S10 1 13 JUNTAS DE DILATACION 163.85 13.01 LATERALES CON MORTERO ASFALTICO m2 8.25 19.86 163.85 12.03 ENCOFRADO DE CONTRAPASOS H=0.40cm m2 33.60 38.11 1,280.50 12.02 PISO DE CEMENTO PULIDO EN PASO E=2.5cm m2 42.00 24.32 1,021.44 12 OBRAS DE MAMPOSTERIA 12,185.51 12.01 MAMPOSTERIA DE PIEDRA CON MORTERO DE CEMENTO 1:10, C-H m3 46.20 213.93 9,883.57 11.02 ELIMINACION DE MATERIAL EXCEDENTE CON CARRETILLA (50m) m3 26.25 8.24 216.30 11 MOVIMIENTO DE TIERRAS 461.37 11.01 EXCAVACION MASIVA m3 21.00 11.67 245.07 10.02 TRAZO Y REPLANTEO m2 42.00 2.02 84.84 10 TRABAJOS PRELIMINARES 153.84 10.01 LIMPIEZA DE TERRENO MANUAL m2 75.00 0.92 69.00 09.03 LIMPIEZA DE OBRA m2 59.50 0.63 37.49 09.02 PINTURA EN CARPINTERIA METALICA m2 238.00 7.62 1,813.56 09 VARIOS 6,651.05 09.01 FLETE TERRESTRE HUANCAYO A OBRA- cerco perimetrico glb 1.00 4,800.00 4,800.00 08.01.04 ANCLAJES DE TUBERIAS EN CONCRETO u 17.00 170.10 2,891.70 08.01.03 ANGULOS DE 1 1/2" X 1/8" m 374.00 14.00 5,236.00 08.01.02 MALLA METALICA CODADA 11/2" DE F°G°#12 m2 238.00 34.25 8,151.50 08.01.01 TUBERIA FIERRO GALAVANIZADO 2"X2.5"mm m 352.20 34.95 12,309.39 08 CARPINTERIA METALICA 28,588.59 08.01 MALLA METALICA SOBRE MURO DE CONTENCION 28,588.59 07.02 LIMPIEZA DE OBRA m2 700.00 0.63 441.00 07 VARIOS 6,441.00 07.01 COMPRA DE TERRENO glb 1.00 6,000.00 6,000.00 06 CARPINTERIA METALICA 5,200.00 06.01 ARCOS(INC MALLA) T ABLERO D E BASQUET ( INC MALLA), PARANTES DE V OLEY (INC MALLA) SEGUN PLANO glb 1.00 5,200.00 5,200.00 05 PINTURA 550.56 05.01 PINTURA EN PISO MARCAS PARA LAS TRES DISCIPLINAS m 444.00 1.24 550.56 04.06 JUNTAS ASFALTICAS m 238.00 3.09 735.42 04.05 JUNTA DE TEKNOPORT ENTRE PAÑOS m2 238.00 3.23 768.74 04.04 ENCOFRADO Y DESENCOFRADO ENTRE PAÑOS m2 49.50 26.68 1,320.66 04.03 CONCRETO EN LOSAS DE ARCO e=0.15m f`c=175kg/cm2 m2 12.00 39.49 473.88 04.02 CONCRETO EN SARDINELES f'c=175 kg/cm2 m3 3.11 279.63 869.65 04 CONCRETO SIMPLE 24,071.31 04.01 CONCRETO EN LOSAS e=0.15m f`c=175kg/cm2 m2 504.00 39.49 19,902.96 03.05 ELIMINACION MATERIAL EXCEDENTE m3 234.88 6.30 1,479.74 03.04 RELLENO CON MATERIAL PROPIO SELECCIONADO e=10cm m3 59.40 50.47 2,997.92 03.03 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 264.00 24.01 6,338.64 03.02 EXCAVACION DE SARDINEL m3 3.11 11.67 36.29 03 MOVIMIENTO DE TIERRAS 15,473.91 03.01 EXCAVACION MASIVA m3 396.00 11.67 4,621.32 02.02 TRAZO REPLANTEO m2 558.00 1.30 725.40 02 TRABAJOS PRELIMINARES 1,332.60 02.01 LIMPIEZA DE TERRENO MANUAL m2 660.00 0.92 607.20 676.78 01.02 CASETA ADICIONAL P/GUARDIANIA Y/O DEPOSITO glb 2.00 500.00 1,000.00 Precio S/. Parcial S/. 01 OBRAS PROVISIONALES 1,676.78 01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m u 1.00 676.78 Lugar HUANCAVELICA - TAYACAJA - COLCABAMBA Item  Descripción Und. Metrado Página Presupuesto Presupuesto 0302003 CONSTRUCCI ON DE LA INF RAESTRUCT URA MULTIDEPORTIVA DEL BARRIO DE AMARU DEL C.P. TOCAS, DITRITO DE COLCABAMBA-TAYACAJA-HUANCAVELICA Cliente MUNICIPALIDAD DISTRITAL DE COLCABAMBA Costo al 15/11/2011

