TRIC Training Log: 09-23-04
Client: Plumbing MD, Davis, CA
Job: Residence, house to city cleanout in service alley
Pull: 65’ / upstream / 4” SDR17 / bursting 4” VCP & AC
2004-0923CA
technical archives
www.trictrenchless.com
We at TRIC Tools have specific requirements for the use and maintenance of our equipment with regard to safety and efficiency on the job. Our written and verbal recommendations coincide with safety regulations set by local, state, and national government agencies. Our
clients may have standards over and above industry regulations. However, the safety equipment, apparel, and operating procedures
demonstrated by our clients in this presentation may or may not comply with above mentioned government regulations.
2004-0923CA
technical archives
www.trictrenchless.com
Facing pipe surfaces: Place pipe in jig, and leave about 1” of pipe extending beyond clamps (loosely closed). Align pipe sections, using wood blocks or other solid objects to support and adjust pipe with relation
to jig. Tighten clamps, bring ends together, and recheck alignment from all angles before inserting facer. Apply slow, even leverage and watch for full “ribbons” of shaved material.
2004-0923CA
technical archives
www.trictrenchless.com
Trim & Check: Continue facing until trimmer stops in jig. Remove all shavings. This will leave about 1/2” of pipe protruding from clamps. Remove facer, bring pipe ends together, and check
alignment again before heating. Be careful not to touch faced surfaces.
2004-0923CA
technical archives
www.trictrenchless.com
Heating: Keep iron set at 450º F. To adjust, unplug iron and turn set screw (near handle, opposite gauge) clockwise to reduce temperature and counterclockwise to increase temperature (1/4 turn at a time). Bring pipe
surfaces to meet iron and make complete contact, but use no pressure while heating.
2004-0923CA
technical archives
www.trictrenchless.com
The melt: Watch for about 1/8” of melt-back from iron surfaces. Again, no pressure should be applied during melt. The plastic needs to “soak up” the heat thoroughly and evenly in the fusion surface areas. Any pressure applied while heating dissipates the weld material before surfaces can be joined together
and also heats unevenly, resulting in a “cold joint” that is subject to failure.
2004-0923CA
technical archives
www.trictrenchless.com
The joint: Remove heater and bring pipe ends together, using steady and even force until melted material rolls back to form a complete rounded “bead” on either side of the joint. Leave pipe undisturbed until just warm,
or about 8–10 minutes for 4” SDR17. (Manufacturer’s cooling times vary for each size of pipe, and facing pressures vary for individual fusion machines. Consult respective literature.)
2004-0923CA
technical archives
www.trictrenchless.com
Entry: Property line, from service alley. Sewer runs next to large tree just upstream from property line cleanout, and one large root (4”–5” diameter) wraps over top of lateral. Single large roots touching existing sewer may not seriously impede bursting head, but they can cause bellies
in line as flexible pipe is pushed aside by relatively immobile root.
2004-0923CA
technical archives
www.trictrenchless.com
Preparation: Since root is readily accessible, it is worth the time and trouble to eliminate it before beginning. For most pulls, the majority of the work is setup.
2004-0923CA
technical archives
www.trictrenchless.com
Almost ready: An extra 8”–10” of relatively open digging and cutting assures an unobstructed entry and as even a grade as possible.
2004-0923CA
technical archives
www.trictrenchless.com
Holes 1 and 2: Pipe is fused and readied while tie-in points are exposed. At lower right is a 4” tie-in from garage/laundry across driveway. Once located, tie-in points can be burst before
excavation, if job logistics or timing demands it.
2004-0923CA
technical archives
www.trictrenchless.com
Holes 3 and 4: A 2” tie-in is exposed near tree at top of driveway (just behind leaf pile). Pulling pit is further upstream, about 10’–15’ downstream from front door at top of image.
2004-0923CA
technical archives
www.trictrenchless.com
Ready for the cable: In many cases, where laterals are relatively short and straight, the pulling cable can be fed right through the line by hand. More difficult laterals (with steep uphill
feed, offsets, bends, root blocks, etc.) require using the duct rodder to pilot the distance first, and then the cable can be taped to the rodder and drawn through the sewer.
2004-0923CA
technical archives
www.trictrenchless.com
Entry: Guide the bursting head into the line to assure the easiest and most direct entry. This may require flexing or bowing the PE pipe to get it in line with the existing sewer. After 4 or 5 feet of travel, the PE pipe will have taken its path and may not need further assistance, other than to
keep it clear of pedestrian and/or vehicular traffic.
2004-0923CA
technical archives
www.trictrenchless.com
From the top: Operator should have clear vision of pressure gauge and exiting cable at all times. Pipe entering at other end of pull should also be monitored periodically. Note another 4”
tie-in just behind ram at lower left.
2004-0923CA
technical archives
www.trictrenchless.com
Hole #2: Tie-in at base of driveway. Lateral and connecting spur are vitreous clay at this point.
2004-0923CA
technical archives
www.trictrenchless.com
Hole #3: 2” ABS connection from main building. Lateral is asbestos concrete at this point.
2004-0923CA
technical archives
www.trictrenchless.com
Traffic control: Keeping pipe clear of existing cleanout stack, and watching the alley at the same time.
2004-0923CA
technical archives
www.trictrenchless.com
Ideal vantage point: During a pull, the operator should stay out of the pulling pit while the cable is under tension. Also, the clearest perspective of the cable’s travel through the pulley base
is from above as shown.
2004-0923CA
technical archives
www.trictrenchless.com
Steady progress: Bursting head is approaching hole #3.
2004-0923CA
technical archives
www.trictrenchless.com
Back at Hole #1: The tree providing all this shade will be undamaged by this trenchless job. (It will also get no further irrigation from the new sewer!)
2004-0923CA
technical archives
www.trictrenchless.com
Hole #3: Asbestos pipe section is pushed upstream and into open pit. This happens more frequently with ABS and PVC plastic lines in softer ground. The blade on the bursting head is
needed to split plastic pipe (and to cut bands and couplings).
2004-0923CA
technical archives
www.trictrenchless.com
Bursting revealed: Hardened steel head with blade usually wins the argument. Plastic pipe can be far more stubborn, and may need to be broken by hand if it folds and collects around
bursting head as it enters an open pit (or as it approaches the pulley base).
2004-0923CA
technical archives
www.trictrenchless.com
Home stretch: Watching hole #3.
2004-0923CA
technical archives
www.trictrenchless.com
Final inches: Watching the cable as it crosses the threshold of the resistance plate and pulley base.
2004-0923CA
technical archives
www.trictrenchless.com
Clear view: Keep the pulley area free of bursting debris, which is especially prevalent towards the end of a pull, and which often immediately precedes the clevis.
2004-0923CA
technical archives
www.trictrenchless.com
End of the line: When clevis sheath is just visible inside pulley housing, it’s time to stop. If sheath is brought under pulley wheel, it will be bent and require new termination. Now it’s time to
detension the cable and remove the resistance plate and use the extender cage.
2004-0923CA
technical archives
www.trictrenchless.com
Extender cage: Release the ram, and remove the resistance plate from pit. Extender cage (at right) is positioned against pulling wall, straddling cable. Pulley base fits into recessed end of cage to allow an extra 18”–24” of pull, to expose bursting head. (Note that some pulling pits are too small to
accommodate the cage, and wood cribbing must be used instead.)
2004-0923CA
technical archives
www.trictrenchless.com
On call: Plumbing MD has added a new trenchless service to its specialized fleet.