Railway Projects In Andhra pradesh : What is pending and What is Proposed
-
Upload
prof-knageshwar -
Category
News & Politics
-
view
18.708 -
download
9
Transcript of Railway Projects In Andhra pradesh : What is pending and What is Proposed
1
GOVERNMENT OF ANDHRA PRADESH
WELCOMES
Shri. DINESH TRIVEDIHon’ble Union Minister for Railways
Shri. K.H. MUNIYAPPAHon’ble Union Minister of State for Railways
&All Members of Parliament
2
STATUS OF
RAILWAY PROJECTS
3
Multi Modal Transport System
(MMTS) Hyderabad
4
Multi Model Transit System Ph-II- Hyderabad
Needs expansion and strengthening to ease suburban traffic in Hyderabad.
6 routes identified for implementation. Cost sharing: 2/3rd – Govt of Andhra
Pradesh. Abstract estimate at Rs. 641 Crores
( Yr. 2006) sent to Board.
5
MMTS Phase-II Routes Moula-ali ‘C’ cabin-Sanathnagar (21.85)Km) Moulali-Malkajgiri-Sitafalmandi ( 10 Km) Secunderabad-Bolarum-Medchal (28 Km) Falaknuma-Umdanagar-Shamshabad (20Km) Moulali ‘C’ cabin – Ghatkesar (12.2Km) Telapur – Patancheru (8.75 Km)
Doubling: 60 km; Third Line:12.2 Km; New Line:15.6Km No. of stations: 27 (Existing:18, New: 9)
Approval of proposal is required from Railway Board in order to commence the work in 2012-13
Additional Route MMTS which is running upto Lingampally should be extended upto Patancheru and also upto Sangareddy and Jadcharla of Mahaboobnagar
6
Sanctioned Projects
Sanctioned Projects as old as 92-93 are still in progress.
Projects sanctioned in 1999 is yet to start
Funds provided are grossly inadequate and provided funds are not utilized due to delay in sanction of estimates.
7
NEW LINES
8
Name of workBudget
CrsRemarks
1 Peddapalli Nizamabad- (92-93) 178 Km
150 Last phase Morthad to Nizamabad 45 km balance
2 Nandyal – Yerraguntla (96-97) 126 Km
180 Last phase Banaganapalli to Nandyal 28 km balance
3 Jaggayyapet- Mellacheruvu(06-07) 45 Km
90 Mellacheruvu to Vishnupuram link will be established
4 Devarakadra - Krishna 50 To speed up the progress
5 Kadapa-Bangalore(08-09) 225 Km
50 Kadapa- Pendlamarri can be completed. Balance Pendlamarri to Bangarpet estimate to be sanctioned early
6
Machela-Nalgonda(97-98) 82 Km
30 To speed up the progress
Total 550
Funds Required for 2012-13
As against the alloted budget of Rs. 365 crores in 2011-12, Railway requires Rs. 550 crores for the year 2012-13
9
Name of work Year of sanction
KM Anticipated
Cost
Remarks
1 NADIKUDI – SRIKALAHASTI
2011-12 308 1313 Final location survey in progress. Target Jan13
2 KOTIPALLI – NARSAPUR
2000-01 57 1047 Three Mega Bridges. Revised cost comes to Rs 20 crs per km. Estimate pending with Board.
3 MAHOHARABAD – KOTTAPALLI
2006-07 151 784 State Govt. agreed to bear 50% cost and land. Railways can sanction this estimate without insisting for annuity.
Rs. In Cr.
NEW LINES
ESTIMATES TO BE SANCTIONED
Contd..
10
Name of work Year of sanc.
KM Anticipated Cost
Remarks
4 KAKINADA – PITHAPURAM
1999-00 21 125 Estimate to be sanctioned.
5 BHADRACHALAM ROAD – SATTUPALLI
2010-11 56 337 As Rate of Return (RoR) is very (25%), Railways can sanction this work without insisting for deposit from SSCL
6 GUDUR – DURGARAJIPPATNAM
2011-12 45 283 Final location survey in progress. Target Jun12
Total 3889
Rs. In Cr.
