DAFTAR HARGA SATUAN UPAH PEKERJA
PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR BWS SUMATERA IVLOKASI : KOTA BATAM
NO. UPAH TENAGA KERJA SATUAN HARGA SATUAN
1 2 3 4
1 Mandor Org/ Hr 55,000.00 2 Kepala Tukang Org/ Hr 60,000.00 3 Tukang Batu Org/ Hr 55,000.00 4 Tukang Kayu Org/ Hr 55,000.00 5 Tukang Besi Org/ Hr 55,000.00 6 Tukang Cat Org/ Hr 55,000.00 7 Operator Alat Berat Org/ Hr 65,000.00 8 Tukang Listrik Org/ Hr 55,000.00 9 Tukang Pipa Org/ Hr 55,000.00
10 Tukang Las Org/ Hr 55,000.00 11 Tukang Alumunium Org/ Hr 55,000.00 12 Tukang Gypsum Org/ Hr 55,000.00 13 Tukang Org/ Hr 55,000.00 14 Pekerja Org/ Hr 35,000.00
Jam Kerja Effektif 1 Hari 7 jam
DAFTAR HARGA SATUAN BAHAN BANGUNAN
PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR BWS SUMATERA IVLOKASI : KOTA BATAM
NO. JENIS MATERIAL SATUAN HARGA SATUAN
1 2 3 4
A BAHAN PASANGAN
1 Bata Merah Bh 1,200.00 2 Batako Bh 1,900.00 3 Paving abu-abu segi enam, tebal 8 cm M2 72,000.00 4 Kanstin abu-abu 15 x 25 x 40 Bh 5,500.00 5 Batu Belah 15-20 cm M3 260,000.00 6 Batu pecah/split 2/3 M3 280,000.00 7 Batu pecah 5/7 M3 280,000.00 8 Abu batu M3 280,000.00 9 Glass Block Bh 25,000.00
10 Pasir Beton/ Cor M3 140,000.00 11 Pasir Pasang M3 140,000.00 12 Pasir Urug M3 120,000.00 13 Sirtu M3 85,000.00 14 Semen PC @ 50 Kg Kg 1,140.00 15 Semen Putih @ 50 Kg Kg 1,300.00 16 Semen Warna Kg 1,300.00 17 Tanah Timbun ( Tanah Merah ) M3 20,000.00 18 Batu Terawang 20 x 20 cm Bh 10,000.00 19 Air Ltr 500.00 20 Beton Ready Mix K-225 M3 800,000.00 21 Boring Tanah 30 cm M 200,000.00 22 Ijuk Kg 10,000.00
![Page 2: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/2.jpg)
NO. JENIS MATERIAL SATUAN HARGA SATUAN
1 2 3 4
B BAHAN KAYU
1 Kayu dolken Ø 8-10/400 cm Btg 6,000.00 2 Kayu Cerucuk dia. 10-15cm Btg 15,000.00 3 Kayu Kapur ( Kelas I ) M3 400,000.00 4 Kayu Meranti Palembang Kaso M3 4,000,000.00 5 Kayu Meranti Palembang Papan M3 4,050,000.00 6 Kayu Meranti Palembang balok M3 3,950,000.00 7 Kayu Campuran (Kelas III) M3 2,500,000.00 8 Kayu 1" x 2" M3 2,750,000.00
9 Papan Meranti ( Kelas II ) 1" x 8" M3 2,800,000.00 10 Papan Meranti ( Kelas II ) 3/4" x 8" M3 2,800,000.00 11 Tunjuk Langit Bh 500,000.00 12 Triplek 4x8 ft 6 mm Lbr 82,000.00 13 Paku biasa 2"-5" Kg 13,000.00 14 Paku biasa 1/2"- 1" Kg 13,000.00 15 Paku Beton Kg 20,000.00 16 Kayu Kamper Medan/Kruing papan M3 4,000,000.00 17 Kayu list profil M' 600.00 18 Kayu Terentang papan 3 cm M3 2,500,000.00 19 Kayu Terentang kaso M3 2,035,000.00 20 Kayu Terentang balok M3 2,300,000.00 21 Triplek 4x8 ft 9 mm Lbr 115,000.00 22 Sekrup 6x1-1,5 Bh 1,100.00 23 Sekrup gypsum Bh 1,200.00
C BAHAN BESI
1 Besi Beton Kg 7,800.00 2 Kawat Beton ( Kawat Ikat ) Kg 12,000.00 3 Railling Besi Galvanish M2 1,100,000.00
D BAHAN LANTAI
1 Keramik Ukuran 40 x 40 KW II Bh 12,800.00 2 Ubin Keramik Ukuran 30 x 30 cm Roman Bh 9,000.00 3 Ubin Keramik Ukuran 20 x 20 cm Roman Bh 2,050.00 4 Plint Keramik 10 x 40 Bh 6,050.00 5 Keramik Ukuran 60 x 60 Bh 20,000.00
keramik Ukuran 20 x 25 Bh 3,500.00
E BAHAN ATAP
1 Perabung Spandek M' 45,000.00 2 Spandek Motif Lurus M2 83,000.00 3 Seng gelombang 3x6 ft BJLS 20 (0,2 mm) Lbr 45,000.00 4 Besi baja WF Kg 15,000.00 5 Genteng Metal M2 82,000.00 6 Nok Genteng Metal M' 63,000.00
![Page 3: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/3.jpg)
NO. JENIS MATERIAL SATUAN HARGA SATUAN
1 2 3 4
F BAHAN DINDING DAN LANGIT - LANGIT
1 Gypsum Padat Setara Jaya Board 9 mm Lbr 48,000.00 2 GRC Board Lbr 46,000.00 3 List Gypsum Tinggi 8 cm M' 8,000.00 4 List Kayu Pracetak M' 10,000.00 5 Triplek 4x8 ft 4 mm Lbr 60,000.00 6 Plywood 9 mm Lbr 115,000.00 7 Plywood 12 mm Lbr 167,000.00 8 Paku Peluru Ramset Bh 2,000.00 9 Hollow 4x4 cm tbl 0.6 mm Btg 20,000.00
10 Hollow 2x4 cm tbl 0.6 mm Btg 18,000.00 11 Gypsumboard 120x240 cm 9 mm Lbr 50,000.00 12 Textile tape rol 55,000.00 13 Compound gypsum zak 50,000.00 14 Amplas lbr 1,500.00 15 Coumpound GRC Zak 50,000.00 16 Calsiboard 120mm x 240 mm 4 mm lbr 40,000.00 17 Paku Rivet Bh 1,000.00 18 GRC-board 120x240 cm 6 mm lbr 55,000.00
G BAHAN PIPA
1 Kran air dia 1/2 " Bh 12,000.00 2 Pipa PVC 4 " M' 18,000.00 3 Pipa PVC 2 " M' 15,000.00 4 Pipa PVC 1/2 " M' 8,500.00 5 Pipa PVC 3/4 " M' 10,000.00 6 Pipa PVC 1 " M' 12,500.00 7 Pipa PVC 3 " M' 16,000.00
Pompa Air Shimidzu Bh 1,000,000.00
H BAHAN SANITAIR
1 Bak Fiber Bh 400,000.00 2 Kloset Jongkok Keramik Bh 900,000.00 3 Kran Air 1/2" Bh 12,000.00 4 Wastafel Keramik Bh 300,000.00 5 Klosed Duduk (Ina) Bh 850,000.00 6 Flour Drain Bh 8,000.00
I BAHAN PAKU
3 Paku Spandek Kg 20,000.00 4 Paku Gypsum Kg 18,000.00 5 Paku Kayu Kg 13,000.00 6 Paku Skrup Kg 20,000.00 7 Paku Tripleks/ Teakwood Kg 13,000.00
J BAHAN PENGGANTUNG/ KUNCI
1 Engsel Pintu Bh 8,000.00 2 Grendel Pintu Bh 18,000.00 3 Kunci Tanam 2 x Putar Bh 110,000.00
![Page 4: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/4.jpg)
NO. JENIS MATERIAL SATUAN HARGA SATUAN
1 2 3 4
K BAHAN STAINLESS
1 Stainless Steel M' 120,000.00
L BAHAN LISTRIK
1 Titik Lampu Ttk 125,000.00 2 Sarang Lampu Down Light Komplit Bh 35,000.00 3 Lampu SL 20 Watt Bh 28,000.00 4 Arde Pentanahan Netral (Lengkap) Bh 115,000.00 5 Stop Kontak Bh 25,000.00 6 Saklar Ganda Bh 22,000.00 7 Saklar Triple Bh 31,500.00 8 Panel MCB Komplit Bh 600,000.00 9 Lampu Down Light Bh 50,000.00
10 Panel MCB Biasa Bh 300,000.00 11 Kabel NYM 2x2,5 mm² m'12 Conduit pipa PVC dia ⅝" C m'13 Tee dos bh14 Inbow doos bh15 Sock bh16 Klem conduit bh17 Lastdop bh18 Flexible pipe m'19 Elbow bh20 Lampu TL 2x 18 Watt bh 28,000.00 21 Penangkal Petir + Grounding Unit 3,000,000.00
M BAHAN PINTU & JENDELA
1 P1 Bh 9,500,000.00 2 P2 Bh 1,350,000.00 3 P3 Bh 900,000.00 4 P4 Bh 600,000.00 5 P5 Bh 900,000.00 6 P6 Bh 600,000.00 7 P7 Bh 500,000.00 8 J1 Bh 1,500,000.00 9 J2 Bh 2,000,000.00
10 J3 Bh 700,000.00 11 J4 Bh 850,000.00 12 J5 Bh 950,000.00 13 BV1 Bh 660,000.00 14 BV2 Bh 1,500,000.00 15 J6 Bh 1,500,000.00 15 J7 Bh 5,250,000.00 15 J8 Bh 3,000,000.00 16 Jendela nako (rangka) daun 300,000.00 17 Besi segi empat 3/8"x3/8" (0,83kg/m') kg 9,800.00 18 Kaca 5 mm m² 25,000.00 19 Engsel pintu biasa/sederhana set 15,000.00 20 Kunci tanam sederhana bh 120,000.00 21 Kusen Pintu Unit 128,000.00 22 Kusen Jendela Unit 122,000.00
