers are routinely available up to 765 kV AC. using SF6 gas as arc extinguishing media due to its high dielectric strength and other advantages.
Live tank circuit breakers are where the enclosure that contains the breaking mechanism is at line potential, that is, "Live". Dead tank circuit breaker enclosures are at earth potential.
Interrupting principles for high-voltage circuit-breakers
1
.
High-voltage circuit-breakers have greatly changed since they were first introduced and several interrupting principles have been developed that have contributed successively to a large reduction of the operating energy. Current interruption in a circuit-breaker is obtained by separating two contacts in a medium, such as sulfur hexafluoride (SF6),insulating oil and air having dielectrical and arc quenching properties. After contact separation, current is carried through an arc and is interrupted when this arc is cooled by a blast of sufficient intensity.
Sulfur hexafluoride is generally used in present high-voltage circuit-breakers (of rated voltage higher than 52 kV).
Property of SF6
The dielectric strength of SF6 in on average 2.5 times that of air, and, by increasing pressure, it can be seen that the dielectric strength also increases and than around 3.5 bar of relative pressure, SF6 has the same strength as fresh oil.
Sound propagation in SF6 gas is about three times less than in air, at atmospheric pressure. The interruption of the arc will therefore be less loud in SF6 than in air.
It is non-toxic,
It is uninflammable,It will not explode.
It is a stable gas
Advantages of SF6 breaker
Advantages of SF6 circuit breakers can explain their success:
Simplicity of the interrupting chamber which does not need an auxiliary breaking chamber;Autonomy provided by the puffer technique;The possibility to obtain the highest performance, up to 63 kA, with a reduced number of interrupting chambers;Short break time of 2 to 2.5 cycles;
High electrical endurance.Possible compact solutions when used for GIS or hybrid switchgear.
2
Integrated closing resistors or synchronized operations to reduce switching over voltages.Reliability and availability
Low noise levels.
The reduction in the number of interrupting chambers per pole has led to a considerable simplification of circuit breakers as well as the number of parts and seals required. As a direct consequence, the reliability of circuit breakers improved, as verified later on by surveys.
Constructional design and operation
SF6 circuit breaker are divided mainly in two section i.e. interrupting chamber and operating mechanism
Construction of the interrupting chamber is more or less similar however design of operating mechanism varies manufacture to manufacture depending upon the type of mechanism.
Interrupting chamber
In modern SF6 circuit breaker interruption of the current are made on puffer principle wherein SF6 gas flow on to arcing zone is generated by puffer cylinder and piston. Stationary contacts and its assembly is suspended from the upper side of the interrupting porcelain. Over head conductors are connected to the upper and the lower terminal pads
6.1.1 Closed position
During this position current flow through stationary contact, moving contact, puffer cylinder and fixed finger contacts.
6.1.2 Opening operation
Opening is done by pulling down the insulating rod, piston rod, puffer cylinder moving contact, moving arc contact and nozzle. After some contact wiping stationary and moving arc contacts separate, thereby generating arc simultaneously gas pressure in puffer chamber builds up and high pressure gas flows through nozzle and quenches the arc.