NEW LINES
ESTIMATES TO BE SANCTIONED
Expeditious sanction of Estimates is required to commence the above works. Necessary budget to be allotted by the Railway Board
11
DOUBLING/THIRD LINE
12
Name of work KMs Budget (Crs)
Justification
1
Guntur – Tenali – Repalle
25 30 Executing by RVNL. Final Location survey in progress. Target Mar12
2
Vijayawada – Gudiwada – Bhimavaram – Narsapur – Machillipatnam
221 100 Executing by RVNL. Final Location survey in progress. Target Mar12
Total 130
Estimate to be sanctioned
Estimate amounts to be sanctioned by Rail Vikas Nigam Limited
13
Establishing Wagon Factory at Kazipet
We thank the Hon’ble Union Railway Minister for sanctioning the Wagon Factory
Land jointly identified by State and Railways is Endowment Land.
The process for sanction of Wagon Factory under PPP will be initiated by Railway Board.
Land is being given by the State Government shortly and we request work to be commenced quickly.
14
Proposal for Workshop and Loco Shed at Vizianagaram
Establishment of traction Loco shed at Guntakal
Establishment of railway allied industry in between Guntakal – Ananthapur or in and around
Improvement to the Gooty Diesel shed Setting up of POH Diesel/Electrical
Loco Shed at Vijayawada.
New Proposals for Workshop and Loco Shed
15
SURVEYS IN PROGRESS - 12
16
Year of survey
Project Km
1 10-11 Pagidipalli- Sankarapalli (NL) Target:Jun12 1102 10-11 Bapatla-Nizampatnam – Repalle (NL)
Target: Mar 1250
3 10-11 Gadchendur- Adilabad (NL) Target:Mar12 594 10-11 Bodhan-Bidar (NL) Target:May12 1005 10-11 Giddalur-Bhakrapet (NL) Target:Jun12 1106 10-11 Guntur -Guntakal (DL) Target:Jun12 3657 11-12 Macherla-Nadikudi (NL) Target:Jul12 238 11-12 Gooty-Dharmavaram (DL) Target:Jul12 919 11-12 Karimnagar-Hasanparti (NL) Target:May12 62
10 11-12 Nandyal-Atmakur (NL) Target:Jul12 6211 11-12 Hyderabad-Srisailam (NL) Target:Sep12 17112 11-12 Tenali-Repalle (NL) Target:Mar13 37
SURVEYS IN PROGRESS
These may be expedited.
17
SOCIALLY DESIRABLE SURVEYS
SANCTIONED - 8 SENT TO BOARD - 3 IN PROGRESS - 5
18
Year of survey
ProjectLength in
kmCOST In Cr
ROR% REMARKS
1 2010-11 Secunderabad – Zaheerabad
63 456 8.07 Sent to Board in2011-12.
2 2010-11 Pandurangapuram- Bhadrachalam Town
13 79 18.43 Sent to Board on 15.2.11 Updated on 6.7.11.
3 2010-11 Kachiguda – Chityal
87 1067 1.03 Sent to Board in 2011-12 Decision Awaited
SENT TO BOARD - 3NOS
Hon’ble Union Minister for Railways to instruct the Board for early sanction.
19
Year survey
ProjectLength in km
1 2010-11BhadrachalamRoad- Visakapatnam (NL) Target:Jun12
316
2 2010-11Krishna – Vikarabad (NL) Target:Feb12 148
3 2010-11Patancheru – Adilabad (NL) Target:Jul12 316
4 2010-11Mantralayam Road – Kurnool Town (NL) Target:Mar12
110
5 2010-11Jaggayyapeta Town – Miryalaguda (NL) Target:Mar12
65
SURVEYS IN PROGRESS
Hon’ble Minister for Railways to instruct the Board for early sanction.