![Page 5: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/5.jpg)
NO. JENIS MATERIAL SATUAN HARGA SATUAN
1 2 3 4
N BAHAN FINISHING1 Cat kayu/besi KW 2 (cat dasar) Kg 15,000.00 2 Cat kayu/besi KW 2 (cat penutup) Kg 17,000.00 3 Cat tembok Catylac (cat dasar) Kg 11,500.00 4 Cat tembok Catylac (cat penutup) Kg 12,000.00 5 Minyak Bekisting Ltr 7,500.00 6 Minyak Cat Ltr 20,000.00 7 Plamir Kg 25,300.00 8 Minyak Bekisting Ltr 6,500.00 9 Wall sealer Dulux/ICI Kg 7,500.00
10 Cat tembok Dulux/ICI (cat dasar) Kg 17,500.00 11 Cat tembok Dulux/ICI (cat penutup) Kg 17,500.00 12 Cat tembok Dulux/ICI Weathershield Kg 18,000.00 13 Cumoir Waterproofing Coating Kg 45,000.00
O BAHAN BAJA RINGAN
1 Supertruss C.75 100 INT Setara Zam Steel M2 190,000.00 2 Alumunium Hollow M' 25,000.00
DAFTAR HARGA SATUAN PERALATAN
PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR BWS SUMATERA IVLOKASI : KOTA BATAM
NO. JENIS PERALATAN SATUAN HARGA SATUAN
1 2 3 4
1 Vibrating Roller 6 - 8 Ton Jam 300,000.00 2 Concrete Mixer 0.3 - 0.6 M3 Jam 25,000.00 3 Generator Set Jam 75,000.00 4 Three Wheel Roller 8 - 10 T Jam 130,000.00 5 Tamper / Hand Compactor Jam 30,000.00 6 Plate Compactor Jam 51,000.00 7 Water Tank Truck 3000 - 4500 L Jam 120,000.00
![Page 6: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/6.jpg)
DAFTAR HARGA SATUAN UPAH PEKERJA
KETERANGAN
5
DAFTAR HARGA SATUAN BAHAN BANGUNAN
KETERANGAN
5
Terpasang
Terpasang
![Page 7: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/7.jpg)
KETERANGAN
5
![Page 8: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/8.jpg)
KETERANGAN
5
Terpasang Terpasang Terpasang
![Page 9: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/9.jpg)
KETERANGAN
5
Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang Terpasang
![Page 10: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/10.jpg)
KETERANGAN
5
DAFTAR HARGA SATUAN PERALATAN
KETERANGAN
5
![Page 11: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/11.jpg)
11
ANALISIS HARGA SATUAN
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
1. Pembuatan kantor sementara dengan lantai plesteran + meja & bangku kayu tiap 1 m²
Harga bahan:
- Semen portland kg 20 1,140 22,800.00
- Pasir beton m³ 0.04 140,000 5,600.00
- Batu pecah/split 2/3 m³ 0.0666 280,000 18,648.00
- Kayu Meranti Palembang kaso m³ 0.0479 4,000,000 191,600.00
- Paku biasa 2"-5" kg 0.27 13,000 3,510.00
- Paku biasa 1/2"- 1" kg 0.079 13,000 1,027.00
- Triplek 4x8 ft 4 mm lbr 1.189 60,000 71,340.00
- Seng gelombang 3x6 ft BJLS 20 (0,2 mm) Lbr 1.158 45,000 52,110.00
- Jendela nako (rangka) daun 0.541 300,000 162,300.00
- Besi segi empat 3/8"x3/8" (0,83kg/m') kg 0.269 9,800 2,636.20
- Kaca 5 mm m² 0.049 25,000 1,225.00
- Engsel pintu biasa/sederhana set 0.078 15,000 1,170.00
- Kunci tanam sederhana bh 0.078 120,000 9,360.00
Harga bahan untuk meja & kursi sederhana:
- Triplek 4x8 ft 6 mm lbr 0.051 82,000 4,182.00
- Kayu Meranti Palembang kaso m³ 0.01 4,000,000 40,000.00
- Kayu Meranti Palembang papan m³ 0.004 4,050,000 16,200.00
- Paku biasa 2"-5" kg 0.074 13,000 962.00
- Paku biasa 1/2"- 1" kg 0.007 13,000 91.00
Jumlah Harga Bahan 604,761.20
Upah tenaga:
- Pekerja Oh 0.931 35,000 32,585.00
- Tukang kayu Oh 1.319 55,000 72,545.00
- Tukang batu Oh 0.022 55,000 1,210.00
- Kepala tukang Oh 0.135 60,000 8,100.00
- Mandor Oh 0.04 55,000 2,200.00
Jumlah Upah Tenaga 116,640.00
Jumlah Total 721,401.20
Total termasuk keuntungan 721,401.20
2. Pasang bouwplank tiap 1 m'
Harga bahan:
- Kayu Meranti Palembang papan m³ 0.007 4,050,000 28,350.00
- Kayu Meranti Palembang kaso m³ 0.012 4,000,000 48,000.00
- Paku biasa 2"-5" kg 0.02 13,000 260.00
Jumlah Harga Bahan 76,610.00
Upah tenaga:
- Tukang kayu Oh 0.1 55,000 5,500.00
- Pekerja Oh 0.1 35,000 3,500.00
- Kepala tukang Oh 0.01 60,000 600.00
- Mandor Oh 0.005 55,000 275.00
Jumlah Upah Tenaga 9,875.00
Jumlah Total 86,485.00
Total termasuk keuntungan 86,485.00
HARGA SAT. DASAR (Rp)
![Page 12: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/12.jpg)
12
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
B PEKERJAAN TANAH
1. Pembersihan lapangan dan perataan tiap 1 m²
Upah tenaga:
- Pekerja Oh 0.1 35,000 3,500.00
- Mandor Oh 0.05 55,000 2,750.00
Jumlah Upah Tenaga 6,250.00
Jumlah Total 6,250.00
Total termasuk keuntungan 6,250.00
2. Galian tanah biasa sedalam 1 meter tiap 1 m³
Upah tenaga:
- Pekerja Oh 0.75 35,000 26,250.00
- Mandor Oh 0.025 55,000 1,375.00
Jumlah Upah Tenaga 27,625.00
Jumlah Total 27,625.00
Total termasuk keuntungan 27,625.00
3. Pembuangan tanah sejauh 150 m tiap 1 m³
Upah tenaga:
- Pekerja Oh 0.516 35,000 18,060.00
- Mandor Oh 0.05 55,000 2,750.00
Jumlah Upah Tenaga 20,810.00
Jumlah Total 20,810.00
Total termasuk keuntungan 20,810
4. Urugan tanah kembali tiap 1 m³
Upah tenaga:
- Pekerja Oh 0.25 35,000 8,750.00
- Mandor Oh 0.0083 55,000 456.50
Jumlah Upah Tenaga 9,206.50
Jumlah Total 9,206.50
Total termasuk keuntungan 9,206.50
5. Urugan pasir urug tiap 1 m³
Harga bahan:
- Pasir urug m³ 1.2 120,000 144,000.00
Jumlah Harga Bahan 144,000.00
Upah tenaga:
- Pekerja Oh 0.3 35,000 10,500.00
- Mandor Oh 0.01 55,000 550.00
Jumlah Upah Tenaga 11,050.00
Jumlah Total 155,050.00
Total termasuk keuntungan 155,050.00
![Page 13: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/13.jpg)
13
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
C PEKERJAAN PASANGAN BATU KALI/BELAH
1. Pasang pondasi/pasangan batu kali/belah 1 Pc : 4 Ps tiap 1 m³
Harga bahan:
- Batu belah 15/20 m³ 1.2 260,000 312,000.00
- Semen portland kg 163 1,140 185,820.00
- Pasir pasang m³ 0.52 140,000 72,800.00
Jumlah Harga Bahan 570,620.00
Upah tenaga:
- Pekerja Oh 1.5 35,000 52,500.00
- Tukang batu Oh 0.6 55,000 33,000.00
- Kepala tukang Oh 0.06 60,000 3,600.00
- Mandor Oh 0.075 55,000 4,125.00
Jumlah Upah Tenaga 93,225.00
Jumlah Total 663,845.00
Total termasuk keuntungan 663,845.00