6.1.3 Closing operation
3
During this operation insulting rod is pushed up and all the parts moved in reverse direction of the opening operation simultaneously SF6 gas is taken in to the puffer chamber
The moving contact system is connected to operating mechanism housed in mechanism housing
Interrupting Chamber
Operating Mechanism
Various types of operating mechanism are used in present days
Pneumatic
Hydraulic
Spring Charged
Major Supplier
Major suppliers of circuit breaker in DTL are BHEL, CGL, ABB, AREVA etc
4
Standards
The Indian and international standard references for CB s are as given in the table below:
Standard
Title
Affirmed date
IS 1138 1991
General requirement of circuit breaker
Sept 2002
IEC 60056 (1987)
above 1000 volt
IS 15136 :1993
Method of Synthetic testing of high
April 2003
IEC 60247 (1989)
voltage AC circuit breaker
IS 14657: 1998
Gas insulated metal enclosed switch
April 2003
IEC 61259 (1994)
gear 72.5 kV and above requirement
of switching of bus charging current
IS 14658: 1999
High voltage AC circuit breakers
April 2004
IEC 61633 (1995)
guide for short circuit and switching
test procedure for metal enclose dead
tank circuit breaker
IS 14674: 1999
High voltage AC circuit breakers
April 2004
IEC 61166 (1993)
guide for seismic qualification
IS 60517 :1990
Gas insulated metal enclosed switch
Sep 2002
IS/IEC 60517 (1990)
gear 72.5 kV and above
5
Site Inspection Record (SFQP)
Equipment: Circuit Breaker
Doc No : SFQP/CB/IR/01
Site:
Bay:
Equipment Sr No.:
Make:
Rating:
Voltage level:
Page 1 of 11
I- RECEIPT AND STORAGE
1
Receipt
Remark
a
Check the serial number and accessories detail
Poles
Operating drives
Switch Cubicle
Air receiver
Compressor
b
Check the name plate details
Remark
Circuit breaker type :
Rated voltage:
Sr NO
Normal Current
Gas Pressure SF6/20 deg.C(abs)
Lightning impulse withstand voltage
Short circuit breaking current
Short time withstand current
Line charging breaking current
Closing & Opening supply voltage
Operating Sequence
First pole to clear factor
Manufacturing Year
c
Complete material is available as per packing list?
Yes
No
If NO, mention the shortfall
Remark:
d
Instruction manual is available?
Yes
No
e
G.A and erection drawing is available?
Yes
No
f
Schematic drawings available?
Yes
No.
2
Storage
Yes
No
a
Was operating drives box stored indoor?
b
Was accessories box stored indoor?
Yes
No
c
Was the outdoor equipments store above raised platform?
Yes
No
d
Any equipment damaged during re transportation/unloading at
Yes
No
site?
e
Is there any gas leakage /oil leakage/smell
Yes
No
f
Is CBs kept away from inflammable material
Yes
No
Note: Deficiencies to be brought to the knowledge of higher authorities.
Site Inspection Record (SFQP)
Equipment: Circuit Breaker
Doc No : SFQP/CB/IR/01
Site:
Bay:
Equipment Sr No.:
Make:
Rating:
Voltage level:
Page 2 of 11
II- ERECTION
Site Inspection Record (SFQP)
Equipment: Circuit Breaker
Doc No : SFQP/CB/IR/01
Site:
Bay:
Equipment Sr No.:
Make:
Rating:
Voltage level:
Page 3 of 11
1.
Foundation
Yes
No
Is foundation and location of equipments including location of
foundation bolts as per G.A drawing?
2.
Structure
a
Is length of the foundation bolts (projected outside) sufficient to
Yes
No
put check nuts?
b
Is there leveling nut available below structure?
Yes
No
c
Is the top side of the structure base plate as per G.A. Drawing?
Yes
No
d
Is direction of the structure as per G.A drawing ?
e
Is the structure leveled in x, y and z axis as per G.A drawing/
Yes
No
instruction Manual? X axis= Pole to pole distance ( Measuring
tape);Y axis= Structure Height ( Water tube level) & z axis =
Alignment of all the structures in one line ( Line thread).
f
Tightness of the nuts and check nuts done?
Yes
No
g
Are the foundation bolts filled with mortar?
Yes
No
3
Switch cubicle and compressor
Is the switch cubicle & compressor erected as per G.A. Drawing?
Yes
No
4.
Trench provision
Are the trenches provide with supporting device for copper pipe
Yes
No
5.
Equipment matching
Are the serial nos of all the equipment matching with the serial
Yes
No
numbers mentioned in the packing list?
6
Pole
a
Is there any chipping on the petticoats of insulators?
Yes
No
* If Yes, what is the size of chipping?
Can erection work proceed further?
Yes
No
Do Not proceed further if chipping is unacceptable, immediately
report
b
Is
there positive pressure verified in all the three poles?
Yes
No
Verification to be done by pressing the gas valve/dilo after
opening the dummy cover.( in case of factory assembled pole)
c
Confirm no damages observed on gas valve/dilo coupling while
Yes
No
mounting the pole column on the structure?
Do Not proceed further, if unacceptable
d
Pole erection Details:
S No
R
Phase
Y
Phase
B
Phase
e
Is the direction of the pole gas valve/pressure gauge as per G.A
Yes
No
drawing?
