US 95, Garwood to Sagle, Bonner County, Sagle KN 09781
US 95, SH-53 to Ohio Match Road, Kootenai CountyKN 011010
US 95, Garwood to Sagle, Bonner County, Sagle
Project Overview
•Approximate Project Limits – M.P. 465.3 to 469.75
•New four-lane highway with limited access
•Frontage roads are planned on both sides of U.S. 95
• The Preliminary Design includes:
•Limited Preliminary design for the new four-lane divided highway
•TS&L for 3 Interchanges and 1 Underpass
•Realignment of Railroad at the curve near M.P. 467
•Right-of-way plans and legal descriptions
Dufort R
d
Monarch R
d
US 95, Garwood to Sagle, Bonner County, Sagle
Project Information
Concept Report
Draft Environmental Document
Preliminary Mapping
Preliminary Total Ownership Map
Draft Phase 1 Report
Conceptual DEIS Plan View
IS&T for US 95, SH-53 to Ohio Match Road, KN 011010
Project Background
• 4 Lane Divided Highway
• No major structures
• Estimated start of construction June ’08
• Completion anticipated to be End of ‘09
• Includes winter shutdown
Requirements
• Idaho Inspector Qualification Program
• WAQTC qualified
• Environmental Inspection
• Comply with Consent Decree
• Field Rates must be approved by ITD
ITD has first right of refusal to any and all IS&T
IS&T for US 95, SH-53 to Ohio Match Road, KN 011010
Anticipated Quantities:
Project Length: 3 Miles
Borrow: 98,500 CY
Aggregate Base: 233,000 Tons
Pipe Culvert: 1,000 Feet
Traffic Signals: 2
Superpave HMA: 71,000 Tons