2. Pasang pondasi/pasangan batu kali/belah 1 Pc : 3 Ps tiap 1 m³
Harga bahan:
- Batu belah 15/20 m³ 1.2 260,000 312,000.00
- Semen portland kg 217.33 1,140 247,756.20
- Pasir pasang m³ 0.39 140,000 54,600.00
Jumlah Harga Bahan 614,356.20
Upah tenaga:
- Pekerja Oh 1.5 35,000 52,500.00
- Tukang batu Oh 0.6 55,000 33,000.00
- Kepala tukang Oh 0.06 60,000 3,600.00
- Mandor Oh 0.075 55,000 4,125.00
Jumlah Upah Tenaga 93,225.00
Jumlah Total 707,581.20
Total termasuk keuntungan 707,581.20
3. Pasang pondasi batu kosong (aanstamping) tiap 1 m³
Harga bahan:
- Batu belah 15/20 m³ 1.2 260,000 312,000.00
- Pasir urug m³ 0.432 120,000 51,840.00
Jumlah Harga Bahan 363,840.00
Upah tenaga:
- Pekerja Oh 0.78 35,000 27,300.00
- Tukang batu Oh 0.39 55,000 21,450.00
- Kepala tukang Oh 0.039 60,000 2,340.00
- Mandor Oh 0.039 55,000 2,145.00
Jumlah Upah Tenaga 53,235.00
Jumlah Total 417,075.00
Total termasuk keuntungan 417,075.00
![Page 14: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/14.jpg)
14
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
D PEKERJAAN DINDING
1. Pasangan bata merah tebal 1/2 bata, 1 Pc : 2 Ps tiap 1m²
Harga bahan:
- Bata merah bh 70 1,200 84,000.00
- Semen portland kg 18.95 1,140 21,603.00
- Pasir pasang m³ 0.038 140,000 5,320.00
Jumlah Harga Bahan 110,923.00
Upah tenaga:
- Pekerja Oh 0.3 35,000 10,500.00
- Tukang batu Oh 0.1 55,000 5,500.00
- Kepala tukang Oh 0.01 60,000 600.00
- Mandor Oh 0.015 55,000 825.00
Jumlah Upah Tenaga 17,425.00
Jumlah Total 128,348.00
Total termasuk keuntungan 128,348.00
2. Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps tiap 1m²
Harga bahan:
- Bata merah bh 70 1,200 84,000.00
- Semen portland kg 11.5 1,140 13,110.00
- Pasir pasang m³ 0.043 140,000 6,020.00
Jumlah Harga Bahan 103,130.00
Upah tenaga:
- Pekerja Oh 0.3 35,000 10,500.00
- Tukang batu Oh 0.1 55,000 5,500.00
- Kepala tukang Oh 0.01 60,000 600.00
- Mandor Oh 0.015 55,000 825.00
Jumlah Upah Tenaga 17,425.00
Jumlah Total 120,555.00
Total termasuk keuntungan 120,555.00
3. Pasangan bata merah tebal 1/2 bata, 1 Pc : 5 Ps tiap 1m²
Harga bahan:
- Bata merah bh 70 1,200 84,000.00
- Semen portland kg 9.68 1,140 11,035.20
- Pasir pasang m³ 0.045 140,000 6,300.00
Jumlah Harga Bahan 101,335.20
Upah tenaga:
- Pekerja Oh 0.3 35,000 10,500.00
- Tukang batu Oh 0.1 55,000 5,500.00
- Kepala tukang Oh 0.01 60,000 600.00
- Mandor Oh 0.015 55,000 825.00
Jumlah Upah Tenaga 17,425.00
Jumlah Total 118,760.20
Total termasuk keuntungan 118,760.20
![Page 15: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/15.jpg)
15
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
4. Pasangan rollag bata merah 1 Pc : 5 Ps , tiap 1 m' (1 lapis bata)
Harga bahan:
- Bata merah bh 16 1,200 19,200.00
- Semen portland kg 2.442 1,140 2,783.88
- Pasir pasang m³ 0.01122 140,000 1,570.80
Jumlah Harga Bahan 23,554.68
Upah tenaga:
- Pekerja Oh 0.0715 35,000 2,502.50
- Tukang batu Oh 0.022 55,000 1,210.00
- Kepala tukang Oh 0.0022 60,000 132.00
- Mandor Oh 0.0033 55,000 181.50
Jumlah Upah Tenaga 4,026.00
Jumlah Total 27,580.68
Total termasuk keuntungan 27,580.68
9. Pasangan rollag bata merah 1 Pc : 4 Ps , tiap 1 m' (2 lapis bata)
Harga bahan:
- Bata merah bh 32 1,200 38,400.00
- Semen portland kg 7.318 1,140 8,342.52
- Pasir pasang m³ 0.0274 140,000 3,836.00
Jumlah Harga Bahan 50,578.52
Upah tenaga:
- Pekerja Oh 0.174 35,000 6,090.00
- Tukang batu Oh 0.0540 55,000 2,970.00
- Kepala tukang Oh 0.0054 60,000 324.00
- Mandor Oh 0.008 55,000 440.00
Jumlah Upah Tenaga 9,824.00
Jumlah Total 60,402.52
Total termasuk keuntungan 60,402.52
E PEKERJAAN PLESTERAN
1. Plesteran 1 Pc : 2 Ps tebal 15 mm tiap 1m²
- Semen portland kg 10.224 1,140 11,655.36
- Pasir pasang m³ 0.02 140,000 2,800.00
Jumlah Harga Bahan 14,455.36
Upah tenaga:
- Pekerja Oh 0.2 35,000 7,000.00
- Tukang batu Oh 0.15 55,000 8,250.00
- Kepala tukang Oh 0.015 60,000 900.00
- Mandor Oh 0.01 55,000 550.00
Jumlah Upah Tenaga 16,700.00
Jumlah Total 31,155.36
Total termasuk keuntungan 31,155.36
2. Plesteran 1 Pc : 3 Ps tebal 15 mm tiap 1m²
Harga bahan:
- Semen portland kg 7.776 1,140 8,864.64
- Pasir pasang m³ 0.023 140,000 3,220.00
Jumlah Harga Bahan 12,084.64
Upah tenaga:
- Pekerja Oh 0.2 35,000 7,000.00
- Tukang batu Oh 0.15 55,000 8,250.00
- Kepala tukang Oh 0.015 60,000 900.00
- Mandor Oh 0.01 55,000 550.00
Jumlah Upah Tenaga 16,150.00
Jumlah Total 28,234.64
Total termasuk keuntungan 28,234.64
![Page 16: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/16.jpg)
16
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
3. Plesteran 1 Pc : 4 Ps tebal 15 mm tiap 1m²
Harga bahan:
- Semen portland kg 6.24 1,140 7,113.60
- Pasir pasang m³ 0.024 140,000 3,360.00
Jumlah Harga Bahan 10,473.60
Upah tenaga:
- Pekerja Oh 0.2 35,000 7,000.00
- Tukang batu Oh 0.15 55,000 8,250.00
- Kepala tukang Oh 0.015 60,000 900.00
- Mandor Oh 0.01 55,000 550.00
Jumlah Upah Tenaga 16,700.00
Jumlah Total 27,173.60
Total termasuk keuntungan 27,173.60
4. Acian 1 m2
Harga bahan:
- Semen portland kg 3.25 1,140 3,705.00
Jumlah Harga Bahan 3,705.00
Upah tenaga:
- Pekerja Oh 0.15 35,000 5,250.00
- Tukang batu Oh 0.1 55,000 5,500.00
- Kepala tukang Oh 0.01 60,000 600.00
- Mandor Oh 0.008 55,000 440.00
Jumlah Upah Tenaga 11,790.00
Jumlah Total 15,495.00
Total termasuk keuntungan 15,495.00
5. Pasang lisplank (3 x 30) cm Kayu Kamper Medan/Kruing tiap 1m'
Harga bahan:
- Kayu Kamper Medan/Kruing papan m³ 0.011 4,000,000 44,000.00
- Paku biasa 2"-5" kg 0.05 13,000 650.00
Jumlah Harga Bahan 44,650.00
Upah tenaga:
- Pekerja Oh 0.11 35,000 3,850.00
- Tukang kayu Oh 0.22 55,000 12,100.00
- Kepala tukang Oh 0.022 60,000 1,320.00
- Mandor Oh 0.005 55,000 275.00
Jumlah Upah Tenaga 17,545.00
Jumlah Total 62,195.00
Total termasuk keuntungan 62,195.00
6. List Plafon kayu profil tiap 1m'
Harga bahan:
- Kayu list profil m' 1.05 600 630.00
- Paku biasa 1/2"- 1" kg 0.01 13,000 130.00
Jumlah Harga Bahan 760.00
Upah tenaga:
- Pekerja Oh 0.05 35,000 1,750.00
- Tukang kayu Oh 0.05 55,000 2,750.00
- Kepala tukang Oh 0.005 60,000 300.00