Transcript of presupuesto total132

  • 5/27/2018 presupuesto total132

    1/3

    S10 1

    13 JUNTAS DE DILATACION 163.85

    13.01 LATERALES CON MORTERO ASFALTICO m2 8.25 19.86 163.85

    12.03 ENCOFRADO DE CONTRAPASOS H=0.40cm m2 33.60 38.11 1,280.50

    12.02 PISO DE CEMENTO PULIDO EN PASO E=2.5cm m2 42.00 24.32 1,021.44

    12 OBRAS DE MAMPOSTERIA 12,185.51

    12.01 MAMPOSTERIA DE PIEDRA CON MORTERO DE CEMENTO 1:10, C-H m3 46.20 213.93 9,883.57

    11.02 ELIMINACION DE MATERIAL EXCEDENTE CON CARRETILLA (50m) m3 26.25 8.24 216.30

    11 MOVIMIENTO DE TIERRAS 461.37

    11.01 EXCAVACION MASIVA m3 21.00 11.67 245.07

    10.02 TRAZO Y REPLANTEO m2 42.00 2.02 84.84

    10 TRABAJOS PRELIMINARES 153.84

    10.01 LIMPIEZA DE TERRENO MANUAL m2 75.00 0.92 69.00

    09.03 LIMPIEZA DE OBRA m2 59.50 0.63 37.49

    09.02 PINTURA EN CARPINTERIA METALICA m2 238.00 7.62 1,813.56

    09 VARIOS 6,651.05

    09.01 FLETE TERRESTRE HUANCAYO A OBRA- cerco perimetrico glb 1.00 4,800.00 4,800.00

    08.01.04 ANCLAJES DE TUBERIAS EN CONCRETO u 17.00 170.10 2,891.70

    08.01.03 ANGULOS DE 1 1/2" X 1/8" m 374.00 14.00 5,236.00

    08.01.02 MALLA METALICA CODADA 11/2" DE FG#12 m2 238.00 34.25 8,151.50

    08.01.01 TUBERIA FIERRO GALAVANIZADO 2"X2.5"mm m 352.20 34.95 12,309.39

    08 CARPINTERIA METALICA 28,588.59

    08.01 MALLA METALICA SOBRE MURO DE CONTENCION 28,588.59

    07.02 LIMPIEZA DE OBRA m2 700.00 0.63 441.00

    07 VARIOS 6,441.00

    07.01 COMPRA DE TERRENO glb 1.00 6,000.00 6,000.00

    06 CARPINTERIA METALICA 5,200.00

    06.01 ARCOS(INC MALLA) TABLERO DE BASQUET (INC MALLA), PARANTES DE VOLEY

    (INC MALLA) SEGUN PLANO

    glb 1.00 5,200.00 5,200.00

    05 PINTURA 550.56

    05.01 PINTURA EN PISO MARCAS PARA LAS TRES DISCIPLINAS m 444.00 1.24 550.56

    04.06 JUNTAS ASFALTICAS m 238.00 3.09 735.42

    04.05 JUNTA DE TEKNOPORT ENTRE PAOS m2 238.00 3.23 768.74

    04.04 ENCOFRADO Y DESENCOFRADO ENTRE PAOS m2 49.50 26.68 1,320.66

    04.03 CONCRETO EN LOSAS DE ARCO e=0.15m f`c=175kg/cm2 m2 12.00 39.49 473.88

    04.02 CONCRETO EN SARDINELES f'c=175 kg/cm2 m3 3.11 279.63 869.65

    04 CONCRETO SIMPLE 24,071.31

    04.01 CONCRETO EN LOSAS e=0.15m f`c=175kg/cm2 m2 504.00 39.49 19,902.96

    03.05 ELIMINACION MATERIAL EXCEDENTE m3 234.88 6.30 1,479.74

    03.04 RELLENO CON MATERIAL PROPIO SELECCIONADO e=10cm m3 59.40 50.47 2,997.92

    03.03 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3 264.00 24.01 6,338.64

