Overview of CAISO Stakeholder Process for FERC Order 764 Compliance Implementation of 15 minute scheduling and settlement Jim Price, CAISO Presentation to WECC Interchange Scheduling and Accounting Subcommittee January 16, 2013

Transcript of Overview of CAISO Stakeholder Process for FERC Order 764 Compliance Implementation of 15 minute...

Page 1: Overview of CAISO Stakeholder Process for FERC Order 764 Compliance Implementation of 15 minute scheduling and settlement Jim Price, CAISO Presentation.

Overview of CAISO Stakeholder Processfor FERC Order 764 ComplianceImplementation of 15 minute scheduling and settlement

Jim Price, CAISOPresentation to WECC Interchange Scheduling and Accounting SubcommitteeJanuary 16, 2013

Page 2: Overview of CAISO Stakeholder Process for FERC Order 764 Compliance Implementation of 15 minute scheduling and settlement Jim Price, CAISO Presentation.

Proposed Implementation of Renewable Integration Market Design Changes

• Fall 2013– Order 764 compliance filing

• May 2013 CAISO Board decision, • Spring 2014

– Dynamic Transfers: Add transmission reservation bid component & look-ahead forecast of VER availability

– Implement 15-minute market• Fall 2014

– Flexible ramping product in DA and RT markets– Integrated DA market & residual unit commitment

Page 2

Page 3: Overview of CAISO Stakeholder Process for FERC Order 764 Compliance Implementation of 15 minute scheduling and settlement Jim Price, CAISO Presentation.

Executive Summary of 15-Minute Market

• Adapt existing functionality to allow 15 minute schedule updates consistent with regional practices

• Use three-settlement market by making Real-Time Unit Commitment (RTUC) financially binding – 15-minute market replaces Hour-Ahead Scheduling Process

(HASP) settlement for energy & ancillary services

• Leverage Dynamic Transfers transmission reservation functionality to address hourly or sub-hourly intertie transmission for VERs?

• Allow intertie Convergence Bidding if day-ahead pricing issue resolved

Page 3

Page 4: Overview of CAISO Stakeholder Process for FERC Order 764 Compliance Implementation of 15 minute scheduling and settlement Jim Price, CAISO Presentation.

Hourly Process for Real Time Market (Straw Proposal)

Page 4

Market transmission reservations in DA, HASP, & RTUCwould be financially binding.

HASP energy schedules would not be financially binding.

Market 1 Market 2 Market 3 Market 4

T-75: Real-Time Bid Submission Deadline

T-45: Awards for Intertie Hourly Transmission Reservations

T-20: E-Tag Deadline for Hourly Intertie Transmission Profiles and Market 1 Energy Schedules

T

T = Start of the Hour

T-37.5: Start of Market 1 Optimization

Page 5: Overview of CAISO Stakeholder Process for FERC Order 764 Compliance Implementation of 15 minute scheduling and settlement Jim Price, CAISO Presentation.

15-minute Process for Real Time Market

Page 5

Second interval of RTUC optimization (currently “advisory”) becomes the binding interval in new 15-minute market, to allow e-

tagging 20 minutes before start of interval

Financially Binding

Market 2

T-5: E-Tag deadline for Market 2 Energy Schedules

T-22.5: Self Schedule Changes for Market 2

T-7.5: Awards for Market 2 Energy Schedules

T

T-22.5: Start of Market 2 Optimization

37.5 Minutes

20 Minutes

T = Start of the Hour

Page 6: Overview of CAISO Stakeholder Process for FERC Order 764 Compliance Implementation of 15 minute scheduling and settlement Jim Price, CAISO Presentation.

5-minute Process for Real Time Market

Page 6

No changes to Real-Time Dispatch (RTD)

RTD provides operational instruction to all resources

Financially Binding

Market 1 Market 2

T+15RTD 4RTD 2 RTD 6

T+7.5: Start of RTD 4 Optimization

T+12.5: Awards of RTD 4 Dispatch, Start of RTD 5 Optimization

T+15

RTD 3 RTD 5

T = Start of the Hour

Page 7: Overview of CAISO Stakeholder Process for FERC Order 764 Compliance Implementation of 15 minute scheduling and settlement Jim Price, CAISO Presentation.

All Real Time Market bids would be submitted in HASP, at T-75• Bids to economically schedule resources in 15-minute

market and 5-minute economic dispatch– Energy self-schedule and/or energy bid, same as now– Ancillary services bids, same as now– No Load bids in RTUC 15-minute market or in RTD

• Dynamic transfer design allows optional intertie transmission reservation bid for VERs, in excess of expected energy, to accommodate variability.

• In straw proposal: Hourly transmission awards, priced at the shadow cost of intertie congestion in HASP– Use of capacity awarded in HASP is exempt from

intertie congestion cost in RTUC and RTD

Page 7

Page 8: Overview of CAISO Stakeholder Process for FERC Order 764 Compliance Implementation of 15 minute scheduling and settlement Jim Price, CAISO Presentation.