- Mandor Oh 0.003 55,000 165.00
Jumlah Upah Tenaga 4,965.00
Jumlah Total 5,725.00
Total termasuk keuntungan 5,725.00
![Page 17: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/17.jpg)
17
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
7. Penutup plafon Gypsumboard 9 mm lengkap dgn rangka hollow tebal 0.6 mm / tiap 1 m²
Harga bahan:
- Paku peluru ramset bh 0.39 2,000 780.00
- Hollow 4x4 cm tbl 0.6 mm btg 0.459 20,000 9,180.00
- Hollow 2x4 cm tbl 0.6 mm btg 0.431 18,000 7,758.00
- Paku beton kg 0.01 20,000 200.00
- Sekrup 6x1-1,5 bh 14 1,100 15,400.00
- Gypsumboard 120x240 cm 9 mm lbr 0.364 50,000 18,200.00
- Sekrup gypsum bh 21 1,200 25,200.00
- Textile tape rol 0.024 55,000 1,320.00
- Compound gypsum zak 0.02 50,000 1,000.00
- Amplas lbr 0.1 1,500 150.00
Jumlah Harga Bahan 79,188.00
Upah tenaga:
- Pekerja Oh 0.26 35,000 9,100.00
- Tukang alumunium Oh 0.26 55,000 14,300.00
- Tukang gypsum Oh 0.05 55,000 2,750.00
- Kepala tukang Oh 0.031 60,000 1,860.00
- Mandor Oh 0.013 55,000 715.00
Jumlah Upah Tenaga 28,725.00
Jumlah Total 107,913.00
Total termasuk keuntungan 107,913
8. Penutup plafon Calsiboard 4 mm lengkap dgn rangka hollow tebal 0.6 mm / tiap 1 m²
Harga bahan:
- Paku peluru ramset bh 0.39 2,000 780.00
- Hollow 4x4 cm tbl 0.6 mm btg 0.459 20,000 9,180.00
- Hollow 2x4 cm tbl 0.6 mm btg 0.431 18,000 7,758.00
- Paku beton kg 0.01 20,000 200.00
- Sekrup 6x1-1,5 bh 14 1,100 15,400.00
- Calsiboard 120x240 cm 4 mm lbr 0.364 40,000 14,560.00
- Sekrup gypsum bh 21 1,200 25,200.00
- Textile tape rol 0.024 55,000 1,320.00
- Compound GRC zak 0.02 50,000 1,000.00
- Amplas lbr 0.1 1,500 150.00
Jumlah Harga Bahan 75,548.00
Upah tenaga:
- Pekerja Oh 0.26 35,000 9,100.00
- Tukang alumunium Oh 0.26 55,000 14,300.00
- Tukang gypsum Oh 0.05 55,000 2,750.00
- Kepala tukang Oh 0.031 60,000 1,860.00
- Mandor Oh 0.013 55,000 715.00
Jumlah Upah Tenaga 28,725.00
Jumlah Total 104,273.00
Total termasuk keuntungan 104,273.00
9. Dinding partisi gypsum 12 mm lkp rk metal Studs 2 muka tiap 1 m²
![Page 18: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/18.jpg)
18
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
Harga bahan:
- Metal wall stud 35mm x 40mm m' 2
- Metal wall track 30mm x 40mm m' 0.75
- Paku rivet bh 4
- Sekrup 6x1-1,5 bh 8
- Gypsumboard 120x240 cm 12 mm lbr 0.75
- Textile tape roll 0.24
- Compound gypsum zak 0.12
- Sekrup gypsum bh 24
- Amplas lbr 0.5
Jumlah Harga Bahan
Upah tenaga:
- Pekerja Oh 0.2
- Tukang gypsum Oh 0.3
- Tukang alumunium Oh 0.2
- Mandor Oh 0.015
Jumlah Upah Tenaga
Jumlah Total
Total termasuk keuntungan
10. Dinding partisi double GRC-board 6 mm rk hollow tiap 1 m²
Harga bahan:
- Hollow 4x4 cm tbl 0.6 mm btg 1.25 20,000 25,000.00
- Hollow 2x4 cm tbl 0.6 mm btg 0.8 18,000 14,400.00
- Paku rivet bh 4 1,000 4,000.00
- Sekrup 6x1-1,5 bh 8 1,100 8,800.00
- GRC-board 120x240 cm 6 mm lbr 0.75 55,000 41,250.00
- Textile tape roll 0.24 55,000 13,200.00
- Compound GRC zak 0.12 50,000 6,000.00
- Sekrup gypsum bh 24 1,200 28,800.00
- Amplas lbr 0.5 1,500 750.00
Jumlah Harga Bahan 142,200.00
- Pekerja Oh 0.2 35,000 7,000.00
- Tukang kayu Oh 0.3 55,000 16,500.00
- Tukang alumunium Oh 0.2 55,000 11,000.00
- Mandor Oh 0.015 55,000 825.00
Jumlah Upah Tenaga 28,325.00
Jumlah Total 170,525.00
Total termasuk keuntungan 170,525.00
![Page 19: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/19.jpg)
19
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
J PEKERJAAN BETON
1. Beton Non Struktur 1Pc : 3Ps : 5Kr - untuk rabatan/ beton tumbuk tiap 1m³
Harga bahan:
- Semen portland kg 218 1,140 248,520.00
- Pasir beton m³ 0.52 140,000 72,800.00
- Batu pecah/split 2/3 m³ 0.87 280,000 243,600.00
Jumlah Harga Bahan 564,920.00
Upah tenaga:
- Pekerja Oh 1.65 35,000 57,750.00
- Tukang batu Oh 0.25 55,000 13,750.00
- Kepala tukang Oh 0.025 60,000 1,500.00
- Mandor Oh 0.08 55,000 4,400.00
Jumlah Upah Tenaga 77,400.00
Jumlah Total 642,320.00
Total termasuk keuntungan 642,320.00
![Page 20: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/20.jpg)
20
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
4. Beton K-175 (1Pc : 2,5Ps : 3,5Kr) tiap 1m³
Harga bahan:
- Semen portland kg 300 1,140 342,000.00
- Pasir beton m³ 0.526 140,000 73,640.00
- Batu pecah/split 2/3 m³ 0.737 280,000 206,360.00
Jumlah Harga Bahan 622,000.00
Upah tenaga:
- Pekerja Oh 1.65 35,000 57,750.00
- Tukang batu Oh 0.25 55,000 13,750.00
- Kepala tukang Oh 0.025 60,000 1,500.00
- Mandor Oh 0.08 55,000 4,400.00
Jumlah Upah Tenaga 77,400.00
Jumlah Total 699,400.00
Total termasuk keuntungan 699,400.00
5. Beton Struktur K-225 (1Pc : 2Ps : 3Kr) tiap 1m³
Harga bahan:
- Semen portland kg 350 1,140 399,000.00
- Pasir beton m³ 0.485 140,000 67,900.00
- Batu pecah/split 2/3 m³ 0.727 280,000 203,560.00
Jumlah Harga Bahan 670,460.00
Upah tenaga:
- Pekerja Oh 2 35,000 70,000.00
- Tukang batu Oh 0.35 55,000 19,250.00
- Kepala tukang Oh 0.035 60,000 2,100.00
- Mandor Oh 0.1 55,000 5,500.00
Jumlah Upah Tenaga 96,850.00
Jumlah Total 767,310.00
Total termasuk keuntungan 767,310.00
Total termasuk keuntungan 767,310.00
Beton Readymix K-225
- Beton Readymix K-225 m3 1.02 800,000.00 816,000.00
- Upah Pengecoran m3 1 200,000.00 200,000.00
- Jumlah Total 1,016,000.00
- Total termasuk keuntungan 1,016,000.00
9. Pembesian dengan besi polos tiap 1 kg
Harga bahan:
- Besi beton polos kg 1.05 7,800 8,190.00
- Kawat beton kg 0.015 12,000 180.00
Jumlah Harga Bahan 8,370.00
Upah tenaga:
- Pekerja Oh 0.007 35,000 245.00
- Tukang besi Oh 0.007 55,000 385.00
- Kepala tukang Oh 0.0007 60,000 42.00
- Mandor Oh 0.0004 55,000 22.00
Jumlah Upah Tenaga 694.00
Jumlah Total 9,064.00
Total termasuk keuntungan 9,064.00
![Page 21: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/21.jpg)
21
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
10. Pembesian dengan besi ulir tiap 1 kg
Harga bahan:
- Besi beton ulir kg 1.05 7,800 8,190.00
- Kawat beton kg 0.015 12,000 180.00
Jumlah Harga Bahan 8,370.00
Upah tenaga:
- Pekerja Oh 0.007 35,000 245.00