20
Project % sharing
Kms Cost In Crs
Remarks
1 Kadapa - Bangarpet NewLine 50 257 1800 Phase I Kadapa-Pendlamarri- Land under acquisition. Tenders under finalisation.
2 Nadikudi – Srikalahasti NewLine 50 309 1313 Final location survey in progress. Target DEC’12
3 Manoharabad – Kothapalli NewLine
33 151 791 State Govt to confirm condition stipulated by Railway Board for cost sharing and Annuity.
4
Kotipalli – Narsapur NewLine 25 57 695Three Mega Bridges. Revised cost comes to Rs 20 crs per km. Estimate with Board.
5
Guntur - Tenali – Repalle Doubling 50 25 130 Executing by RVNL. Final Location survey in progress. Target Mar12
6Vijayawada-Gudiwada-BVRM-Narsapur-MTM Doubling 50 221 1010 Executing by RVNL. Final Location
survey in progress. Target Mar12
COST SHARING PROJECTS BY STATE GOVT
21
Year survey Project
Km Cost in Cr
ROR % Remarks
1 2008-09 Dornakal – Manuguru DL,PETS
104 450 24.53 Sent to Board on 27.8.10
2 2006-07 Tadikalapudi – Koyagudem RETS
19 119 17.94 Sent to Board on 24.9.10.
3 2004-05 Secunderabad –Dronachellam DL,PETS
297 534 14.00 Sent to Board on Jan 05.
4 1974-75 Mancherial – Chinnur, PETS
36 8 11.29 Sent to Board on May77.
5 2009-10 Bibinagar& Nallapadu DL,PETS
252 821 10.02 Sent to Board on 12.7.10
6 1976-77 Karimnagar – Kazipet, PETS
155 23 8.50 Sent to Board on Feb 85.
7 95-96 Sarpavaram – Chandrampalem, PETS
11 20 6.00 Sent to Board on Aug 96.
8 2007-08 Markapur Road-Srisailam, PETS
65 452 (-)9.25 Sent to Board on 29.9.10.
SURVEYS SUBMITTED TO RAILWAY BOARD
22
Year of survey Project
Km Cost in Cr
ROR %
REMARKS
9 2008-09 Armur-Adilabad (Updt) 136 700 (-) 10.8 Sent to Board on 16.8.10
10 2005-06 Donakonda – Bitragunta RETS
197 818 1.24 Sent to Board on May.07
11 2009-10 Piduguralla – Narsaraopet, RETS
32237 (-)0.44
Sent to Board on 29.9.10.
12 2005-06 Manuguru - Ramagundam incl TrD(RETS)
1991112
3.01& 7.34 (50%)
Sent to Board on May-08.
13 2005-06 Jadcherla – Nandyal RETS 182 565 (-)10.4 Sent to Board on Sept 07.
14 2004-05 Ongole – Donakonda, RETS
87 293 -0.36 Sent to Board on OCT97.
15 2004-05 Machilipatnam - Repalle, RETS
45 276 1.52 Sent to Board on Jan 05.
SURVEYS SUBMITTED TO RAILWAY BOARD
23
Year survey Project
Km Cost Cr
ROR %
Remarks
16 2002-03Donakonda – Vadarevu 113 228 (-) 6.95 Sent to Board on Aug 03.
17 2007-08Macherla – Gadwal (Tirumalgiri-Arepalli), UPDT
184 919 (-)4. Sent to Board on 5.8.10 Updated on 21.12.10.
18 00-01 Patancheru – Jogipet 44 108 (-) 3.61 Sent to Board on Dec2000.
19 99-00 Hyderabad – Raichur 189 456 (-) 35.03Sent to Board on Mar2000.
20 98-99 Kurnool –Kamalapurm(Kurnool – Nandyal)
81 153 (-) 13.37Sent to Board on Mar 99.
21 98-99 Yerraguntla – Dhamavaram 105 224 (-) 1.00 Sent to Board on Feb 09.
