Rekapitulasi Hasil.docx

10
RQD RQD = 100 e -0.1λ (1 + 0.1λ) No Titik Pengamatan RQD (%) 1 TP-1 97.6 2 TP-2 99.1 3 TP-3 97.6 4 TP-4 99.1 5 TP-5 98.36 GSI GSI = 52 . ( Jr Ja ) 1 +( Jr Ja ) +RQD / 2 N o Titik Pengamat an GSI 1 TP-1 88 2 TP-2 80 3 TP-3 87 4 TP-4 88 5 TP-5 80

Transcript of Rekapitulasi Hasil.docx

RQDRQD = 100 e-0.1 (1 + 0.1)

NoTitik PengamatanRQD (%)

1TP-197.6

2TP-299.1

3TP-397.6

4TP-499.1

5TP-598.36

GSIGSI = NoTitik PengamatanGSI

1TP-188

2TP-280

3TP-387

4TP-488

5TP-580

SIFAT FISIK & MEKANIKNoTitik PengamatanBatuanUnit Weight (MN/m3)Cohesion (MPa)Friction Angle (0)Tensile Strenght (MPa)Uniaxial Compressive Strenght (MPa)Modulus of Deformation (MPa)

1TP-1Claystone0.0181.9831.7-1.57.734518

2TP-2Claystone0.0182.3834.8-1.69.830800.7

3TP-3Limestone0.02656.846-3.536.472867

4TP-4Limestone0.02657.246-3.838.577184.6

5TP-5Shalestone0.02454.942.7-2.724.648700.2

Average =0.02274.640.2-2.623.452814.1

REKAPITULASIKlasifikasiHasilAverage

TP-1TP-2TP-3TP-4TP-5

RMR576576677768 (Good Rock)

Q-system1.460.790.21.20.60.8 (Very Poor Rock)

RSR445370535655

Total Displacement : No Support = 0.00122812 m RMR = 0.00122772 m Q-System = 0.00122732 m RSR = 0.00122782 mGambar. . Rekomendasi sistem penyanggaan metode RMR RMR Sebelum dipasang penyanggaSetelah dilakukan penyanggaan

Supporting : Rock-bolting Panjang 3 m dan spasi 2.5 m Shotcrete 50 mm

Q-SystemSebelum dipasang penyanggaSetelah dilakukan penyanggaan

Supporting : Rock-bolting Panjang 2.5 m dan spasi 1.6 m Shotcrete 120 mm

RSRSebelum dipasang penyanggaSetelah dilakukan penyanggaan

Supporting : Rock-bolting Panjang 1.2 m dan spasi 2 m Shotcrete 20 mm

Table. . Data Teknik Dari Grouted Cable Bolt-FlexiropeKualitas steel1770 N/mm2

Diameter kabel28 mm

Beban batas (Yield load) kabel500 kN

Beban ultimat (Ultimate load) kabel500 kN

Regangan axial ultimate kabel3 %

Berat kabel3,1 kg/m

Panjang kabelSesuai panjang yang dibutuhkan

Diameter lubang bor yang dianjurkan35 mm

Total Displacement : No Support = 0.00122812 m RMR = 0.00122772 m Q-System = 0.00122732 m RSR = 0.00122782 m

MetodaTotal Displacement

Sebelum disanggaSetelah dilakukan Penyanggaan

RMR0.00122812 m0.00122772 m

Q-System0.00122812 m0.00122732 m

RSR0.00122812 m0.00122782 m