- Tukang besi Oh 0.007 55,000 385.00
- Kepala tukang Oh 0.0007 60,000 42.00
- Mandor Oh 0.0004 55,000 22.00
Jumlah Upah Tenaga 694.00
Jumlah Total 9,064.00
Total termasuk keuntungan 9,064.00
11. Pasang bekisting untuk pondasi 1 m²
Harga bahan:
- Kayu Terentang papan 3 cm m³ 0.04 2,500,000 100,000.00
- Paku biasa 2"-5" kg 0.3 13,000 3,900.00
- Minyak Bekisting lt 0.1 6,500 650.00
Jumlah Harga Bahan 104,550.00
Upah tenaga:
- Pekerja Oh 0.52 35,000 18,200.00
- Tukang kayu Oh 0.26 55,000 14,300.00
- Kepala tukang Oh 0.026 60,000 1,560.00
- Mandor Oh 0.026 55,000 1,430.00
Jumlah Upah Tenaga 35,490.00
Jumlah Total 140,040.00
Total termasuk keuntungan 140,040.00
2x Pemakaian 70,020.00
12. Pasang bekisting untuk sloof 1 m²
Harga bahan:
- Kayu Terentang papan 3 cm m³ 0.045 2,500,000 112,500.00
- Paku biasa 2"-5" kg 0.3 13,000 3,900.00
- Minyak Bekisting lt 0.1 6,500 650.00
Jumlah Harga Bahan 117,050.00
Upah tenaga:
- Pekerja Oh 0.52 35,000 18,200.00
- Tukang kayu Oh 0.26 55,000 14,300.00
- Kepala tukang Oh 0.026 60,000 1,560.00
- Mandor Oh 0.026 55,000 1,430.00
Jumlah Upah Tenaga 35,490.00
Jumlah Total 152,540.00
Total termasuk keuntungan 152,540.00
2x Pemakaian 76,270.00
![Page 22: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/22.jpg)
22
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
13. Pasang bekisting untuk sloof 1 m² dengan bahan tripleks 9 mm
Harga bahan:
- Triplek 4x8 ft 9 mm lbr 0.35 115,000 40,250.00
- Kayu Terentang kaso m³ 0.03 2,500,000 75,000.00
- Paku biasa 2"-5" kg 0.3 13,000 3,900.00
- Minyak Bekisting lt 0.1 6,500 650.00
Jumlah Harga Bahan 119,800.00
Upah tenaga:
- Pekerja Oh 0.52 35,000 18,200.00
- Tukang kayu Oh 0.26 55,000 14,300.00
- Kepala tukang Oh 0.026 60,000 1,560.00
- Mandor Oh 0.026 55,000 1,430.00
Jumlah Upah Tenaga 35,490.00
Jumlah Total 155,290.00
Total termasuk keuntungan 155,290.00
2x Pemakaian 77,645.00
14. Pasang bekisting untuk kolom 1 m²
Harga bahan:
- Kayu Terentang kaso m³ 0.04 2,035,000 81,400.00
- Paku biasa 2"-5" kg 0.4 13,000 5,200.00
- Minyak bekisting lt 0.2 7,500 1,500.00
- Kayu Terentang balok m³ 0.015 2,300,000 34,500.00
- Triplek 4x8 ft 9 mm lbr 0.35 115,000 40,250.00
- Kayu dolken Ø 8-10/400 cm btg 2 6,000 12,000.00
Jumlah Harga Bahan 174,850.00
Upah tenaga:
- Pekerja Oh 0.66 35,000 23,100.00
- Tukang kayu Oh 0.33 55,000 18,150.00
- Kepala tukang Oh 0.033 60,000 1,980.00
- Mandor Oh 0.033 55,000 1,815.00
Jumlah Upah Tenaga 45,045.00
Jumlah Total 219,895.00
Total termasuk keuntungan 219,895.00
2x Pemakaian 109,947.50
15. Pasang bekisting untuk balok 1 m²
Harga bahan:
- Kayu Terentang kaso m³ 0.04 2,035,000 81,400.00
- Paku biasa 2"-5" kg 0.4 13,000 5,200.00
- Minyak bekisting lt 0.2 7,500 1,500.00
- Kayu Meranti Palembang balok m³ 0.018 2,300,000 41,400.00
- Triplek 4x8 ft 9 mm lbr 0.35 115,000 40,250.00
- Kayu dolken Ø 8-10/400 cm btg 2 6,000 12,000.00
Jumlah Harga Bahan 181,750.00
Upah tenaga:
- Pekerja Oh 0.66 35,000 23,100.00
- Tukang kayu Oh 0.33 55,000 18,150.00
- Kepala tukang Oh 0.033 60,000 1,980.00
- Mandor Oh 0.033 55,000 1,815.00
Jumlah Upah Tenaga 45,045.00
Jumlah Total 226,795.00
Total termasuk keuntungan 226,795.00
2x Pemakaian 113,397.50
![Page 23: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/23.jpg)
23
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
16. Pasang bekisting untuk pelat lantai 1 m²
Harga bahan:
- Kayu Terentang kaso m³ 0.04 2,035,000 81,400.00
- Paku biasa 2"-5" kg 0.4 13,000 5,200.00
- Minyak bekisting lt 0.2 7,500 1,500.00
- Kayu Meranti Palembang balok m³ 0.015 3,950,000 59,250.00
- Triplek 4x8 ft 9 mm lbr 0.35 115,000 40,250.00
- Kayu dolken Ø 8-10/400 cm btg 6 6,000 36,000.00
Jumlah Harga Bahan 223,600.00
Upah tenaga:
- Pekerja Oh 0.66 35,000 23,100.00
- Tukang kayu Oh 0.33 55,000 18,150.00
- Kepala tukang Oh 0.033 60,000 1,980.00
- Mandor Oh 0.033 55,000 1,815.00
Jumlah Upah Tenaga 45,045.00
Jumlah Total 268,645.00
Total termasuk keuntungan 268,645.00
2x Pemakaian 134,322.50
Kolom Praktis
Beton K-175 m3 1.00 699,400 699,400.00
Pembesian kg 100.00 9,064 906,400.00
Begesting m2 6.67 109,948 732,983.33
Jumlah Total 2,338,783.33
Total termasuk keuntungan 2,338,783.33
K PEKERJAAN PENUTUP ATAP
1. Pasang atap genteng metal tiap 1m²
Harga bahan:
- Genteng metal m² 1.02 82,000 83,640.00
- Paku biasa 2"-5" kg 0.2 13,000 2,600.00
Jumlah Harga Bahan 86,240.00
Upah tenaga:
- Pekerja Oh 0.2 35,000 7,000.00
- Tukang kayu Oh 0.1 55,000 5,500.00
- Kepala tukang Oh 0.01 60,000 600.00
- Mandor Oh 0.001 55,000 55.00
Jumlah Upah Tenaga 13,155.00
Jumlah Total 99,395.00
Total termasuk keuntungan 99,395.00
2. Pasang nok genteng metal tiap 1m'
Harga bahan:
- Nok genteng metal bh 1.1 63,000 69,300.00
- Paku biasa 1/2"- 1" kg 0.05 13,000 650.00
Jumlah Harga Bahan 69,950.00
Upah tenaga:
- Pekerja Oh 0.25 35,000 8,750.00
- Tukang kayu Oh 0.15 55,000 8,250.00
- Kepala tukang Oh 0.015 60,000 900.00
- Mandor Oh 0.013 55,000 715.00
Jumlah Upah Tenaga 18,615.00
Jumlah Total 88,565.00
Total termasuk keuntungan 88,565.00
![Page 24: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/24.jpg)
24
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
L PEKERJAAN SANITASI
1. Memasang 1 buah kloset duduk/monoblok (sederhana)
Harga bahan:
- Kloset duduk ex RRC (sederhana) bh 1
- Perlengkapan (6% harga kloset) % 6
Jumlah Harga Bahan
Upah tenaga:
- Pekerja Oh 3.3
- Tukang batu Oh 1.1
- Kepala tukang Oh 0.001
- Mandor Oh 0.16
Jumlah Upah Tenaga
Jumlah Total
Total termasuk keuntungan
2. Memasang 1 buah kloset duduk/monoblok setara INA (sedang)
Harga bahan:
- Kloset duduk setara INA (sedang) bh 1 850,000 850,000.00
- Perlengkapan (6% harga kloset) % 6 51,000.00
Jumlah Harga Bahan 901,000.00
Upah tenaga:
- Pekerja Oh 3.3 35,000 115,500.00
- Tukang batu Oh 1.1 55,000 60,500.00
- Kepala tukang Oh 0.001 60,000 60.00
- Mandor Oh 0.16 55,000 8,800.00
Jumlah Upah Tenaga 184,860.00
Jumlah Total 1,085,860.00
Total termasuk keuntungan 1,085,860.00
![Page 25: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/25.jpg)
25
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp)
