Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Terrell PlaceWashington D.C.
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Project Overview
� An 11 Story cast-in-place concrete office building � Location: 575 7th St NW
Washington D.C.� Function:
� Office Building� Retail space on 1st floor� Parking garage
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Project Overview
� Size: 439,390 sq ft� Construction Date:
� Started in Aug of 2001� Finish in Oct of 2003
� Cost: $48.5 million
Existing Hecht’sBuilding
New WestBuilding
ExistingGang of Four
New BuildingNot in project
Existing AARP
Existing Building
Future Residential
Terrell Place
MCI Center
NRC
Firehouse
F street, NW
E Street, NW
7th street, NW
6th street, NW
N
Terrell Place - Site Plan
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Project OverviewProject Team
� Owner: Carr America Urban Development LLC� GC: Clark Construction Groups� Architect/Engineer: SmithGroup� Mechanical Contractor: Pierce Associates, Inc.� Electrical Contractor: Truland Systems Corp.
Interesting FactNamed the Best Office Lease/Urban for 2001 in the Washington Business Journal’s Annual Best Real Estate Deals of the years awards with the largest law firm in Washington D.C.
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Presentation Outline
� Site Logistic� Studies of Historical Renovation� Possibilities of Using other Horizontal
Formwork� Redesign the Foundation System� Research: Mold Issues in construction
industry
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Site Logistic
Current Problem� Only one site plan developed
� Relatively congested site and narrow access road
Proposed Solution� Three phase site plans
� Clearly show the location of the equipments and access during different phases
� Create one way traffic flow
ExistingAARP BuildingExisting Restaurant
(5 story)
Future Residential(under construction)
Existing 5-story
building
Existing Site Plan
Sheeting/Shoring
Façade Support
Existing Hecht’s Building
(1 Basement)
Existing Gang of Four(to be demolished)
New West Building4 Basements
Sheeting/Shoring
Staging Area Curb Lane
Construction Safety Fence
Trash Chute & Dumpster
MaterialHoist
Entrance
ExcavationRamp
ConstructionTrailer
Temporary Access Road for
DemolitionDebris Removal
Construction Safety Fence
Temporary Pedestrian Sidewalk
Crane #1
Crane #2
ExistingAARP BuildingExisting Restaurant
(5 story)
Future Residential(under construction)
Existing 5-story
building
Demolition/Excavation Phase
Façade Support
Existing Hecht’s Building
(1 Basement)
Existing Gang of Four(to be demolished)
New West Building4 Basements
Sheeting/Shoring
Staging Area Curb Lane
Construction Safety Fence
Trash Chute & Dumpster
MaterialHoist
Entrance
ExcavationRamp
ConstructionTrailer
Temporary Access Road for
DemolitionDebris Removal
Construction Safety Fence
Temporary Pedestrian Sidewalk
Sheeting/Shoring
ExcavationRamp
ExistingAARP BuildingExisting Restaurant
(5 story)
Future Residential(under construction)
Existing 5-story
building
Superstructure Phase
Sheeting/Shoring
Façade Support
Hecht’s Building
Gang of Four
New West Building
Sheeting/Shoring
Staging Area Curb Lane
Construction Safety Fence
Trash Chute & Dumpster
MaterialHoist
Entrance
ConstructionTrailer
Construction Safety Fence
Temporary Pedestrian Sidewalk
Concrete Pump
Crane #1
Crane #2
Staging Area
ExistingAARP BuildingExisting Restaurant
(5 story)
Future Residential(under construction)
Existing 5-story
building
Finishes Phase
Hecht’s Building
Gang of Four
New West Building
Curb Lane
Construction Safety Fence
Trash Chute & Dumpster
MaterialHoist
Entrance
ConstructionTrailer
Construction Safety Fence
Temporary Pedestrian Sidewalk
Mobile Crane
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Presentation Outline
� Site Logistic� Studies of Historical Renovation� Possibilities of Using other Horizontal Formwork� Redesign the Foundation System� Research: Mold Issues in construction industry
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Historical Preservation� Government of D.C. – Preservation law� 8 different types of windows on the façade and three different store front.
