Count Dept.
JVS RG CS Jan
Management
Project Manager JVS 1 A. C. Goins
Safety
Safety Co-ordinator CS 2 J. Crossan
Safety Officer CS 3 L. Casenas
Safety Officer CS 4 M. Endaya
Business / Project Controls
Business Manager JVS 5 G. Carvel 0.1
Business Team Lead JVS 6 T.B.A.
Project Controls Manager JVS 7 B. Back 0.1
Contracts Engineer JVS 8 D. Kirsch 0.1
RGPMS / RGEE Co-ordinator JVS 9 T. Taylor
Senior Analyst - Venture Projects RG 10 J. Srinivasan
Senior Project Accountant RG 11 R. Rao 0.1
Project Controls Engineer CS 12 C. Brayford 0.1
Cost Engineer JVS 13 I. Mohammed 0.05
Schedule Engineer CS 14 J. Domingo
Procurement Co-ordinator CS 15 F. McCabe 0.1
Quality
Quality Manager CS 16 I. Ambrose 0.1
Quality Co-ordinator (Pipelines) CS 17 M. Weal
Quality Co-ordinator (Platforms) CS 18 S.Ogle
Lead E&I Inspector CS 19 R. Hawyes
Lead Mechanical and Welding Inspector CS 20 M. Dennett
Quality Engineer CS 21 D. McGrory
Engineering
Engineering Manager JVS 22 H. van de Graaf 0.1
Mechanical Completions Engineer CS 23 D. Apps
Piping / Layout Engineer CS 24 D. Topp 0.15
Process Engineer CS 25 T.B.A.
Facilities Engineer CS 26 T.B.A.
Facilities Engineer CS 27 C. Bell
Control Systems Engineer CS 28 S. Gammie 0.15
Facilities Engineer CS 29 W. Fitzgerald 0.15
Pipeline Engineer CS 30 TBA
Pipeline Engineer CS 31 S. Jones 0.25
Piping / Layout Engineer CS 32 A. Summers 0.25
Construction / Installation
Construction Manager JVS 33 D. Baron 0.15
Construction Superintendent CS 34 R. Carter
Construction Superintendent CS 35 J. Vernal
Construction Engineer JVS 36 T.B.A. 0.15
Construction Superintendent Qatar CS 37 P. Hughes
Total per source 10 2 25 37 OVERALL PMT
Additional personnel
2.1
FULL TIME (CORE TEAM) OFFSHORE PMT MA
WP&B 2009 PMT MANMONTHS
WP&B 2009 PMT YEARLY MANMONTHS
Full Time PMTSource
File: 218140671.xls.ms_office (CORE PMT 2009)
3/22/2014
8/12/2019 PMT Manpower WBarzan
http://slidepdf.com/reader/full/pmt-manpower-wbarzan 2/4
JVS RG CS
Project Manager JVS
Safety Co-ordinator CS
Safety Officer CS
Safety Officer CS
Business Manager JVS
Business Team Lead JVS
Project Controls Manager JVS
Contracts Engineer JVS
RGPMS / RGEE Co-ordinator JVS
Senior Analyst - Venture Projects RG
Senior Project Accountant RG
Project Controls Engineer CS
Cost Engineer JVS
Schedule Engineer CS
Procurement Co-ordinator CS
Quality Manager CS
Quality Co-ordinator (Pipelines) CS
Quality Co-ordinator (Platforms) CS
Lead E&I Inspector CS
Lead Mechanical and Welding Inspector CSQuality Engineer CS
Engineering Manager JVS
Mechanical Completions Engineer CS
Piping / Layout Engineer CS
Process Engineer CS
Facilities Engineer CS
Facilities Engineer CS
Control Systems Engineer CS
Facilities Engineer CS
Pipeline Engineer CS
Pipeline Engineer CS
Piping / Layout Engineer CS
Construction Manager JVS
Construction Superintendent CS
Construction Superintendent CS
Construction Engineer JVS
Construction Superintendent Qatar CS
Total per source 10 2 25
Pre-qualification o
BARZAN EPC CONTRA
WP&B 2009 PMT OVERALL MA
WP&B 2009 PMT MANMON
WP&B 2009 PMT YEARLY MAN
Full Time PMTSource
8/12/2019 PMT Manpower WBarzan
http://slidepdf.com/reader/full/pmt-manpower-wbarzan 3/4
Suppor
Project
Tehnica
Accoun
Accoun
Total pe
Suppor
Vessel
Vessel
Safety L
Safety L
Dive Le
Dive Le
Technic
Technic
Technic
Technic
Vessel
Vessel
Safety L
Safety L
Dive Le
Dive Le
Technic
Technic
Technic
Technic
Vessel
Safety L
Diver
Technic
Technic
Vessel
Diver
Diver
Constru
Vessel
Safety L
Diver
Technic
Technic
Total pe
Suppor
Installat
8/12/2019 PMT Manpower WBarzan
http://slidepdf.com/reader/full/pmt-manpower-wbarzan 4/4
2009
MANMONTHSRATE TOTAL COST Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
JVS 57 48 2,729 36 70 96 110 122 192 259 271 317 372 442 442
Contract staff 81 30 2,423 38 56 89 107 137 150 168 201 278 329 435 438
RG staff 5 16 71 2 2 2 2 2 2 2 2 2 8 25 25
142 5,223 80 130 190 220 260 340 430 470 600 710 900 900
COST RATE TOTAL COST Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
PMT support expenses 5,223 7.5% 392 6 10 14 17 20 26 32 35 45 53 68 68
Secure office 250 250 36 36 36 36 36 36 36
Houston support 100 DAYS 3.0 / day 300 50 50 50 50 50 50
942 10 10 10 50 60 60 120 120 130 140 120 120
6,164 90 140 200 270 320 400 550 590 730 850 1,020 1,020
616 10 10 20 30 30 40 60 60 70 90 100 100
6,800 100 150 220 300 350 440 610 650 800 940 1,120 1,120
Anticipated 2008 expenditure (Accrued December 2008) 188
TOTAL (ROUNDED)
Allocation Cost CORE TEAM
TOTAL
OTHER COSTS
SUB-TOTAL
2009 Monthly ExpenditureU.S. $ x 1,000
PMT - Barzan EPC ContractU.S. $ X 1,000
Offshore PMT (Jebel Ali) 2009 only
TOTAL
+ 10% CONTINGENCY