1 2 3 4 5 6
HARGA SAT. DASAR (Rp)
7. Memasang 1 buah wastafel
Harga bahan:
- Wastafel bh 1 300,000 300,000.00
- Perlengkapan (12% harga wastafel) % 12 36,000.00
- Semen portland kg 6 1,140 6,840.00
- Pasir pasang m³ 0.01 140,000 1,400.00
Jumlah Harga Bahan
Upah tenaga:
- Pekerja Oh 1.2 35,000 42,000.00
- Tukang batu Oh 1.45 55,000 79,750.00
- Kepala tukang Oh 0.15 60,000 9,000.00
- Mandor Oh 0.1 55,000 5,500.00
Jumlah Upah Tenaga
Jumlah Total
Total termasuk keuntungan
![Page 26: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/26.jpg)
26
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
11. Memasang pipa PVC tipe AW dia 1/2" tiap m'
Harga bahan:
- Pipa PVC dia 1/2" AW m' 1.2 8,500 10,200.00
- Perlengkapan (35% harga pipa) % 35 2,975.00
Jumlah Harga Bahan 13,175.00
Upah tenaga:
- Pekerja Oh 0.036 35,000 1,260.00
- Tukang pasang pipa Oh 0.06 55,000 3,300.00
- Kepala tukang Oh 0.006 60,000 360.00
- Mandor Oh 0.0018 55,000 99.00
Jumlah Upah Tenaga 5,019.00
Jumlah Total 18,194.00
Total termasuk keuntungan 18,194.00
12. Memasang pipa PVC tipe AW dia 3/4" tiap m'
Harga bahan:
- Pipa PVC dia 3/4" AW m' 1.2 10,000 12,000.00
- Perlengkapan (35% harga pipa) % 35 3,500.00
Jumlah Harga Bahan 15,500.00
Upah tenaga:
- Pekerja Oh 0.036 35,000 1,260.00
- Tukang pasang pipa Oh 0.06 55,000 3,300.00
- Kepala tukang Oh 0.006 60,000 360.00
- Mandor Oh 0.0018 55,000 99.00
Jumlah Upah Tenaga 5,019.00
Jumlah Total 20,519.00
Total termasuk keuntungan 20,519.00
13. Memasang pipa PVC tipe AW dia 1" tiap m'
Harga bahan:
- Pipa PVC dia 1" AW m' 1.2 12,500 15,000.00
- Perlengkapan (35% harga pipa) % 35 4,375.00
Jumlah Harga Bahan 19,375.00
Upah tenaga:
- Pekerja Oh 0.036 35,000 1,260.00
- Tukang pasang pipa Oh 0.06 55,000 3,300.00
- Kepala tukang Oh 0.006 60,000 360.00
- Mandor Oh 0.0018 55,000 99.00
Jumlah Upah Tenaga 5,019.00
Jumlah Total 24,394.00
Total termasuk keuntungan 24,394.00
14. Memasang pipa PVC tipe AW dia 2" tiap m'
Harga bahan:
- Pipa PVC dia 2" AW m' 1.2 15,000 18,000.00
- Perlengkapan (35% harga pipa) % 35 5,250.00
Jumlah Harga Bahan 23,250.00
Upah tenaga:
- Pekerja Oh 0.054 35,000 1,890.00
- Tukang pasang pipa Oh 0.09 55,000 4,950.00
- Kepala tukang Oh 0.009 60,000 540.00
- Mandor Oh 0.0027 55,000 148.50
Jumlah Upah Tenaga 7,528.50
Jumlah Total 30,778.50
Total termasuk keuntungan 30,778.50
![Page 27: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/27.jpg)
27
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
15. Memasang pipa PVC tipe AW dia 3" cm tiap m'
Harga bahan:
- Pipa PVC dia 3" AW m' 1.2 16,000 19,200.00
- Perlengkapan (35% harga pipa) % 35 5,600.00
Jumlah Harga Bahan 24,800.00
Upah tenaga:
- Pekerja Oh 0.081 35,000 2,835.00
- Tukang pasang pipa Oh 0.135 55,000 7,425.00
- Kepala tukang Oh 0.0135 60,000 810.00
- Mandor Oh 0.0041 55,000 225.50
Jumlah Upah Tenaga 11,295.50
Jumlah Total 36,095.50
Total termasuk keuntungan 36,095.50
16. Memasang pipa PVC tipe AW dia 4" tiap m'
Harga bahan:
- Pipa PVC dia 4" AW m' 1.2 18,000 21,600.00
- Perlengkapan (35% harga pipa) % 35 6,300.00
Jumlah Harga Bahan 27,900.00
Upah tenaga:
- Pekerja Oh 0.081 35,000 2,835.00
- Tukang pasang pipa Oh 0.135 55,000 7,425.00
- Kepala tukang Oh 0.0135 60,000 810.00
- Mandor Oh 0.0041 55,000 225.50
Jumlah Upah Tenaga 11,295.50
Jumlah Total 39,195.50
Total termasuk keuntungan 39,195.50
![Page 28: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/28.jpg)
28
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
20. Memasang 1 floor drain sederhana
Harga bahan:
- Floor drain sederhana bh 1 8,000 8,000.00
Jumlah Harga Bahan 8,000.00
Upah tenaga:
- Pekerja Oh 0.01 35,000 350.00
- Tukang batu Oh 0.1 55,000 5,500.00
- Kepala tukang Oh 0.01 60,000 600.00
- Mandor Oh 0.005 55,000 275.00
Jumlah Upah Tenaga 6,725.00
Jumlah Total 14,725.00
Total termasuk keuntungan 14,725.00
21. Memasang 1 floor drain stainless
Harga bahan:
- Floor drain stainless bh 1
Jumlah Harga Bahan
Upah tenaga:
- Pekerja Oh 0.01
- Tukang batu Oh 0.1
- Kepala tukang Oh 0.01
- Mandor Oh 0.005
Jumlah Upah Tenaga
Jumlah Total
Total termasuk keuntungan
22. Membuat 1 unit sumur air tanah bor manual dalam 12 m' + pompa air listrik
Harga bahan:
- Pipa PVC dia 3/4" AW m' 14 10,000 140,000.00
- Pipa PVC dia 2" D m' 12 15,000 180,000.00
- Pompa air listrik Shimizu 125 W unit 1 1,000,000 1,000,000.00
- Perlengkapan (35% harga pipa+pompa) % 35 358,750.00
Jumlah Harga Bahan 1,678,750.00
Upah tenaga:
- Pekerja Oh 3.162 35,000 110,670.00
- Tukang pasang pipa Oh 2.32 55,000 127,600.00
- Kepala tukang Oh 0.232 60,000 13,920.00
- Mandor Oh 0.1581 55,000 8,695.50
Jumlah Upah Tenaga 260,885.50
Jumlah Total 1,939,635.50
Total termasuk keuntungan 1,939,635.50
![Page 29: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/29.jpg)
29
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
23.
Harga bahan:
- Bata merah bh 441 1,200 529,200.00
- Semen portland kg 126.17 1,140 143,833.80
- Pasir pasang m³ 0.439 140,000 61,460.00
- Batu pecah/split 2/3 m³ 0.13 280,000 36,400.00
- Besi beton polos kg 11.44 7,800 89,232.00
- Kawat beton kg 0.164 12,000 1,968.00
- Pasir beton m³ 0.093 140,000 13,020.00
- Pasir urug m³ 0.106 120,000 12,720.00
- Kayu Terentang balok m³ 0.007 2,300,000 16,100.00
- Triplek 4x8 ft 9 mm lbr 0.675 115,000 77,625.00
- Paku biasa 2"-5" kg 0.71 82,000 58,220.00
- Pipa PVC dia 2" D m' 1 15,000 15,000.00
- Pipa PVC dia 4" D m' 1.7 18,000 30,600.00
- Perlengkapan (35% harga pipa) % 35 6,300.00
Jumlah Harga Bahan 1,091,678.80
Upah tenaga:
- Pekerja Oh 5.44 35,000 190,400.00
- Tukang batu Oh 2.181 55,000 119,955.00
- Tukang pasang pipa Oh 0.32 55,000 17,600.00
- Kepala tukang Oh 0.25 60,000 15,000.00
- Mandor Oh 0.3055 55,000 16,802.50
Jumlah Upah Tenaga 359,757.50
Jumlah Total 1,451,436.30
Total termasuk keuntungan 1,451,436.30
Membuat 1 unit tanki septik sederhana kapasitas Ø 1,2 m dalam 1,2 m
![Page 30: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/30.jpg)
30
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
25.