Real time self schedules may change at T-37.5 for every 15-minute interval

• Self schedule can change in 15-minute market, e.g., due to physical or operational characteristics

• VERs can update using rolling 5-minute or 15-minute granularity forecast to establish real-time schedule

• Intertie changes 20 minutes before 15-minute intervals, due to physical or operational characteristics (including e-tag curtailments and reloads in other BAAs), would be limited by ISO’s transmission reservations

• Changes from day-ahead to RTUC settle at RTUC price• RTUC to RTD deviations settle at the RTD price

– Intertie operational adjustments to 15-minute schedule settle at RTD

Page 8

Page 9: Overview of CAISO Stakeholder Process for FERC Order 764 Compliance Implementation of 15 minute scheduling and settlement Jim Price, CAISO Presentation.

Transmission Reservation Overview

• Explicit TR bid only available to VERs with self-schedules (SS) and no ancillary services bids– Ensures ISO receives accurate expected energy so resources are

not committed using inflated SS, since HASP energy not binding– Allows VERs to ensure intertie capacity is available in real-time

and not allocated to hourly block schedules

• For hourly block schedules,– TR bid is imbedded in energy bid– Enforce HASP constraint for same MW in each 15-min interval

• For conventional 15-minute intertie or non-VER dynamics,– TR bid is embedded in energy bid– Intertie scheduling limit enforced every 15-minute interval, but

advisory energy schedule can differ by 15-minute interval– TR award in HASP = avg of 15-minute advisory energy schedules

Page 9

Page 10: Overview of CAISO Stakeholder Process for FERC Order 764 Compliance Implementation of 15 minute scheduling and settlement Jim Price, CAISO Presentation.

HASP transmission award would define priority for energy schedules and basis for congestion settlement

• HASP would award financially binding hourly transmission capacity, which is then used for financially binding energy schedules and AS awards within operating hour:– Intra-hour energy schedules: 15-minute intervals– Dynamic transfer energy: dispatch by 5-minute interval– Ancillary service awards: 15-minute intervals

• Unused intertie capacity would be released in each interval– Self-schedules would have higher priority within

HASP transmission award

• Resources using released capacity would be charged the relevant real-time intertie shadow price

Page 10

Page 11: Overview of CAISO Stakeholder Process for FERC Order 764 Compliance Implementation of 15 minute scheduling and settlement Jim Price, CAISO Presentation.

Issue: Settlement of Transmission Reservation (TR) in multiple markets would have increased complexity

• TR has separate limits for import and export directions, and considers advisory energy counterflows (e.g., 3500 MW import & 500 MW export on 3000 MW intertie)

• TR would be separated into Import Right, Import Obligation, Export Right and Export Obligation

• TR is unidirectional for an hour. Market participant would receive a “right” or “obligation” for each direction.– Right: For energy at or below TR, settle at original TR price. For

energy exceeding TR, settle at subsequent market’s price– Obligation: Settlement principles would balance those of a

“right”

• Stakeholder concerns include uplift from TR settlement

Page 11

Page 12: Overview of CAISO Stakeholder Process for FERC Order 764 Compliance Implementation of 15 minute scheduling and settlement Jim Price, CAISO Presentation.

15-minute market may allow scheduling alternatives for reliably managing the grid

• Perform market optimization based upon intertie bids– Hourly Blocks

• Enforce constraint that T = T+15 = T+30 = T+45• If economic bid is not cleared, hourly block schedule is 0 MW

– 15-minute schedules and dynamic transfers• 15 minute intervals can have different MW level• If not accepted, option to not allow economic bid in RT market

– VER forecast over intertie, to allow delivery to exceed hourly avg.• How to create the VER forecast to account for variability?

• Publish awarded hourly block schedules at T-45– May be able to further streamline timing

• Hourly block schedules are price takers in 15-min market – Even if an economic bid submitted for hourly block schedule

Page 12

Page 13: Overview of CAISO Stakeholder Process for FERC Order 764 Compliance Implementation of 15 minute scheduling and settlement Jim Price, CAISO Presentation.

ISO is looking for opportunities to improve timeline while remaining consistent with WECC

• Accepted hourly block schedules posted by T-45– Note: binding optimization for each 15-minute interval is started

afterwards

• 2.5 minutes is tight for updating tags for 15-minute energy schedules, after awarding intra-hour schedules– ISO investigating if solution times can be reduced

• Continue to work with WECC task force and ISO stakeholders– But, tagging timeline not expected to change in near term

Page 13

Page 14: Overview of CAISO Stakeholder Process for FERC Order 764 Compliance Implementation of 15 minute scheduling and settlement Jim Price, CAISO Presentation.

Next steps

• More info: http://www.caiso.com/informed/Pages/StakeholderProcesses/FERCOrderNo764MarketChanges.aspx

• Comments on revised straw proposal may be submitted by February 26 to [email protected].

Page 14

Item DateStraw Proposal October 23, 2012

Stakeholder Meeting October 30, 2012Technical Workshop Stakeholder Call December 18, 2012

Revised Straw Proposal February 5, 2013Stakeholder Meeting February 12, 2013

Stakeholder Comments Due February 26, 2012Draft Final Proposal March 26, 2013Stakeholder Meeting April 2, 2013

Board Meeting May 2013Tariff Filing September 2013