22 98-99 Chitoor –Bangarapet 140 356 (-) 0.43 Sent to Board on Nov 98.
23 97-98 Kapada -Nellore 181 355 (-) 0.46 Sent to Board on July 98.
SURVEYS SUBMITTED TO RAILWAY BOARD
24
Sl. No
Year of survey Project
Km Cost in Cr
ROR %
Remarks
24 97-98 Patancheru – Akkanapet, PETS
102 183 (-) 0.34Sent to Board on Jan 98.
25 1982-83Nidubrolu – Nizampatnam, PETS
21 12 0.82 Sent to Board on Jun 85.
26 1980-81Patancheru – Peddapalli & ,PETS
300 96 3.07 Sent to Board on Mar 81.
27 1972-73Gooty - Krishna - Adilabad – Wardah,Tfc
592 113 0.54 Sent to Board on Dec74.
SURVEYS SUBMITTED TO RAILWAY BOARD
25
Important projects in Andhra Pradesh to be sanctioned
26
Multi Model Transit System Ph-II- Hyderabad
New line from Nadikudi to Srikalahasti with an anticipated cost of Rs. 1313 crores
New line from Latur to Kovur
New line from Rajam to Vizianagaram
Important projects in Andhra Pradesh to be sanctioned
27
Increase in supply of rakes for procurement of rice
More passenger services
Passenger amenities to be improved
More stoppages
Important projects in Andhra Pradesh to be sanctioned
28
Wadi – Latur - Howrah
Bombay to Latur Road railway line is existing. If New line projects are sanctioned as mentioned
below, it will be a shortest route from West Coast to East coast, also connects under developed areas. Latur Road- Bodhan, Survey is completed - To be
sanctioned Ramagundam- Manuguru, survey done, GoAP agreed for
50%, but RoR is only 7%, we request that this be included in works under Extremist affected Districts and start the work immediately.
Bhadrachalam- Kovvur, Survey done, GoAP agreed for 50%, RoR is 28% - May be approved since it is a viable project
29
BODHAN
KOVVUR
PEDDAPALLI
30
NEW TRAINS PROPOSED
Secunderabad to Tirupathi Express via Kurnool – Dhone – Guntakal – Dharmavaram – Kalikiri - Madanapally
Nizamabad to Tirupathi overnight Express A new intercity Express between Visakhapatnam to
Secunderabad via Vijayawada – Khammam- Kazipet; duly delinking the present Janmabhoomi Exp.runnig in a circutous route as Janmabhoomi Exp. between Visakapatnam-Tenali and as Nagarjuna Exp.between Tenali-Sec’bad as was run earlier.
Kacheguda-Bangalore Garibrath Exp.
Contd..
31
SirpurKagaznagar-Tirupati Exp.Visakhapatnam-Shirdi ExpSecunderabad – Porbandar Exp.Kakinada-Mumbai Exp. Via SecunderabadKacheguda-Earnakulam Exp.Secunderabad- Manchiryal Intercity Exp.Hyderabad – Nagpur Exp.Vijayawada-Trivandrum ExpNellore- Secunderabad intercity Exp.Kurnool- Vikarabad Exp.Vizianagaram- Chennai Exp.
Contd..
Guntur – Mysore via, Guntakal, BangaloreKacheguda- Vasco ExpressHyderabad-Korba Exp.Secunderabad- Jaipur Exp.Yarraguntla – Banaganapalle PassengerDuronto Exp. Between Secunderabad- HowrahHyderabad-Jammutawi Exp. via New DelhiKacheguda- Tirunelveli Exp.
We request the Hon’ble Union Minister for Railways to consider the above.
33
EXTENSION OF TRAINS
Extension T.No.17603/ 17604 Kachiguda - Yesvantpur express to Mysore
Extension T.No.17063/17064 Secunderabad - Manmad Express to CST Mumbai
Extension T.No.12720/12719 Hyderabad - Ajmer bi-weekly Express to Jaipur
Extension T.No.12720/12719 Hyderabad - Mumbai CST- Latur Express to H.S.Nanded.