Site Inspection Record (SFQP)
Equipment: Circuit Breaker
Doc No : SFQP/CB/IR/01
Site:
Bay:
Equipment Sr No.:
Make:
Rating:
Voltage level:
Page 4 of 11
f
Application of proper torque on all the mounting bolts?
Yes
No
*If YES, mention the values
1. Foundation bolts
Nm
2. Structure hardware
Nm
3. Pole mounting bolts
Nm
g
Whether
associated equipment are placed in their position during
Yes
No
the erection as per approved drawing and manual in correct phase
sequence
7.
Fixing of operating mechanism/ drive
a
Was there any ingress of water found inside the drives ?
Yes
No
Rectification /overhauling required
Yes
No
Do not proceed further before rectification/ overhauling of the drive
b
Threads of bottom seal rod found intact?
Yes
No
* if No, in which serial number of the drive is damage observed:
---------------------
Replacement of the bottom seal rod to be done in the above drive
c
Removal of the close interlock pipe done to avoid damage during
Yes
No
erection?
d
Matching of serial numbers done
with respective pole and drive?
Yes
No
e
Thorough cleaning of mounting surface done before mounting
Yes
No
f
Serial number details after fixing the drives:
R Phase
Pole:
Drive:
Y Phase
Pole:
Drive:
B Phase
Pole:
Drive:
g
Is the clearances between phases and with earth are conforming to
Yes
No
design value through out
h
Check that earthing of CB and structure done as per approved
Yes
No
earthing drawing?
i
Check connection in between individual pole unit and control unit
Yes
No
8.
Pneumatic piping (if applicable)
a
Availability of following material?
Yes
No
Bending machine, pipe cutter, hacksaw, flat & round file, emery
paper ,any special tools as per OEM manual , Mulmul cloth, pull
wire, petrol/CTC, bench vice and general purpose grease/oil.
* If No, to be arrange at site before starting the job.
b
Method used for bending the pipes
Remarks
*Avoid hot bending ,only cold bending
c
Are all the pipes flushed with water jet before starting bending?
Yes
No
*If No, first flush the pipe with water jet.
d
Cleaning of pipes with water jet after bending?
Yes
No
e
After bending are the pipes cleaned with pull through method
Yes
No
using mulmul cloth & petrol/CTC?
* If NO, reclean the pipe using above method
f
Is there
the emergency tripping unit in the breaker?
Yes
No
* If Yes, clean thoroughly
g
Procedure given in instruction manual for making ermetto joints
Yes
No
was followed?
* If No, cut the ermetto rings and follow the procedure with fresh
ring
Site Inspection Record (SFQP)
Equipment: Circuit Breaker
Doc No : SFQP/CB/IR/01
Site:
Bay:
Equipment Sr No.:
Make:
Rating:
Voltage level:
Page 5 of 11
h
Clamping of all pipe joints?
Yes
No
* If NO, to be done prior to air filling
9
Cabling
a
Availability of following tools for carrying out the cabling work?
Yes
No
Multi meter, hacksaw, Knife, set of pliers, set of screw drivers,
Insulation tape, ferrules, crimping tool and belt- button
*If No, arrange proper tools before commencing the cabling job.
b
Procedure for cable glanding being followed?
Yes
No
c
Identification of each core with suitable ferrules done as per
Yes
No
schematic drawing?
* If NO, check continuity of the cable and rework.
d
Is proper size of screw driver used for fixing wires in terminal
Yes
No
blocks and auxiliary switches ?
* If No., replace damage terminals and auxiliary switches
e
Are wires at safe distance from the cam of the aux. Switch, ON-
Yes
No
OFF indicator, space heaters/ variable resistors/thermostat, etc?
* If No, redress the cable
f
IR value of cables after completion of wiring by using 500 V megar.
Measured Value :
M ohm.