Study of the facade
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Study of the facade
Problem� Long installation time
� Reason for delay
Proposed Methods� Combining Precast and window supplier
� But…..some windows are 10 feet high and 800 pounds, difficult for handling and shipping
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Presentation Outline
� Site Logistic� Studies of Historical Renovation� Possibilities of Using other Horizontal
Formwork� Redesign the Foundation System� Research: Mold Issues in construction industry
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Possibility of Using other Horizontal Formwork
� Three options
� Compare the cost and schedule for all the options� Each floor of the New West Building: 19,200 SF� Each floor of the GOF building: 12,000 SF
PERI skydeck with customized design
Original structural design
PERI skydeckNew structural design
Scaffolds and plywoodOriginal structural design
Construction methodsStructural changes
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Original structural design using scaffolds and plywood (Option 1)
� Two way slab with drop panels� Original slab thickness: 8 in� Drop panels: 8 in� Plywood and aluma frames� Cost: $0.83 – $0.91 / sf
� Total cost of formwork and labor: $961,634
� Productivity rate:18-20 sf / mh� Duration of GOF: 104 days � Duration of West building: 164 days
Possibility of Using other Horizontal Formwork
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
New structural design using PERI skydeck (Option two)
� ADOSS program, determine slab thickness
Possibility of Using other Horizontal Formwork
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Possibility of Using other Horizontal Formwork
PERI skydeck� Cost: $1.10 -$1.50 / sf
� Total cost and labor: $954,126
� Productivity rate: 20-30 sf / mh� Duration of GOF: 65 days � Duration of West: 113 days
� Impact of changing the formwork
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Possibility of Using other Horizontal Formwork
Original Structure using PERI skydeck with customized formwork around the drop panels(option 3)
� Cost of the formwork: $1.39-$1.50 / sf� Total cost of formwork and labor: $1,128,574
� Productivity rate:18-20 sf / mh� Same as option 1
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Possibility of Using other Horizontal Formwork
Comparisons of the original method and the two other alternatives:
Most expensive, relative slower rateNo changes in
structural designGOF –102 daysWest – 164 days
18-20sf / mh
$1,281,574$1.39-1.50/ sf
3 - Original design with drop panels using customized PERI Skydeck
Less plenum space, changes of structural design
Cheapestfastest method among the three options
GOF –65 daysWest -113 days20-30
sf / mh$954,126
$1.10-1.50/ sf
2 - Flat slab using PERI Skydeck
Relative slower rateTraditional method
GOF –102 daysWest – 164 days
18-20sf / mh
$961,634$0.83-0.91/ sf
1 - Original design with drop panels using stick build method
DisadvantagesAdvantagesDurationProductivity RateTotal CostCostOption
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Presentation Outline
� Site Logistic� Studies of Historical Renovation� Possibilities of Using other Horizontal Formwork� Redesign the Foundation System� Research: Mold Issues in construction industry
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Analysis 4: Redesign the Foundation Systems
Problem� Spread Footings� Constructability issues:
� Difficult to construct the spread footings for this project due to the footings having different elevations adjacent to each other
� OSHA standard - sloping back around the excavation was necessary
Proposed System� Mat slab foundation
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Analysis 4: Redesign the Foundation Systems
121333861107375000 psi
123506841479394000 psi
122652771093423000 psi
CostConcrete Unit Cost
VolumeThickness of Foundation (in)
Gang of Four
352959864107505000 psi
367177844397534000 psi
357405774642573000 psi
CostConcrete Unit Cost
VolumeThickness of Foundation (in)
West Building
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Analysis 4: Redesign the Foundation Systems
Spread FootingsDisadvantages:
� More concrete is used for the GOF� Difficult excavation due to different elevations of the footings� Slow productivity during excavation, takes longer to excavate
Advantages:
� Less concrete is used for the West Building
� Less material (rebar, formwork)
� Allow to set rebar along the footings while formwork is being placed
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Analysis 4: Redesign the Foundation Systems
Mat SlabDisadvantages:� Need to set rebar on site because of the amount of rebar� Large amount of concrete and rebar� One continuous pour, longer hours for workers� Heavy traffic due to 30-40 trucks per hour move through the site
Advantages:� Better constructability� Reduce duration by 10
days � Comparable cost as spread
footings
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Presentation Outline
� Site Logistic� Studies of Historical Renovation� Possibilities of Using other Horizontal Formwork� Redesign the Foundation System� Research: Mold Issues in construction industry
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Research Topic:Mold Issues
Why are people looking into mold related problem in the construction industry?
� Litigation� Sickness related to mold
What is mold? What causes mold?
� A non-specific term of a type of fungus� Air borne� Moisture, food source, oxygen and warm temperature
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Research Topic:Mold Issues
Is Mold toxic?� Mold itself is not toxic� By products – mycotoxins will cause serious health
problem
Sickness Related to Mold� No medical evidence on mold in buildings lead to sickness � Allergic reactions
Studies of Court Cases� Property damage claims and personal injury claims� Pay millions of dollars
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Research Topic:Mold Issues
Lack of standards� No standards related to the level of mold exposure that is harmful to human� No inspection standards
What to do if mold if found?� Follow guidelines established by the EPA or AGC
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Research Topic:Mold Issues
What needs to be done related to this problem?� Need more development on medical field� Set up regulations and standards
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Conclusion
Site Logistic� Important to create one way traffic within the site� More detailed site plans provide better
understandingStudies of Historical Renovation
� Good concept to combine the window and precastpanels suppliers
� But difficult to implement due to the special condition
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
ConclusionPossibilities of Using other Horizontal Formwork
� Prefabricated formwork for slab would be the best choice in terms of time and cost
� More changes of other structural components to increase the plenum space was necessary
Resign the Foundation System� Mat slab foundation will shorten the schedule by 10 days� Large amount of material and intensive work
Research: Mold Issues in construction industry� More government involvement is needed to set up the
standards
Tracy LoConstruction Management
Senior Thesis PresentationApril 16, 2003
Thanks to
Clark Construction GroupTruland Systems Inc.
Dr. HormanDr. Messner
Dr. RileyAE faculty
Friends and FamilyDave