![Page 1: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/1.jpg)
Center Grove High SchoolAddition & Remodeling
Schematic Design Phase
Faculty PresentationAugust 27, 2008
![Page 2: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/2.jpg)
Traffic Study• Finish Road Construction
• Let Patterns Establish
• Measure for 1-Week
• Data available 30 days later
2007 Aerial Photo
![Page 3: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/3.jpg)
Floor Levels
Existing 1st Floor: 0’-0”
New 1st Floor: 0’-0”
Existing 3rd Floor: 24’-8”
Existing 2nd Floor: 14’-0”
New 2nd Floor: 14’-0”
New 4th Floor: 28’-0”
New 5th Floor: 32’-0”
Cafeteria
New 6th Floor: 46’-0”
10’-8”14’-0”
14’-0”
14’-0”
18’-0”
14’-0”
Former Maple Grove + 32’-0”
![Page 4: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/4.jpg)
Phase I: Existing Building
ExistingMediaCenter
ExistingAcademicDepartments
ExistingArt & MusicSpaces
AdministrationCafeteria
ExistingAuditorium
![Page 5: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/5.jpg)
Phase I: Existing Building
ExistingMediaCenter
ExistingAcademicDepartments
1953Addition
ExistingArt & MusicSpaces
ExistingNatatoriumHall of
Excellence
AdministrationCafeteria
ExistingVandermeerGym
ExistingAuditorium
![Page 6: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/6.jpg)
Phase I: Expansion – New East/West Concourse
ExistingMediaCenter
ExistingAcademicDepartments
1953Addition
ExistingArt & MusicSpaces Hall of
Excellence
AdministrationCafeteria
ExistingNatatorium
ExistingVandermeerGym
NewEast / WestConcourse
ExistingAuditorium
![Page 7: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/7.jpg)
ExistingMediaCenter
ExistingAcademicDepartments
1953Addition
ExistingArt & MusicSpaces Hall of
Excellence
AdministrationCafeteria
ExistingNatatorium
ExistingVandermeerGym
NewEast / WestConcourse
Phase I: Demolish 1953 Addition
ExistingAuditorium
![Page 8: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/8.jpg)
ExistingMediaCenter
ExistingAcademicDepartments
ExistingArt & MusicSpaces Hall of
Excellence
AdministrationCafeteria
ExistingNatatorium
ExistingVandermeerGym
NewEast / WestConcourse
Phase I: Addition & Renovation: New North/South Concourse
NewNorth / SouthConcourse
ExistingAuditorium
![Page 9: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/9.jpg)
ExistingMediaCenter
ExistingAcademicDepartments
ExistingArt & MusicSpaces Hall of
Excellence
ExistingNatatorium
ExistingVandermeerGym
NewEast / WestConcourse
Phase I: Main Level: Cafeteria & Community PE Center
NewNorth / SouthConcourse
NutritionalServices
NewPE / HealthCenter
Kitchen
Serving Dining
ExistingAuditorium
![Page 10: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/10.jpg)
ExistingMediaCenter
ExistingAcademicDepartments
ExistingArt & MusicSpaces Hall of
Excellence
ExistingNatatorium
ExistingVandermeerGym
Phase I: Upper Level: Main Entry & Administration
NewNorth / SouthConcourse
NutritionalServices
NewPE / HealthCenter
Visitor Parkingand
Main Entry
AdministrationGuidanceHealth
ExistingAuditorium
![Page 11: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/11.jpg)
ExistingMediaCenter
ExistingAcademicDepartments
ExistingArt & MusicSpaces Hall of
Excellence
ExistingNatatorium
ExistingVandermeerGym
Phase I: Academic Additions
NewNorth / SouthConcourse
NutritionalServices
Visitor Parkingand
Main Entry
AdministrationGuidanceHealth
Art & MusicAddition
NewTech High &Business SLC
SpecialServices
NewPE / HealthCenter
ExistingAuditorium
![Page 12: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/12.jpg)
ExistingMediaCenter
ExistingAcademicDepartments
ExistingAuditorium
ExistingArt & MusicSpaces Hall of
Excellence
ExistingNatatorium
ExistingVandermeerGym
Phase I: Academic Remodeling (Phase I Project Completed)
NewNorth / SouthConcourse
NutritionalServices
Visitor Parkingand
Main Entry
AdministrationGuidanceHealth
Art & MusicAddition
NewTech High &Business SLC
SpecialServices
NewPE / HealthCenter
Small Learning Communities Traditional Humanities Health STEM Early College
![Page 13: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/13.jpg)
Future Phases
ExistingMediaCenter
ExistingArt & MusicSpaces
ExistingVandermeerGym
Relocated Weight TrainingHall of
Excellence
NewNatatorium
NewTechnologyHigh SLC
AcademyOf BusinessAddition
NewEast / WestConcourse
NewNorth / SouthConcourse
SpecialServices
NutritionalServices
Visitor Parkingand
Main Entry
AdministrationGuidanceHealth
NewPE / HealthCenter
Art & MusicAdditionExisting
Auditorium
Small Learning Communities Traditional Humanities Health STEM Early College
Music Expansion
![Page 14: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/14.jpg)
Main EntryAdministration / Guidance / Health
Guidance
Administration
HealthLightWells
CafeteriaOverlook
New Tech High &Academy of Business
NTH / A of BUpper Level (6)
Level 5
![Page 15: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/15.jpg)
Levels 3 & 4
Special Services
Upper Level:
Traditional SLC
![Page 16: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/16.jpg)
Early CollegeHigh School
STEM Academy(Upper Level)
Humanities SLC
Traditional SLC
Family & Consumer Science
Art
Information Technology
KitchenServingDining
Level 2
Physical Education / HealthAthletics
![Page 17: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/17.jpg)
Level 1
STEM Academy
Health SLC
Music
Humanities SLC(Lower Level)
![Page 18: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/18.jpg)
![Page 19: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/19.jpg)
Next Steps• August
– Complete Schematic Design estimate– Begin building level design review
• Review sessions scheduled through Paul Buck• Architects in building Thursday and Friday (8/28-29/08)
– Form final scope & budget options & recommendation
• September - October– Board work session– Determine final scope & budget
to be presented in a public hearing– Schedule formal “1028 Hearing”
![Page 20: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/20.jpg)
Next Steps• Winter/Spring 2008-2009
– Complete public referendum process– Attain local agency design approvals
– Design Development with building faculty & staff– Bid early sitework package of drawings
• Spring/Summer 2009– Begin Construction
• Demolish Maple Grove E.S.• Relocate Utilities, Drives and Parking
• Grading for Building Pad• SLC Roll-out spaces
– Complete Construction Documents
![Page 21: Center Grove High School Addition & Remodeling Schematic Design Phase Faculty Presentation August 27, 2008.](https://reader033.fdocument.pub/reader033/viewer/2022051417/56649cd85503460f949a0c6a/html5/thumbnails/21.jpg)
Next Steps• 2009-2010 School Year
– Begin construction of additions– Roll-Out of first SLC’s
• 2010-2011 School Year– Construction continues
• 2011-2012 School Year– Additions completed– Remodeling continues
• 2012-2013 School Year– Remodeling continues– Project is completed during the year.