Extension T.No.57502/57503 Bodhan - Nizamabad passenger to Kamereddy
Extension T.No.56011/56012 Arakkonam- Nandalur Passenger to Cuddapah
34
Sl.No
Train No. & Description Stoppage required at
1 Train No.12735/12736 Garib Rath & Train No.17307/17308 BGT-YPR-BGT
Adoni
2 Train No.15906/15905 Dibrugarh- Cape Renigunta
3 Train No.12731/12732 TPTY-Sc Exp Kadiri & Guntakal
4 Train No.11019/11020 VSKP-NZM Exp Annavaram
5 Train No 17035/17036 SC-SKZR Exp Ghatkesar,Uppal,
Konanur, Asifabad Road,
Potkapalli & Ravindrakhanni
6 Train No 17064/17063 SC-MMR Exp Urmi
7 Train No.11045/11046 CSMT-DHB Exp Jalna
8 Train No. 11045/11046 CSMT-DHB Exp Kinwat, Himayatnagar
ADDITIONAL STOPPAGES REQUIRED
35
Representations from Hon’ble MPs and Union
Ministers of State of Andhra Pradesh
36
Sri Ananta Venkata Rami Reddy, MP
RoB at Anantapur to be taken up in this year’s budget.
Guntakal – Tirupati Express Train was announced but not started.
Guntakal Loco Shed already sanctioned, but sufficient budget is not being allotted.
37
Dr.Botcha Jhansi Lakshmi, MP (LS)
Proposed New Trains:(1) Vizianagaram to Chennai(2) Extension of Garib Rath Express to Vizianagaram, Land Acquisition in Kothavalasa to Visakhapatnam – Total land acquired 19 Acs. Actual handed over land is 6.6 Acs.
Cheepurupalli line over bridge.
38
Sri Magunta Sreenivasulu Reddy, MP
Ongole – Donakonda Railway Line- This may be taken up with 50% cost sharing, if
necessary in PPP mode. May be taken up during this budget.
Cumbum – Proddatur and Giddalur- Project to be taken up on cost sharing basis at the earliest.
Guntur – Dhone - Doubling Works to be done immediately.
39
Sri Mohd. Ali Khan, MP (RS)
MMTS Phase – II : To be sanctioned.
Trains to Ajmeer : To be sanctioned
40
Sri Manda Jagannadham, MP
Secunderabad – Mahabubnagar Doubling Works to be taken up immediately.
Secunderabad to Srisailam via Kollapur be taken up immediately.
MMTS to be extended upto Jedcharla of Mahabubnagar.
41
Ms. M.Vijayashanti, MP (LS)
New BG Survey Line from Akkannapet – Medak to be taken up
Construction of New BG Line from Hyderabad – Gajwel - Siddipet – Siricilla – Jagityal to be taken up.
Patancheru-Adilabad New Survey Line to be taken up.
Extension of Passenger Services between Shankerpally - Ordnance Factory at Yeddumailaram (MOD).
42
Sri T.Subbarami Reddy, MP (RS)
Duronto Express from Visakhapatnam.
Electrification of Bibi Nagar – Nallapadu and Nallapadu – Dronachalam.
More connectivity to Visakhapatnam to Sai Nagar City (Shiridi).
Visakhapatnam to Trivendrum connectivity.
43
Sri Anjan Kumar Yadav, MP
Lack of minimum facilities at Secunderabad, Nampally and Kachiguda Railway Stations.
Connectivity to Samshabad Airport.
Provision of Escalators in the Railway Stations of Secunderabad, Nampally and Kachiguda.
44
Sri Komati Reddy Rajagopal Reddy, MP
Lack of civic amenities in the Railway Stations of Bhongir / Alair and Janagaon.
