Terminal 2 Pier A Expansion Project Site
Oct-11: Pre-Contract Apron Works by SACL- Ford Civil Contracting undertook Apron enabling
works, directly for SACL.- Fuel lines, stormwater drainage and aviation
lighting- Gate Hardstands concrete aprons slabs- Taxiway AC pavements
Apr-12: Site Establishment- Piling Complete- Footings and Lift base under construction- Operational airport facilities entirely envelope the
project site.
Jul-12: Super-Structure Underway- Partial Demolition of the Southern Terminal
Structure complete- Post-tensioned concrete structure under way,
Level 2 Poured- Tower Crane positioned within building to
minimise slew radius over operational gates.
Aug-12: Final Slab Pour - Mobile pump setup for daytime concrete pour of
stair Core.- Note the cleanliness of compound to prevent
debris on the taxiways
Sep-12: Super-Structure Nearing Completion- Cores and columns extending above the uppermost
storey- Temporary perimeter waterproofing has permitted
early commencement of internal fit-out.
Oct-12: Roof Steelwork and Roofing - 100T of Roof Steelwork installed in 12 days- Roofing to Plant rooms advanced- Cooling Towers installed
Nov-12: Aerobridge Installation- Aircraft Boarding Bridges being clad on site prior
to lifting.- Aerobridges delivered and stored within lift radius
of mobile cranes, tandem lift required.
Dec-12: Four Gates and Bus Terminal Operational- December 12 Interim Occupation achieved and Separable
Potion 1 Practical Completion granted.- Virgin commissioning complete and facilities fully
functional.- Busy with Christmas holiday passengers volumes
Jul-13: Works Complete - Terminal 2 Pier A works complete and fully utilised.