Nr 3 M Wahlgren ESCL Presentation 060825 MW

16
Mikael Wahlgren Mikael Wahlgren NCC Construction Sverige AB NCC Construction Sverige AB ESCL Conference August 25th 2006 ESCL Conference August 25th 2006 – Risk in Construction and how – Risk in Construction and how to deal with them. to deal with them. Duty for the contractor to inspect Duty for the contractor to inspect the site and other physical the site and other physical conditions according to FIDIC. conditions according to FIDIC. Presented by Presented by Mikael Wahlgren Mikael Wahlgren Former Senior Legal Counsel Former Senior Legal Counsel NCC Construction Sweden AB NCC Construction Sweden AB

description

fidic standard forms

Transcript of Nr 3 M Wahlgren ESCL Presentation 060825 MW

Page 1: Nr 3 M Wahlgren ESCL Presentation 060825 MW

Mikael Wahlgren Mikael Wahlgren NCC Construction Sverige ABNCC Construction Sverige AB

ESCL Conference August 25th ESCL Conference August 25th 2006 – Risk in Construction and 2006 – Risk in Construction and how to deal with them.how to deal with them.

Duty for the contractor to inspect the site Duty for the contractor to inspect the site and other physical conditions according to and other physical conditions according to

FIDIC.FIDIC.

Presented by Presented by

Mikael WahlgrenMikael WahlgrenFormer Senior Legal CounselFormer Senior Legal CounselNCC Construction Sweden ABNCC Construction Sweden AB

Page 2: Nr 3 M Wahlgren ESCL Presentation 060825 MW

Mikael Wahlgren Mikael Wahlgren NCC Construction Sverige ABNCC Construction Sverige AB

FIDIC’s old standard FIDIC’s old standard forms forms Conditions of Contract for Works of Civil Engineering Conditions of Contract for Works of Civil Engineering

ConstructionConstruction, Fourth Edition, 1987 (reprinted in 1988 with , Fourth Edition, 1987 (reprinted in 1988 with editorial amendments and reprinted in 1992 with further editorial amendments and reprinted in 1992 with further amendments) (the “old Red Book”);amendments) (the “old Red Book”);

Conditions of Subcontract for Works of Civil EngineeringConditions of Subcontract for Works of Civil Engineering, , Construction, First Edition, 1994 (to function with the old Red Construction, First Edition, 1994 (to function with the old Red Book);Book);

Conditions of Contract for Electrical and Mechanical Conditions of Contract for Electrical and Mechanical WorksWorks, Third Edition, 1987 (reprinted in 1988 with editorial , Third Edition, 1987 (reprinted in 1988 with editorial amendments) (the “old Yellow Book”); andamendments) (the “old Yellow Book”); and

Conditions of Contract for Design-Build and TurnkeyConditions of Contract for Design-Build and Turnkey, First , First Edition, 1995 (the “Orange Book”).Edition, 1995 (the “Orange Book”).

Client-Consultant Model Services AgreementClient-Consultant Model Services Agreement (3rd Ed., 1998, (3rd Ed., 1998, ) ("White Book") ) ("White Book")

Page 3: Nr 3 M Wahlgren ESCL Presentation 060825 MW

Mikael Wahlgren Mikael Wahlgren NCC Construction Sverige ABNCC Construction Sverige AB

FIDIC’s (the International FIDIC’s (the International Federation of Consulting Federation of Consulting Engineers) new standard formsEngineers) new standard forms Conditions of Contract for ConstructionConditions of Contract for Construction (1999; for (1999; for

building and engineering works designed by the building and engineering works designed by the employer) (the “new Red Book”);employer) (the “new Red Book”);

Conditions of Contract for Plant and Design-BuildConditions of Contract for Plant and Design-Build (1999; for electrical and mechanical plant and for building (1999; for electrical and mechanical plant and for building and engineering works designed by the contractor) (the and engineering works designed by the contractor) (the “new Yellow Book”);“new Yellow Book”);

Conditions of Contract for EPC Turnkey ProjectsConditions of Contract for EPC Turnkey Projects (1999; EPC being the abbreviation for Engineer-Procure-(1999; EPC being the abbreviation for Engineer-Procure-Construct) (the “Silver Book”); andConstruct) (the “Silver Book”); and

Short Form of ContractShort Form of Contract (1999; for projects of relatively (1999; for projects of relatively small value) (the “Green Book”).small value) (the “Green Book”).

