S K P D : DINAS PU BINA MARGA KAB. MUSI BANYUASIN - APBD TA. 2014 KEGIATAN : ............................................................................................................................................... PEKERJAAN : ............................................................................................................................................... KECAMATAN : ............................................................................................................................................... KABUPATEN : ............................................................................................................................................... Jumlah Harga No. Divisi Uraian Pekerjaan (Rupiah) 1 Umum 41.516.000,00 2 Drainase - 3 Pekerjaan Tanah 60.291.333,05 4 Pelebaran Perkerasan dan Bahu Jalan - 5 Pekerasan Berbutir 167.642.311,10 6 Perkerasan Aspal 24.086.386,27 7 Struktur 577.391.305,80 8 Pengembalian Kondisi dan Pekerjaan Minor - 9 Pekerjaan Harian - 10 Pekerjaan Pemeliharaan Rutin - (A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 870.927.336,22 (B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 87.092.733,62 (C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B) 958.020.069,84 (D) JUMLAH DIBULATKAN 958.020.000,00 Terbilang : .............................................................................................................................. ............................................................ Nama Jelas / Jabatan KOP. PERUSAHAAN REKAPITULASI BILL OF QUANTITI ( BOQ ) ...................... , ............................. 20.. CV/PT, .............................................. File : BOQ BUKIT SELABU.xls

description

y

Transcript of Rekap Boq

  • S K P D : DINAS PU BINA MARGA KAB. MUSI BANYUASIN - APBD TA. 2014 KEGIATAN : ............................................................................................................................................... PEKERJAAN : ............................................................................................................................................... KECAMATAN : ............................................................................................................................................... KABUPATEN : ...............................................................................................................................................

    Jumlah HargaNo. Divisi Uraian Pekerjaan

    (Rupiah)1 Umum 41.516.000,00

    2 Drainase -

    3 Pekerjaan Tanah 60.291.333,05

    4 Pelebaran Perkerasan dan Bahu Jalan -

    5 Pekerasan Berbutir 167.642.311,10

    6 Perkerasan Aspal 24.086.386,27

    7 Struktur 577.391.305,80

    8 Pengembalian Kondisi dan Pekerjaan Minor -

    9 Pekerjaan Harian -

    10 Pekerjaan Pemeliharaan Rutin -

    (A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 870.927.336,22

    (B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 87.092.733,62

    (C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B) 958.020.069,84

    (D) JUMLAH DIBULATKAN 958.020.000,00

    Terbilang : ..............................................................................................................................

    ............................................................Nama Jelas / Jabatan

    KOP. PERUSAHAAN

    REKAPITULASIBILL OF QUANTITI ( BOQ )

    ...................... , ............................. 20..

    CV/PT, ..............................................

    File : BOQ BUKIT SELABU.xls