RoBs at two places between Bibi Nagar and Yadagirigutta to be taken up / permitted by the GM, SCR.
45
Sri Gutha Sukender Reddy, MP
Bibi Nagar and Nadikudi electrification to be completed immediately, since it is the first project taken up after the Independence.
Mellacheruvu – Jaggaiahpet, Mattampalli – Janpahad to be completed early.
Kachiguda to Chittyal be extended upto Vijayawada and Survey proposals may be furnished accordingly.
Nalgonda – Macherla – So far no funds are spent on this.
Wagon coach factory at Kazipet to be established immediately, for which State Govt. should hand over the land by Coordinating with Endowments Dept.
46
Sri Kanumuri Bapi Raju, MP
The issue of provision of Railway Wagons to FCI for procurement of Paddy be increased.
RUB at Shivalayam Street to be taken up.
Un-manned railway gates to be provided with guards as announced by the then Railway Minister.
Railway gates on Railway crossing should not be closed permanently by the railway Authorities unilaterally. They should consult District Ministers / District Collector, before closing down.
47
Sri Nandi Yellaiah, MP (RS)
Manoharabad to Kothapalli via Siddipet, was announced long back but no budget has been spent on this.
MMTS - Lingampally – Patancheru may be extended to Sangareddy.
The District Headquarters of Medak is not connected with Railway network and it is a long pending demand of the people (Medak to Sangareddy – 70 Kms.)
48
Sri Rayapati Sambasiva Rao, MP
Guntur RoB at Arandalpet to be expanded six feet at both the sides.
Repalle – Tenali Electrification – Survey should be done immediately.
49
Sri Kavuri Sambasiva Rao, MP
40 RoB proposals can be completed in 2 years by releasing 50% of State share.
Bhadrachalam – Kovvur Railway line be taken up immediately, since it connects most of tribal and underdeveloped parts.
100 Escalators to be provided across the State.
50
Dr. D. Purandeswari, Hon’ble Union Minister of State for HRD
Waltair Division should be made as a separate zone and if it is not possible as a last option should merge in South Central Railway.
Amending the present policy - Railway lands for slum Dwellers in Visakhapatnam to provide alternative land to railways.
To develop Tourism in that area by providing exclusive trains to Araku Valley.
Originating trains from Visakhapatnam to Chennai, Bangalore and Tirupati to be introduced.
51
Sri Lagadapati Rajagopal, MP
Vijayawada station should be upgraded to world Class Railway Station.
Kachiguda – Chittyal to be extended to Vijayawada.
Kondapalli – Kothagudem is very important and RoR is also good, hence to be taken up.
Permission to the local bodies to take up the civic works. Requested the Railway Authorities to permit without any hurdle.
52
Sri Sarve Satyanarayana, MP
MMTS Phase – II to be sanctioned immediately.
RoBs at Malkajgiri, Safilguda and other places to be taken up.
Though Malkajgiri is declared as ‘Adarsh Station’, no works on platform and civic amenities have been taken up.
Vikarabad Hitech Railway station works to be taken up.
53
Sri Suresh Shetkar, MP
Bodhan – Bidar railway Line : Survey is completed, but work is not taken up.
Patancheruvu – Sangareddy announced, but no survey has been taken up.
Demu – Hyderabad – Vikarabad – Zaheerabad – Bidar – is announced not taken up so far.
Bombay to Lathur via Zaheerabad and short distances to Hyderabad to be taken up.
Progress of works at Zaheerabad ‘Adarsh Station’ are not satisfactory.
54
Sri Harsha Kumar, MP
Kotipally – Amalapuram and Kotipally – Narsapur be taken up immediately.
At Dwarakapudi Adarsh Station, no trains are stopping.
55
Sri Madhu Yashki, MP
Adarsh Railway Station at Nizamabad to be improved.
At Bodhan Gandhi Park Railway Station, though Rs.15 lakhs have been provided from MP Lads, the platform is at a low level and causing inconvenience.