Harga bahan:
- Batu pecah/split 3/5 m³ 0.603 280,000 168,840.00
- Ijuk kg 0.716 10,000 7,160.00
- Pipa PVC dia 4" D m' 2 18,000 36,000.00
Jumlah Harga Bahan 212,000.00
Upah tenaga:
- Pekerja Oh 1.05 35,000 36,750.00
- Tukang pasang pipa Oh 0.27 55,000 14,850.00
- Kepala tukang Oh 0.027 60,000 1,620.00
- Mandor Oh 0.0969 55,000 5,329.50
Jumlah Upah Tenaga 58,549.50
Jumlah Total 270,549.50
Total termasuk keuntungan 270,549.50
Membuat 1 unit resapan Ø 0,8 m (digali 1 m) dalam 1 m (digali 1,9 m) kap. 0,5 m³
![Page 31: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/31.jpg)
31
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
2. Pasang Rangka Atap Baja tiap kg
Harga bahan:
- Besi baja WF kg 1.1 15,000 16,500.00
Jumlah Harga Bahan 16,500.00
Upah tenaga:
- Pekerja Oh 0.042 35,000 1,470.00
- Tukang las Oh 0.03 55,000 1,650.00
- Kepala tukang Oh 0.0045 60,000 270.00
- Mandor Oh 0.003 55,000 165.00
Jumlah Upah Tenaga 3,555.00
Jumlah Total per Kg 20,055.00
Jumlah Total Per M2 140,385.00
Total termasuk keuntungan 140,385
![Page 32: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/32.jpg)
32
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
O PEKERJAAN PENUTUP LANTAI DAN DINDING
1. Pasang lantai Granito ukuran 60 x 60 cm tiap 1m²
Harga bahan:
- Granito tile 60x60 cm bh 6.63 20,000 132,600.00
- Semen portland kg 9.8 1,140 11,172.00
- Pasir pasang m³ 0.045 140,000 6,300.00
- Semen warna kg 1.3 1,300 1,690.00
Jumlah Harga Bahan 151,762.00
Upah tenaga:
- Pekerja Oh 0.25 35,000 8,750.00
- Tukang batu Oh 0.12 55,000 6,600.00
- Kepala tukang Oh 0.012 60,000 720.00
- Mandor Oh 0.013 55,000 715.00
Jumlah Upah Tenaga 16,785.00
Jumlah Total 168,547.00
Total termasuk keuntungan 168,547.00
![Page 33: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/33.jpg)
33
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
3. Pasang lantai keramik ukuran 30 x 30 cm Roman tiap 1m²
Harga bahan:
- Ubin keramik 30 x 30 cm Roman bh 11.87 9,000 106,830.00
- Semen portland kg 10 1,140 11,400.00
- Pasir pasang m³ 0.045 140,000 6,300.00
- Semen warna kg 1.5 1,300 1,950.00
Jumlah Harga Bahan 126,480.00
Upah tenaga:
- Pekerja Oh 0.62 35,000 21,700.00
- Tukang batu Oh 0.35 55,000 19,250.00
- Kepala tukang Oh 0.035 60,000 2,100.00
- Mandor Oh 0.03 55,000 1,650.00
Jumlah Upah Tenaga 44,700.00
Jumlah Total 171,180.00
Total termasuk keuntungan 171,180.00
4. Pasang lantai keramik ukuran 20 x 20 cm Roman tiap 1m²
Harga bahan:
- Ubin keramik 20 x 20 cm Roman bh 26.5 2,050 54,325.00
- Semen portland kg 10.4 1,140 11,856.00
- Pasir pasang m³ 0.045 140,000 6,300.00
- Semen warna kg 1.62 1,300 2,106.00
Jumlah Harga Bahan 74,587.00
Upah tenaga:
- Pekerja Oh 0.62 35,000 21,700.00
- Tukang batu Oh 0.35 55,000 19,250.00
- Kepala tukang Oh 0.035 60,000 2,100.00
- Mandor Oh 0.03 55,000 1,650.00
Jumlah Upah Tenaga 44,700.00
Jumlah Total 119,287.00
Total termasuk keuntungan 119,287.00
5. Pasang dinding keramik 20 x 25 cm Roman tiap 1m²
Harga bahan:
- Ubin keramik 20 x 25 cm Roman bh 21.2 3,500 74,200.00
- Semen portland kg 9.3 1,140 10,602.00
- Pasir pasang m³ 0.018 140,000 2,520.00
- Semen warna kg 1.94 1,300 2,522.00
Jumlah Harga Bahan 89,844.00
Upah tenaga:
- Pekerja Oh 0.6 35,000 21,000.00
- Tukang batu Oh 0.45 55,000 24,750.00
- Kepala tukang Oh 0.045 60,000 2,700.00
- Mandor Oh 0.03 55,000 1,650.00
Jumlah Upah Tenaga 50,100.00
Jumlah Total 139,944.00
Total termasuk keuntungan 139,944.00
![Page 34: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/34.jpg)
34
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
P PEKERJAAN PENGECATAN
1. Pengecatan bidang kayu baru dg plamir 1 m² + 1 lps dsr + 2 lps penutup KW 2
Harga bahan:
- Cat meni kayu kg 0.2 11,500 2,300.00
- Plamir kayu kg 0.15 25,300 3,795.00
- Cat kayu/besi KW 2 (cat dasar) kg 0.17 15,000 2,550.00
- Cat kayu/besi KW 2 (cat penutup) kg 0.26 17,000 4,420.00
Jumlah Harga Bahan 13,065.00
Upah tenaga:
- Pekerja Oh 0.07 35,000 2,450.00
- Tukang cat Oh 0.09 55,000 4,950.00
- Kepala tukang Oh 0.006 60,000 360.00
- Mandor Oh 0.0025 55,000 137.50
Jumlah Upah Tenaga 7,897.50
Jumlah Total 20,962.50
Total termasuk keuntungan 20,962.50
2. Pengecatan tembok baru dg plamir 1 m² + 1 lps dsr + 2 lps Catylac
Harga bahan:
- Plamir tembok kg 0.1 25,300 2,530.00
- Cat tembok Catylac (cat dasar) kg 0.1 11,500 1,150.00
- Cat tembok Catylac (cat penutup) kg 0.26 12,000 3,120.00
Jumlah Harga Bahan 6,800.00
Upah tenaga:
- Pekerja Oh 0.02 35,000 700.00
- Tukang cat Oh 0.063 55,000 3,465.00
- Kepala tukang Oh 0.0063 60,000 378.00
- Mandor Oh 0.0025 55,000 137.50
Jumlah Upah Tenaga 4,680.50
Jumlah Total 11,480.50
Total termasuk keuntungan 11,480.50
3. Pengecatan tembok baru dg wall sealer 1 m² + 1 lps dsr + 2 lps Dulux/ICI
Harga bahan:
- Wall sealer Dulux/ICI kg 0.1 7,500 750.00
- Cat tembok Dulux/ICI (cat dasar) kg 0.1 17,500 1,750.00
- Cat tembok Dulux/ICI (cat penutup) kg 0.26 17,500 4,550.00
Jumlah Harga Bahan 7,050.00
Upah tenaga:
- Pekerja Oh 0.02 35,000 700.00
- Tukang cat Oh 0.063 55,000 3,465.00
- Kepala tukang Oh 0.0063 60,000 378.00
- Mandor Oh 0.0025 55,000 137.50
Jumlah Upah Tenaga 4,680.50
Jumlah Total 11,730.50
Total termasuk keuntungan 11,730.50
4. Pengecatan tembok baru dg wall sealer 1 m² + 1 lps dsr + 2 lps Dulux/ICI Weathershield
Harga bahan:
- Wall sealer Dulux/ICI kg 0.1 7,500 750.00
- Cat tembok Dulux/ICI Weathershield kg 0.36 18,000 6,480.00
Jumlah Harga Bahan 7,230.00
Upah tenaga:
- Pekerja Oh 0.02 35,000 700.00
- Tukang cat Oh 0.063 55,000 3,465.00
- Kepala tukang Oh 0.0063 60,000 378.00
- Mandor Oh 0.0025 55,000 137.50
Jumlah Upah Tenaga 4,680.50
Jumlah Total 11,910.50
Total termasuk keuntungan 11,910.50
![Page 35: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/35.jpg)
35
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
5. Pengecatan waterproofing (coating) tiap 1 m²
Harga bahan:
- Cumoir Waterproofing Coating kg 0.3 45,000 13,500.00
Jumlah Harga Bahan 13,500.00
Upah tenaga:
- Pekerja Oh 0.02 35,000 700.00
- Tukang cat Oh 0.063 55,000 3,465.00
- Kepala tukang Oh 0.0063 60,000 378.00
- Mandor Oh 0.0025 55,000 137.50
Jumlah Upah Tenaga 4,680.50
Jumlah Total 18,180.50
Total termasuk keuntungan 18,180.50
![Page 36: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/36.jpg)
36
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
6.
VIBRATING ROLLER 6-8 TON
Kecepatan alat v 4 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 1.2 m'
Banyak lintasan (pass) n 6 lintasan 3 kali bolak-balik
Tebal lapis hamparan t 0.2 m'
Kap. prod / jam = (v x 1000) x b x t x Fa Qj 132.8
n
Qt 0.0076 jam
WATER TANK TRUCK 3000-4500 L
Volume tangki air V 4
Efisiensi alat Fa 0.83
Wc 0.07
Pengisian tangki / jam n 3 kali
Kap. prod / jam = V x n x Fa Qj 142.285714286
Wc
Qt 0.0071 jam
Harga bahan:
- Tanah merah m³ 1.2 20,000 24,000.00
Jumlah Harga Bahan 24,000.00
Harga pemakaian alat:
- VIBRATING ROLLER 6-8 TON jam 0.0076 300,000 2,280.00
- WATER TANK TRUCK 3000-4500 L jam 0.0071 120,000 852.00
Jumlah Harga Peralatan 3,132.00
Upah tenaga:
- Pekerja Oh 0.25 35,000 8,750.00
- Mandor Oh 0.025 55,000 1,375.00
Jumlah Upah Tenaga 10,125.00
Jumlah Total 37,257.00
Total termasuk keuntungan 37,257
Urugan tanah merah dipadatkan alat berat tiap 1m³
m³/jam
Koefisien Alat / m³ = 1 : Qj
m³
Kebutuhan air / m³ material padat m³
m³/jam
Koefisien Alat / m³ = 1 : Qj
![Page 37: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/37.jpg)
37
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
4.
