ARENA update on large scale solar

13
1 NSW Renewable Energy Investment Briefing Ian Kay CFO ARENA 25 May 2016

Transcript of ARENA update on large scale solar

1

NSW Renewable Energy Investment Briefing

Ian Kay – CFO ARENA

25 May 2016

2

The large scale solar market has come a long way in 5 years

0

100

200

300

400

500

600

700

800

0

50

100

150

200

250

300

2012 2013 2014 2015 2016 2017* 2018

Large Scale Solar Developments in Australia (MW)

Non-ARENA Funded (LHS) ARENA Funded (LHS) Cumulative (RHS)

2012 – Greenough River Solar Farm built. Financed by Synergy, GE and the WA government

* Projects to be announced

3

With the state governments leading the initial charge

0

100

200

300

400

500

600

700

800

0

50

100

150

200

250

300

2012 2013 2014 2015 2016 2017* 2018

Large Scale Solar Developments in Australia (MW)

Non-ARENA Funded (LHS) ARENA Funded (LHS) Cumulative (RHS)

2014 – Royalla Solar Farm built by FRV as part of ACT Government Solar Auction

* Projects to be announced

4

AGL stepping in for Australia’s first major deployment

0

100

200

300

400

500

600

700

800

0

50

100

150

200

250

300

2012 2013 2014 2015 2016 2017* 2018

Large Scale Solar Developments in Australia (MW)

Non-ARENA Funded (LHS) ARENA Funded (LHS) Cumulative (RHS)

2015 – AGL’s Nyngan Solar Farm comes online with NSW Government support

* Projects to be announced

5

2014 and 2015 were lean years for the industry

0

100

200

300

400

500

600

700

800

0

50

100

150

200

250

300

2012 2013 2014 2015 2016 2017* 2018

Large Scale Solar Developments in Australia (MW)

Non-ARENA Funded (LHS) ARENA Funded (LHS) Cumulative (RHS)

2016 – Broken Hill, Moree Solar Farm, Mugga Lane, Normanton and Sunshine Coast

* Projects to be announced

6

But the path to parity has been forged in perseverance

0

100

200

300

400

500

600

700

800

0

50

100

150

200

250

300

2012 2013 2014 2015 2016 2017* 2018

Large Scale Solar Developments in Australia (MW)

Non-ARENA Funded (LHS) ARENA Funded (LHS) Cumulative (RHS)

Clare Solar Farm

2017 – Barcaldine and Clare Solar Farms announced

* Projects to be announced

7

The market is clearly exceeding all expectations

0

100

200

300

400

500

600

700

800

0

50

100

150

200

250

300

2012 2013 2014 2015 2016 2017* 2018

Large Scale Solar Developments in Australia (MW)

Non-ARENA Funded (LHS) ARENA Funded (LHS) Cumulative (RHS)

ARENA LSS Round 2018 – ARENA’s large scale solar competitive round expected to exceed by 25%

* Projects to be announced

8

Measuring the ripple effect is difficult, only hindsight is a useful yardstick

$80 – $100

BREE 2012

$210 – $300

LC

OE

$/M

Wh

2010 2015 2020

ACT FIT *

$110 - $130

Australian LCOE trajectory

* Normalised for capital structure advantages associated with 20 year FIT

ARENA

current

portfolio

Short term target

wind parity

$140 - $170

Were we too conservative?

9

The large scale solar round was launched in a difficult environment Consultations began in mid 2015 before the round was launched in September 2015.

200+ registrations, 80+ applicants, 22 shortlisted parties and ?? winners

10

Shared knowledge is an invaluable commodity

1.5

1.7

1.9

2.1

2.3

2.5

2.7$

/W

Average Total Capital Costs per Watt of Installed Capacity (DC and AC)

Capital Costs (DC) per Watt Capital Costs (AC) per Watt

Average AC Average Australia Wind

Source: ARENA

Solar capital costs now below wind

11

Solar now looking to take its fair share of the market to 2021

Source: Bloomberg New Energy Finance, 2016

7,205 7,205 7,205

4,067

7,990 8,081 642

643 644

243

2,882 2,699

12,360

19,131 19,040

0

5,000

10,000

15,000

20,000

25,000

2015 Aggressive buildscenario

Gradual buildscenario

Landfill gas

Indstrial PV

STEG

Large-scale PV

Biomass

Wind

Hydro

12

Thank you

Questions?

13

Find out more at arena.gov.au