Narrow crossing is causing accidents, hence, expansion of gate to be taken up immediately and RoB at a later stage.
56
Sri Ponnam Prabhakar, MP
Survey work of two newly sanctioned lines in 2011-12 Railway Budget i.e. Karimnagar to Secunderabad via Siddipeta and Karimnagar to Hasanparthy is pending.
ROB at Iammikunta is pending
Introduction of bi-weekly train from Karimnagar to Tirupathi
Establishment of Rake siding at Jammikunta Railway station
Sri. Porika Balram Naik, MP
New Line from Singareni Colleries to Gandhipuram to be laid
To construct a new modern style building on the newly constructed platform and providing general waiting hall and improve the circulating area with Arch Gate and to develop greenery at Dornakal Railway station categorised as B-Class
Restoration of passenger train facility from Singareni to Yellandu
Fixing of an online booking counter at Mulugu, Warangal District
Stoppage of TrainsTrain NO. 2705/06 at KesamudramTrain No. 1405/1406 at KesamudramTrain No. 12763/64 at NekkondaTrain No. 18645/46 at DornakalTrain No. 12727/28, 12511/12, 12615/16, 12752 at
Mahabubabad
Sri. M.M. Pallam Raju, Hon’ble Union Minister of State for Defence
Commencement of work on Kakinada – Pithapuram BG Line as the GoAP has committed to provide land free of cost.
New Train from Hyderabad – Kakinada (in addition to Gautami Express)
New Train from Kakinada to Mumbai and Kakinada to Varanasi
Conversion of Bi-Weekly Shiridi Express (Train No. 17206) as daily train
Provision of 4th Platform at Kakinada Town Railway Station Stoppage of Nagavali Express, Lokmanya Tilak Express and
Bhuvaneswar-Chennai at Samalkot Railway Station Stoppage of Garib Rath Express at Tuni Railway Station Augumentation of additional bogies for Sheshadiri Express
(3AC – 2, SL Class-3 bhogies) and Circar Express
Sri. A. Sai Pratap, MP
In addition to Venkatadri Express one more train from Kachiguda to Tirupati via Guntakal to be sanctioned
Conversion of Padmavati express into daily train Stoppage of Amaravathi Express at Molakalacheruvu, CTM
Madanapalli and Vayalpad Stoppage of Sampark Kranthi Express at Rajampet Extension of Arkonam passenger train upto Kadapa For Kadapa – Bangalore ongoing new project, atleast Rs.
100 crores from Railways to be released as that State contribution will also be released (50:50 cost sharing)
At Nandaluru Station of Guntakal Division nearly 200 acres of railway land along with 150 houses plus locomotive shed with infrastructure is available. Request to utilize this infrastructure and provide suitable industry connected to railways.
60
RAILWAY SAFETY WORKS
ROB’s/RUB’s
61
Road Over / Under Bridges (ROBs/RUBs) are being taken up under cost sharing basis with State Governments on 50:50 basis where Train Vehicular Units (TVUs) is more than 1.00 Lakh.
As of now 120 Nos costing Rs 2707.40 cr of ROBs/RUBs are approved by Railway Board which are at various stages of construction.
62
Further, ROBs/RUBs are taken up at LC’s which are having less than 1.00 Lakh TVU’s with entire cost borne by State Govt.
12 such ROBs/RUBs costing Rs 201.95 cr. are at various stages of construction
63
Sl.no
Stage Cost sharing 50:50
State Govt. funds
Total
Nos Cost Nos
Cost Nos
Cost
1 Works completed
48 628.83
3 34.92
51 663.75
2 Works in progress
36 898.05
3 21.43
39 919.48
3 Works at tender stage
8 235.20
2 45.00
10 280.20
4 Works at estimate stage
9 325 4 100.50
13 425.50
5 Investigation stage
19 645.32
0 0.00 19 645.32
120 2707.4
12 201.95
132
2909.35
The stage –I approvals for 19 works are under process
64
Railway zone Eligible Lcs
Proposals submitted by state Govt. to Railway zones
Proposals sent to railway Board by Railway zones
South Central Railways
41 10 6
East Coast Railways
4 2 1
South west Railways
- 3 0
Total 45 15 7
65
Proposals submitted by state Govt. to Railways to include in
RWP:2012-13Sl No
L.C. No.