VIBRATING ROLLER 6-8 TON
Kecepatan alat v 2.5 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 1.2 m'
Banyak lintasan (pass) n 8 lintasan 4 kali bolak-balik
Kap. prod / jam = (v x 1000) x b x Fa Qj 311.25
n
Qt 0.0033 jam
WATER TANK TRUCK 3000-4500 L
Volume tangki air V 4
Efisiensi alat Fa 0.83
Wc 0.07
Pengisian tangki / jam n 3 kali
Kap. prod / jam = V x n x Fa Qj 142.285714286
Wc
Qt 0.0071 jam
Harga pemakaian alat:
- VIBRATING ROLLER 6-8 TON jam 0.0033 300,000.000000 990.00
- WATER TANK TRUCK 3000-4500 L jam 0.0071 120,000.000000 852.00
Jumlah Harga Peralatan 1,842.00
Upah tenaga:
- Pekerja Oh 0.025 35,000.000000 875.00
- Mandor Oh 0.0004 55,000.000000 22.00
Jumlah Upah Tenaga 897.00
Jumlah Total 2,739.00
Total termasuk keuntungan 2,739
Penyiapan badan jalan / tanah dasar (Subgrade) tiap 1m²
m²/jam
Koefisien Alat / m² = 1 : Qj
m³
Kebutuhan air / m² tanah m³
m²/jam
Koefisien Alat / m² = 1 : Qj
![Page 38: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/38.jpg)
38
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
5.
VIBRATING ROLLER 6-8 TON
Kecepatan alat v 2.5 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 1.2 m'
Banyak lintasan (pass) n 8 lintasan 4 kali bolak-balik
Tebal lapis hamparan t 0.15 m'
Kap. prod / jam = (v x 1000) x b x t x Fa Qj 46.6875
n
Qt 0.0215 jam
WATER TANK TRUCK 3000-4500 L
Volume tangki air V 4
Efisiensi alat Fa 0.83
Wc 0.07
Pengisian tangki / jam n 3 kali
Kap. prod / jam = V x n x Fa Qj 142.285714286
Wc
Qt 0.0071 jam
Harga bahan:
- Sirtu m³ 1.2 85,000 102,000.00
Jumlah Harga Bahan 102,000.00
Harga pemakaian alat:
- VIBRATING ROLLER 6-8 TON jam 0.0215 300,000 6,450.00
- WATER TANK TRUCK 3000-4500 L jam 0.0071 120,000 852.00
Jumlah Harga Peralatan 7,302.00
Upah tenaga:
- Pekerja Oh 0.25 35,000 8,750.00
- Mandor Oh 0.025 55,000 1,375.00
Jumlah Upah Tenaga 10,125.00
Jumlah Total 119,427.00
Total termasuk keuntungan 119,427
Urugan sirtu (agregat kelas C) dipadatkan tiap 1m³
m³/jam
Koefisien Alat / m³ = 1 : Qj
m³
Kebutuhan air / m³ material padat m³
m³/jam
Koefisien Alat / m³ = 1 : Qj
![Page 39: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/39.jpg)
39
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
6.
THREE WHEEL ROLLER 8-10 TON
Kecepatan alat v 3 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 1.2 m'
Banyak lintasan (pass) n 8 lintasan 4 kali bolak-balik
Tebal lapis hamparan t 0.1 m' 6 lintasan u/ agregat kasar;
2 lintasan u/ agregat halus.
Kap. prod / jam = (v x 1000) x b x t x Fa Qj 37.35
n
Qt 0.0268 jam
WATER TANK TRUCK 3000-4500 L
Volume tangki air V 4
Efisiensi alat Fa 0.83
Wc 0.07
Pengisian tangki / jam n 1 kali
Kap. prod / jam = V x n x Fa Qj 47.4285714286
Wc
Qt 0.0211 jam
Harga bahan:
- Batu pecah 5/7 m³ 0.935 280,000 261,800.00
- Pasir urug m³ 0.165 120,000 19,800.00
Jumlah Harga Bahan 281,600.00
Harga pemakaian alat:
- THREE WHEEL ROLLER 8-10 TON jam 0.0268 130,000 3,484.00
- WATER TANK TRUCK 3000-4500 L jam 0.0211 120,000 2,532.00
Jumlah Harga Peralatan 6,016.00
Upah tenaga:
- Pekerja Oh 1 35,000 35,000.00
- Mandor Oh 0.034 55,000 1,870.00
Jumlah Upah Tenaga 36,870.00
Jumlah Total 324,486.00
Total termasuk keuntungan 324,486
Lapis Pondasi Jalan Tanpa Penutup Aspal jenis Waterbound Macadam tiap 1m³
m³/jam
Koefisien Alat / m³ = 1 : Qj
m³
Kebutuhan air / m² material padat m³
m³/jam
Koefisien Alat / m³ = 1 : Qj
![Page 40: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/40.jpg)
40
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
7. Pekerjaan paving jalan setapak (warna abu T-16 uk. 8x10,5x21) + urugan sirtu 10 cm + urugan pasir 5 cm tiap m²
TAMPER / HAND COMPACTOR
Kecepatan alat v 0.5 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 0.25 m'
Banyak lintasan (pass) n 14 lintasan 7 kali bolak-balik
Kap. prod / jam = (v x 1000) x b x Fa Qj 7.41071428571
n
Qt 0.135 jam
PLATE COMPACTOR
Kecepatan alat v 0.5 km/jam
Efisiensi alat Fa 0.83
Lebar pemadatan b 0.43 m'
Banyak lintasan (pass) n 6 lintasan 3 kali bolak-balik
Kap. prod / jam = (v x 1000) x b x Fa Qj 29.7416666667
n
Qt 0.0337 jam
Harga bahan:
- Sirtu m³ 0.12 85,000 10,200.00
- Pasir urug m³ 0.06 120,000 7,200.00
- Paving abu-abu segi enam, tebal 8 cm m² 1.05 72,000 75,600.00
- Abu batu 0.018 280,000 5,040.00
Jumlah Harga Bahan 98,040.00
Harga pemakaian alat:
- TAMPER / HAND COMPACTOR jam 0.135 30,000 4,050.00
- PLATE COMPACTOR jam 0.0337 51,000 1,718.70
Jumlah Harga Peralatan 5,768.70
Upah tenaga:
- Pekerja Oh 0.1875 35,000 6,562.50
- Tukang batu Oh 0.12 55,000 6,600.00
- Kepala tukang Oh 0.012 60,000 720.00
- Mandor Oh 0.01375 55,000 756.25
Jumlah Upah Tenaga 14,638.75
Jumlah Total 118,447.45
Total termasuk keuntungan 118,447
m²/jam
Koefisien Alat / m² = 1 : Qj
m²/jam
Koefisien Alat / m² = 1 : Qj
m³
![Page 41: Analisa Harga Satuan Gedung 2010](https://reader034.fdocument.pub/reader034/viewer/2022050700/55cf903d550346703ba4375b/html5/thumbnails/41.jpg)
41
NO. URAIAN SAT KUANTI TAS SUB TOTAL (Rp) HSP (Rp)
1 2 3 4 5 6 7
HARGA SAT. DASAR (Rp)
8. Pekerjaan kanstin tiap 1 m'
Harga bahan:
- Kayu Meranti Palembang papan m³ 0.0007 4,050,000 2,835.00
- Kayu Meranti Palembang kaso m³ 0.0012 4,000,000 4,800.00
- Paku biasa 2"-5" kg 0.002 13,000 26.00
- Pasir urug m³ 0.015 120,000 1,800.00
- Kanstin abu-abu 15 x 25 x 40 bh 2.625 5,500 14,437.50
- Semen portland kg 7.075 1,140 8,065.50
- Pasir pasang m³ 0.0195 140,000 2,730.00
Jumlah Harga Bahan 34,694.00
Upah tenaga:
- Pekerja Oh 0.076 35,000 2,660.00
- Tukang batu Oh 0.0225 55,000 1,237.50
- Kepala tukang Oh 0.00225 60,000 135.00
- Mandor Oh 0.005 55,000 275.00
Jumlah Upah Tenaga 4,307.50
Jumlah Total 39,001.50
Total termasuk keuntungan 39,002
9. List Plafon Gypsum tinggi 8 cm, tiap 1m'
Harga bahan:
- List Gypsum tinggi 8 cm m' 1.1 8,000 8,800.00
- Compound gypsum zak 0.025 50,000 1,250.00
- Sekrup gypsum bh 4 1,200 4,800.00
- Amplas lbr 0.2 1,500 300.00
Jumlah Harga Bahan 15,150.00
Upah tenaga:
- Pekerja Oh 0.05 35,000 1,750.00
- Tukang kayu Oh 0.05 55,000 2,750.00
- Kepala tukang Oh 0.005 60,000 300.00
- Mandor Oh 0.003 55,000 165.00
Jumlah Upah Tenaga 4,965.00
Jumlah Total 20,115.00
Total termasuk keuntungan 20,115