10
Gas
filling and leakage test
Prerequisite for SF6 gas filling: Thermometer, Temperature v/s pressure Chart from OEM
manual, SF6 gas cylinder, gas filling kit, suitable right/left connector, spanners, fresh cloth,
CTC/Petrol & Mulmul cloth etc.
a
Presence of pressure in all the three poles? For checking use
Yes
No
double spanners to open the dummy cover of gas valve/dilo
Coupling
* If NO, Fill the pressure in that particular pole up to 2.0 bar
absolute and sniff the complete pole with the leak detector and
find the leakage. If no leakage is found, continue gas filing and if
any leakage is found first attend the leakage point before
proceeding further. Decision for vacuum can vary case to case.
b
Is the gas monitoring system fixed as per G.A drawing?
Yes
No
c
Gas filling kit is Available at site
Yes
No
* If No, arrange gas filling Kit.
d
Calibration of density Monitor/ switch at ambient Temperature
Yes
No
Ambient temperature at
site substation control room --------Deg C
TB No
Absolute Bar
Low pressure alarm (connected between Terminals)
Opening Block- I (connected between Terminals)
Opening Block II (connected between Terminals)
Time at which Calibration done:
e
Is following procedure adopted for connection of gas pipes:
Yes
No
Ensure that gas pipe is through and without any blockage or
physical damage
Site Inspection Record (SFQP)
Equipment: Circuit Breaker
Doc No : SFQP/CB/IR/01
Site:
Bay:
Equipment Sr No.:
Make:
Rating:
Voltage level:
Page 6 of 11
Cleaning the sealing surfaces at both the ends of the gas pipes
as well as at density
monitor/block end and pole end with
petrol or CTC.
Applying thin layer of grease on the threads and also on the
O rings.
Holding the gas valve/ dilo with one spanner and tightening
the nut of the gas pipe with another spanner. Ensure That Gas
Valve/Dilo does not rotate during fixing the gas pipe.
f
SF6 gas leakage test
Is
Leak detector available in working condition?
Yes
No
* If NO, do not proceed further till leak detector is arranged.
Is the compete SF6 gas system in the breaker
( which includes
Yes
No
pole, gas pipes & density switch/ monitor) free from any SF 6 gas
leakage?
* If
No, describe leakage found from which joints:------------
Can these points be rectified at site?
Yes
No
* If No, does it needs replacement?
Is any material removed from spare breaker available at site?
Yes
No
Is material to be replenished/replaced
Replenish
Replaced
List of the material required to replenish/ replace
g
Check for tightening of all bolts and nuts
Yes
No
Remark:
III-COMMISSIONING CHECK
Site Inspection Record (SFQP)
Equipment: Circuit Breaker
Doc No : SFQP/CB/IR/01
Site:
Bay:
Equipment Sr No.:
Make:
Rating:
Voltage level:
Page 7 of 11
1
Compressor detail
Make
------------------
Serial number
------------------
Year of manufacturing
-----------------
Observation
Is oil filled up to required level?
Yes
No
Is quality of oil as per specification?
Yes
No
*If NO, drain the oil and fill the specified oil
up to
specific level.
Is the tension of the belt adequate?
Yes
No
*If NO, adjust the tension
2
Air filling
Presence
of mud/ dust or dirt in drive mechanism chamber
Yes
No
of any of the drive?
*If
YES,
proper cleaning is to be carried out in drive.
serial number:
Is the complete pneumatic system including air storage
Yes
No
receiver clean & free from foreign particles?
* If
NO, Repeat the cleaning exercise till satisfaction
Switch on AC supply
Measurement of 3 phase supply : Between phase to phase
:Between phase to neutral
Thermal over load relay settings done at
Measured motor current in all the 3 phase
R phase _____A
Y phase _____ A
B phase _____ A
Compressor stops at __
bar
Is there any air leakage detected with soap solution from any of
Yes
No
the joint?
* If YES, rectify the air leakage point. If required drain the air
Are all the pipes clamps firmly into the trench and with structure
Yes
No
angles?
IF NO, clamp the Pipes.