Location District Remarks
SOUTH CENTRAL RAILWAYS
1 57 Ravindrakhani AdilabadProcessed by SCR and sent to Rly. Board to sanction in RWP:2012-13.
2 30 Adilabad town limits AdilabadProposals furnished to SCR vide Govt. Letter dt.07.06.2011.
3 80 Sirpur town limits AdilabadProcessed by SCR and sent to Rly. Board to sanction in RWP:2012-13.
4 127Ramnagar gate in Ananthapur town limits
Ananthapur
Proposals furnished to SCR for inclusion in RWP:2012-13.
5 124 NH Ananthapur
Processed by SCR and sent to Rly. Board to sanction in RWP:2012-13.
6 102 NH ChittoorProcessed by SCR and sent to Rly. Board to sanction in RWP:2012-13.
7 134 Kamalapuram Kadapa
Proposals furnished to SCR for inclusion in RWP:2012-13.
66
Proposals submitted by state Govt. to Railways to include in
RWP:2012-13Sl No
L.C. No.
Location District Remarks
SOUTH CENTRAL RAILWAYS
8 33 Wangapalli NalgondaProcessed by SCR and sent to Rly. Board to sanction in RWP:2012-13.
9 44 Raghunathapally Warangal
Processed by SCR and sent to Rly. Board to sanction in RWP:2012-13..
10 193 MadhavanagarNizamabad
Processed by SCR and sent to Rly. Board to sanction in RWP:2012-13.
EAST COAST RAILWAYS
1 SP-5 Waltair Marshal yardVSKP-Bhu'neswar
Proposals furnished to SCR for inclusion in RWP:2012-13.
2 RV-324Manapuram(NH)Rayapur-VSKP
Processed by SCR and sent to Rly. Board to sanction in RWP:2012-13.
SOUTH WESTERN RAILWAYS
Proposals furnished to SCR for inclusion in RWP:2012-13.
67
Proposals submitted by state Govt. to Railways to include in
RWP:2012-13Sl No
L.C. No.
Location District Remarks
SOUTH WESTERN RAILWAYS
1 71 Chakarala palli AnantapurProposals furnished to SCR for inclusion in RWP:2012-13.
2 83 Penukonda town limits AnantapurProposals furnished to SCR for inclusion in RWP:2012-13.
3 85Penukonda (Peddacheruvu gate)
AnantapurProposals furnished to SCR for inclusion in RWP:2012-13.
Total Proposals sent to Railways = 15 NosProcessed by the Railways 1.South Central Railways = 6 Nos2.East Coast Railways = 1 Nos3.Total Processed by Railways = 7 Nos.
South Central Railways communicated a list of 40 nos of eligible LCs for processing the proposals for inclusion in RWP 2013-14.
New Railway guidelines communicated by Railway board vide Lr. dated 7-10-2011 has to be followed for processing proposals for RWP 2013-14.
69
According to new guidelines, alignment, GAD has to be processed by R&B and railways . Further the site has to be made encumbrance free by acquiring land, shifting of utilities etc., and detailed estimate has to be sent along with proposal for inclusion in RWP.
70
The Honorable Minister for Railways may kindly consider to sanction all 15 proposals under Railway works programme 2012-13.
The Hon’ble Minister for Railways may kindly re-consider the Railway guidelines issued vide Railway Board letter dt.07.10.2011, in processing the proposals to be included in Railway Works Programme 2013-14 onwards.
1. So as to avoid delay 2. It may be difficult to safe guard the land
so acquired from encroachments in case the proposal is not approved in Railway Works Programme.
THANK YOU