•Sittwe Ch. 0.0 km
Paletwa Ch. 158 Km
Kaletwa (Ch 225 km
Myeikwa (IM Border)
•Kyauktaw
•Bay of Bengal
Kolkata Sittwe 539 km
Sittwe Paletwa 158 km
Paletwa Kaletwa 67 km
Kaletwa Myeikwa (IM Border) 62 km
Myeikwa (IM Border) Lawngtlai 100 km
Lawngtlai Aizawl 334 km
•Aizawl
•Lawngtlai
•NH
54
•B A N G L A D E S H•I N D I A
•Myanmar
•I N D I A
•Kaladan R
.
Kaladan Multimodal Transit Transport Project
I W T
• RO
AD
IN IN
DIA
RO
AD
IN
M
YA
NM
AR
DISTANCES
3
Project Components …post review
Fairway development / Sea-dredging in Sittwe port area
Construction of Port / IWT terminals at Sittwe
Fairway development / Dredging on Sittwe – Paletwa stretch of Kaladan river (158 Km)
Construction of IWT Terminal at Paletwa
Construction of 6 IWT vessels (300 ton each)
Highway (129 kms) from Paletwa to Indo-Myanmar Border.
77
Progress made
• MEA issued Letter of Acceptance(LoA) to Essar Projects India Ltd. in April 2010 at a cost of Rs. 342 Crores (Approx US $ 75 millions) for the Port & IWT works.
• Agreement between MEA and Contractor signed in May 2010.
• Port & IWT works to be implemented in 36 months.
88
Govt. of Myanmar has provided land for Construction & Setting up of Contractor’s camp at Sittwe during Sep 2010. Permissions for import of Construction equipments & Opening of bank account in Oct 2010.
Progress made… contd.
9
Progress made… contd.
Ground breaking ceremony attended by Senior dignitaries from both countries held on 19th December 2010 at Sittwe.
1010
Progress made… contd.
• Construction activity at Sittwe started in Dec 2010.
• Consequent to relocation of terminal to Paletwa, preparation of DPR for New road section between Paletwa and Kaletwa has become necessary.
• MEA has appointed M/s IRCON Infrastructure & Services Ltd. New Delhi as the agency for preparing the D.P.R. for the new road section.
• Design and model testing of 300 DWT Barges has been completed. Selection of Yard is in final stage. Barges are to be built in Myanmar.
1111
Progress made… contd.
• Reclamation for backup facilities at Sittwe 96% completed, Construction of Rubble mounted Dyke 70% Completed.
• Construction of Pile work at IWT & Port Approach Jetty at Sittwe 98% completed. Main Jetty piling work shall commence shortly.
• Pre-cast concrete works for IWT & Port Jetty at Sittwe 50% completed.
• Excavation work at Paletwa 15% completed.
1818
Progress made… contd.
• Hydrographic Survey at Sittwe Port and also in between Sittwe – Paletwa stretch was completed on 2.11.2009 and 20.2.2012 respectively by IWAI with the assistance from the local Survey agency.
• 6 Nos of Shallow area for dredging in Kaladan river was identified. 5 Nos of Shallow area was indicated in DPR (2002).
• The Location of Navigational Aids, Positions of submerged Rocks and Dredging alignment are to be demarcated as per the new Survey charts.
2323
Important Points / issues
• Approval of General layout drawings for backup facilities was submitted to Working Committee, Govt. of Myanmar :-
on 3.11.2011 for Sittwe.
on 9.11.2011 for Paletwa
Approvals are yet to be received.
2424
Important Points / issues
• M/s. Essar Projects has already expressed that they can complete the work within the scheduled time by mobilising additional resources subject to the receipt of above approvals without further delay.
• Otherwise project may get delayed by another 6 more working months.