3
Pressure switch setting in
bar ( reference pressure gauge of cubicle)
Pressure in bar
Decrease
Increase
Trip block- I
Trip block- II
Close block
Auto re-close
Low Pressure alarm
Compressor start/ stop
Site Inspection Record (SFQP)
Equipment: Circuit Breaker
Doc No : SFQP/CB/IR/01
Site:
Bay:
Equipment Sr No.:
Make:
Rating:
Voltage level:
Page 8 of 11
4
Operation of the compressor safety valve is satisfactorily
Yes
No
* If yes, what is blow-off pressure
------- bar
* If NO, any required setting done /
What is the Re- setting pressure
------- bar
5
Is the inter cabling between operating drives and the switch
Yes
No
cubicle complete?
* If No, complete the wiring
Checking of complete wiring done as per schematic drawing
number--------
Connection of density switch/monitor cables:
Setting of the variable resisters ( Measuring of coil resistance)
Ambient temperature during measurement of resistance ___ at degree centigrade
What is the control voltage
___ V DC
Current across the control circuit
---- A DC
CLOSE COIL
R Phase -Coil resistance_____
+Variable Resistance
Total
_____Ohms
Resistance
Y Phase Coil resistance ____ + Variable Resistance
Total
_____Ohms
Resistance
B Phase coil resistance:_____ + Variable Resistance
Total
_____Ohms
Resistance
TRIP COIL-1
R Phase - Coil resistance_____ +Variable Resistance
Tot
_____Ohms
Resistance
Y Phase Coil resistance ____ + Variable Resistance
Total
_____Ohms
Resistance
B Phase coil resistance:_____+ Variable Resistance
Total
_____Ohms
Resistance
TRIP COIL-2
R Phase - Coil resistance_____
+Variable Resistance
Total
_____ Ohms
Resistance
Y Phase Coil resistance ____
+ Variable Resistance
Total
_____ Ohms
Resistance
B Phase coil resistance:_____
+ Variable Resistance
Total
_____Ohms
Resistance
Requirement of DC control voltage in ideal condition: (220 VDC)
Actually measured at site with multimeter _________ VDC
Switch ON DC supply
Local Operation of The Breaker (Electrically):
Local closing operation
OK
Local tripping operation for trip coil 1
OK
Anti pumping function
OK
Trip command provided directly on terminal number:
--------
Site Inspection Record (SFQP)
Equipment: Circuit Breaker
Doc No : SFQP/CB/IR/01
Site:
Bay:
Equipment Sr No.:
Make:
Rating:
Voltage level:
Page 9 of 11
9
Pole discrepancy relay operation
OK
Timer
Timer setting ------------- sec
10
Remote operation
Closing command given on terminal number
______
Tripping command (T1) given on terminal number
______
Tripping command (T2) given on terminal number
_____
11
Post clos. Trip circuit
supervision checked on terminal numbers
For Trip Coil 1
_______________________
For Trip Coil 2
_______________________
Pre
close Trip circuit
supervision checked on terminal numbers
12
Breaker position indication (electrical)
Which colour of the lamp glow when breaker
is TRIP
--------------
Which colour of the lamp glow when breaker
is CLOSE --------------
13
Spare Contact Checking:
Position of the breaker
TRIP
Serial number of contacts found
NC:
Serial number of contacts found
NO:
Position of the breaker
CLOSE
Serial number of contacts found NC:
Serial number of contacts found NO:
14
Is the breaker with Emergency Tripping Unit (ETU)?
Yes
No
*If Yes, follow procedure listed below to test the ETU:
Close the breaker electrically.
Switch OFF the DC Supply
TRIP the breaker through Emergency trip Unit
Check whether all the 03 poles are in trip position
15
Check number of operations,
in case of failure of compressor.
(i) Breaker in close position
Build up the normal
operating pressure as per OEM manual
Number of Trip & close
operations performed till blocking.------------------
(ii) Breaker in open position
Build up the normal
operating pressure as per OEM manual
Number of Trip & close
operations performed till blocking. -----------------
16
Breaker Timing
Serial number of the Timer
Last date of calibration
Operation
Limit
Phase
Measured value
Closing
millisecond
R
______
m sec
Y
______
m sec
B
______
m sec
Site Inspection Record (SFQP)
Equipment: Circuit Breaker
Doc No : SFQP/CB/IR/01
Site:
Bay:
Equipment Sr No.:
Make:
Rating:
Voltage level:
Page 10 of 11
Tripping(T1))
