RAB RENOVASI GRIYA PATRA BLOK . G . 8
NO URAIAN PEKERJAANVOLSATHARGA SATUANJUMLAH
MATERIALJASAMATERIALJASA
PONDASI3.24
1Galian Pondasi1.81--243,000
2Pondasi Batu Merah 250,00075,000452,500271,000
TOTAL I50,000452,500514,000
PEK BETON BERTULANG
1Tapak 8 : 8 ( 60,60,20 )0.431,100,000500,000473,000215,000
2Slof 8 : 5 (15/20 )0.81900,000500,000729,000405,000
3Kolom 8 : 6 (10/10)0.36900,000500,000324,000180,000
4Ring Balok 8 : 6 (12/15)0.47900,000500,000423,000235,000
5Dak Level Depan ( 1:2:3 ) 8 : 61.001,900,000500,0001,900,000500,000
6Dak Level Belakang (1:7:3 ) 8 : 60.501,900,000500,000950,000250,000
7Topi Beton ( 1 : 2 : 3 ) 8 : 60.07900,000500,00063,00035,000
TOTAL II1,820,000
IIIPEK. DINDING
1Psng dinding bata merah ad. 1:447.0095,00030.0004.465.0001.410.000
2Pelester dinding ad 1 : 4222.0045,00025.0009.990.0005.550.000
3Cat dinding451.009,0006.0004.059.0002.706.000
TOTAL III9.666.000
PEK . KUSEN, PINTU, JENDELA
1Kusen pintu pagar2.00LB-140,000-280,000
2Setel pintu komplit6.00Unit-100,000-600,000
3Setel jendela kaca komplit10.00Unit-75,000-750,000
4pPsang/ setelpintu PVC . Mandi1.00Unit-50,000-50,000
TOTAL IV1.680.000
VPEK. LANTAI
1Floor lantai ad 1 : 2: 337.0075,00025,0002.2775,000925,000
2Pasng Lantai keramik: 40X4092.0050,00035,0004,600,0003,220,000
3Pasang lantai K.Mandi 20X203.0045,00030,000135,00090,000
4Pasang keramik dinding2.7550,00035,000137,00096,250
TOTAL V7,647,0004,331,250
VIPEK. PELUMBING/ SANITASI
1Instalasi air bersih1.00Is-50,000-50,000
2Instalasi air kotor1.00Is-100,000-100,000
3Septi Tank1.00Set85,000400,000800,000400,000
TOTAL VI800,000550,000
VIIPEK.LAINNYA
1Meja Dapur
aPasang bata merah 2.1095,00030,000199,50063,000
BCor beton ( 1 : 2 : 3 ) 8 : 61.67900,000500,00015,030,000835,000
cPasang Dioc Washer1.00set175,00025,000175,00025,000
DPasang Keramik 20X253.9350,00035,000196,500137,550
2Kloset duduk American std.1.001,000,00075,0001,000,00075,000
3Cor port( 1: 2 : 3 )21.0065,00025,0001,365,000525,000
4Pagar Depan
APasang batu merah3.2595,00030,000308,75097,500
BKolom 8 : 6 (10/10)0.02900,000500,00018,00010,000
cRing Blok 8 : 6 (12/15)0.12900,000500,000108,00060,000
dPlesteran6.50450,00025,000292,500162,500
TOTAL VII5.166.2501,990,550
VIIPEK. PENUTUP GAVANIS
Plapond Hollo Galvanis gypsum120.7275,00035,0009,054,0004,225,000
Atap RBR Limas pasir18.31150,00030,0002,746,500548,300
Instalasi listrik1.00LS--500,000
TOTAL VIII11,800,5005,274,300
GRAND TOTAL I S/D VII
37,127,25020,552,300
GRAND TOTAL I S/D VIII
48,927,75025,826,800
Note :Urungan tanah luas tanah : 10 x 15 x 0,30 = 45 M3 : 5 = 9 TrukUrungan tanah luas bangun : 98,75 x 0,30 = 29,625 M3 = 5 = 5,8 Truk ( 6 )Untuk tanah urug : 9 x 250.000 = Rp. 2.250.000Jasa Angkut + rata = 9 x 200.000 = Rp. 1.800.000