    03.02 EXCAVACION DE SARDINEL m3 3.11 11.67 36.29

    03 MOVIMIENTO DE TIERRAS 15,473.91

    03.01 EXCAVACION MASIVA m3 396.00 11.67 4,621.32

    02.02 TRAZO REPLANTEO m2 558.00 1.30 725.40

    02 TRABAJOS PRELIMINARES 1,332.60

    02.01 LIMPIEZA DE TERRENO MANUAL m2 660.00 0.92 607.20

    676.78

    01.02 CASETA ADICIONAL P/GUARDIANIA Y/O DEPOSITO glb 2.00 500.00 1,000.00

    Precio S/. Parcial S/.

    01 OBRAS PROVISIONALES 1,676.78

    01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m u 1.00 676.78

    Lugar HUANCAVELICA - TAYACAJA - COLCABAMBA

    Item Descripcin Und. Metrado

    Pgina

    Presupuesto

    Presupuesto 0302003 CONSTRUCCION DE LA INFRAESTRUCTURA MULTIDEPORTIVA DEL BARRIO DE AMARU DEL C.P. TOCAS, DITRITO DE

    COLCABAMBA-TAYACAJA-HUANCAVELICA

    Cliente MUNICIPALIDAD DISTRITAL DE COLCABAMBA Costo al 15/11/2011

  • 5/27/2018 presupuesto total132

    2/3

    SUPERVISOR 5,000

    EXPEDIENTE TECNICO 5,000

    COSTO TOTAL DE LA OBRA 208,882

    SUB TOTAL 168,544

    IMPUESTOS(IGV 18%) 30,338

    TOTAL DEL PRESUPUESTO 198,882

    COSTO DIRECTO 141,781

    GASTOS GENERALES 10% 14,178

    UTILIDADES (0.088761%) 12,584

    20.03 LIMPIEZA DE OBRA m2 123.00 0.63 77

    20.02 FLETE TERRESTRE HUANCAYO A OBRA-MURO DE CONTENCION glb 1.00 1,600.00 1,600

    20 VARIOS 2,102

    20.01 TUBERIA DE DRENAJE (PVC, SAP CLASE 7.5D=3") m 32.00 13.27 424

    19 JUNTAS DE DILATACION 374

    19.01 LATERALES CON MORTERO ASFALTICO m2 18.88 19.86 374

    18 OBRAS DE MAMPOSTERIA DE PIEDRA 30,040

    18.01 MAMPOSTERIA DE PIEDRA CON MORTERO DE CEMENTO 1:10, C-H m3 140.42 213.93 30,040

    17 OBRAS DE CONCRETO SIMPLE 883

    17.01 SOLADOS CONCRETO f'c=100 kg/cm2 h=2" m2 83.30 10.61 883

    16.03 ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50m) m3 104.13 8.24 858

    16.02 REFINE Y NIVELACION Y COMPACTACION MANUAL EN CARRETILLA(50m) m2 83.30 10.59 882

    16 MOVIMIENTO DE TIERRAS 2,301

    16.01 EXCAVACION PARA ZAPATAS DE MURO m3 83.30 6.74 561

    15.02 TRAZO Y REPLANTEO m2 83.30 2.02 168

    15 TRABAJOS PRELIMINARES 281

    15.01 LIMPIEZA DE TERRENO MANUAL m2 123.00 0.92 113

    14.02 LIMPIEZA DE OBRA m2 75.00 0.63 47

    14 VARIOS 2,847

    14.01 FLETE TERRESTRE HUANCAYO A OBRA-TRIBUNAS glb 1.00 2,800.00 2,800