millisecond
R
_______ m sec.
Y
_______ m sec
B
________m sec
Tripping (T2)
millisecond
R
________m sec
Y
_______ m sec
B
_______ m sec
CO ( through T1)
millisecond
R
_______ m sec
Y
_______ m sec
B
________m sec
CO ( through T2)
millisecond
R
_______ m sec
Y
________ m sec
B
________ m sec
17
If closing and tripping time need to be adjusted (Procedure of
Yes
No
Adjustment as per OEM manual to be recoded)
R
________
Y
________
B
________
18
Pressure Drop During Operation :
Close
________
Trip
_______
CO
________
19
Tightness of all the electrical terminals of switch cubicle and
Yes
No
drive
20
Is Gas leakage, once again verified after timing and operation?
Yes
No
21
SF6
gas pressure
after completion of job :
Bar
Time
at which the final pressure noted:
PM
22
Is air leakage, once again verified after timing and operation?
Yes
No
23
Are all the petticoats of insulators, switch cubicle , drive
Yes
No
mechanism are thoroughly cleaned and free
from dust and dirt?
* If No, clean it thoroughly with dry cloth, before charging
24
Operational counter reading as on Date:
R phase
Y phase
B phase
25
Are all the covers of drive mechanism closed properly & firmly?
Yes
No
Site Inspection Record (SFQP)
Equipment: Circuit Breaker
Doc No : SFQP/CB/IR/01
Site:
Bay:
Equipment Sr No.:
Make:
Rating:
Voltage level:
Page 11 of 11
Remark:
IV- COMMISSIONING
1
Breaker cleared for charging?
Yes
No
* If No, mention the reason/ pending points
2
Date and time of breaker charging
Signature
Signature
OEM Engineer
JE DTL
DELHI TRANSCO LTD
Standard Field Quality Plan
Name of Equipment: Circuit
Breaker
Doc No: SFQP/CB/01
Page 1 of 2
Sl
Characteristic /Item
Reference
Remark
No
document
/acceptance norms
RECEIPT & STORAGE
1.
Receipt
BOM/Packing
2.
Storage
list/manufactures
instruction manual
IIERECTION
1.
Foundation
BOM/Packing
2.
Structure erection
list/manufactures
3.
Switch cubical & compressor
instruction
4.
Trench provision
manual/approved
5.
Equipment Matching
drawing
Pole erectionFixing of operating mechanism/ drive.Pneumatic pipingCabling
10 Gas filling & leakage test III COMMISSIONING CHECK
1.
Compressor
Approved drawing/
2.
Air filling
Manufactures
3.
Pressure switch setting
instruction
4.
Compressor safety valve
manual/Test report
Inter-cablingMeasurement of coil resistanceDC control supplyLocal operation of breakerPole discrepancy operationRemote OperationTrip circuit supervisionBreaker position indicationSpare contacts checkingEmergency tripping unitNumber of operation in case of compressor failureBreaker timingClosing tripping time adjustmentPressure Drop during operation.Tightness of electrical terminals.
Re-checking of Gas leakage
Recording of SF6 gas pressure
Re-checking of air leakage.
Cleanliness of petticoats of insulator, switch cubical & drive mechanism
Operational counter reading
DELHI TRANSCO LTD
Standard Field Quality Plan
Name of Equipment: Circuit
Breaker
Doc No: SFQP/CB/01
Page 2 of 2
Sl
Characteristic /Item
Reference
Remark
No
document
/acceptance norms
Closing of covers of drive Mechanism
IV
COMMISSIONING
1. Clearance of breaker charging
Approved drawing/
2. Date and time of charging
Manufactures
instruction
manual/Test
report/Check list
Notes:
DTL specification shall mean DTL Technical Specification, approved drawings, LOA provision for specific contracts.Tests/Checks indicated at column No.2 of SFQP are only generally required to be conducted. However, any other test /check required may be carried out as per site requirement.All the testing and measuring equipment for testing should be calibrated.Test check which is not applicable for particular equipment/mode/contract shall be considered to have omitted.Latest revision/amendment of specification/standard/drawings shall be followed.For all checks suitable record shall be maintained.) Test /check indicated in column no 2 of
SFQP should be carried as per 100% sampling planning basis