Page 4: Nr 3 M Wahlgren ESCL Presentation 060825 MW

Mikael Wahlgren Mikael Wahlgren NCC Construction Sverige ABNCC Construction Sverige AB

Clause 4.10 (new Red Clause 4.10 (new Red Book & Yellow Book) – Book & Yellow Book) – Site DataSite Data““The Employer shall have made available to The Employer shall have made available to the Contractor for his information, prior to the Contractor for his information, prior to the Base Date, all relevant data in the the Base Date, all relevant data in the Employer’s possession on sub-surface and Employer’s possession on sub-surface and hydrological conditions at the Site, including hydrological conditions at the Site, including environmental aspects. The Employer shall environmental aspects. The Employer shall similarly make available to the Contractor similarly make available to the Contractor all such data which come into the all such data which come into the Employer’s possession after the Base Date. Employer’s possession after the Base Date. The Contractor shall be responsible for The Contractor shall be responsible for interpreting all such data.interpreting all such data.

Page 5: Nr 3 M Wahlgren ESCL Presentation 060825 MW

Mikael Wahlgren Mikael Wahlgren NCC Construction Sverige ABNCC Construction Sverige AB

Clause 4.10 (new Red Book Clause 4.10 (new Red Book & Yellow Book) – Site Data & Yellow Book) – Site Data (cont.)(cont.)

To the extent which was practicable (taking account of cost and time), the To the extent which was practicable (taking account of cost and time), the Contractor shall be deemed to have obtained all necessary information as to risks, Contractor shall be deemed to have obtained all necessary information as to risks, contingencies and other circumstances which may influence or affect the Tender or contingencies and other circumstances which may influence or affect the Tender or Works. To the same extent, the Contractor shall be deemed to have inspected and Works. To the same extent, the Contractor shall be deemed to have inspected and examined the Site, its surroundings, the above data and other available information, examined the Site, its surroundings, the above data and other available information, and to have been satisfied before submitting the Tender as to all relevant matters and to have been satisfied before submitting the Tender as to all relevant matters including (without limitation):including (without limitation):

(a)(a) the form and nature of the Site, including sub-surface conditions,the form and nature of the Site, including sub-surface conditions,

(b)(b) the hydrological and climatically conditions,the hydrological and climatically conditions,

(c)(c) the extent and nature of the work and Goods necessary for the execution and the extent and nature of the work and Goods necessary for the execution and completion of the Works and the remedying of any defects,completion of the Works and the remedying of any defects,

(d)(d) the laws, procedures and labour practices of the Country (means the country the laws, procedures and labour practices of the Country (means the country in which the Site (or most of it) is located, where the Permanent Works are to in which the Site (or most of it) is located, where the Permanent Works are to be executed), andbe executed), and

(e)(e) the Contractor’s requirement for access, accommodation, facilities, personnel, the Contractor’s requirement for access, accommodation, facilities, personnel, power, transport, water and other services.”power, transport, water and other services.”

Page 6: Nr 3 M Wahlgren ESCL Presentation 060825 MW

Mikael Wahlgren Mikael Wahlgren NCC Construction Sverige ABNCC Construction Sverige AB

Clause 4.10 (Silver Book) Clause 4.10 (Silver Book) – Site Data– Site DataThe last sentence of paragraph 1 have been The last sentence of paragraph 1 have been deleted and replaced the 2nd paragraph deleted and replaced the 2nd paragraph with the following wording:with the following wording:

““The Contractor shall be responsible for The Contractor shall be responsible for verifying and interpreting all such data. The verifying and interpreting all such data. The Employer shall have no responsibility for Employer shall have no responsibility for the accuracy, sufficiency or completeness the accuracy, sufficiency or completeness of such data, except as stated in Sub-Clause of such data, except as stated in Sub-Clause 5.1 [General Design Responsibilities].”5.1 [General Design Responsibilities].”

Page 7: Nr 3 M Wahlgren ESCL Presentation 060825 MW

Mikael Wahlgren Mikael Wahlgren NCC Construction Sverige ABNCC Construction Sverige AB

Comments to Clause Comments to Clause 4.10 – Site Data4.10 – Site DataIn the new Red Book and new Yellow Book:In the new Red Book and new Yellow Book:

Constitutes a step backwards for the Contractor by Constitutes a step backwards for the Contractor by inserting the words inserting the words “relevant data in the Employer’s “relevant data in the Employer’s possession”possession”..

Reference to Reference to “relevant data” “relevant data” limits the information to limits the information to be provided by the Employer. be provided by the Employer.

Contractors are advised to amend this requirement so Contractors are advised to amend this requirement so that thethat the Employer is required to supply all available data Employer is required to supply all available data on hydrological and sub-surface conditions. on hydrological and sub-surface conditions.

In the new Yellow Book should beIn the new Yellow Book should be expanded to include all expanded to include all information relevant to the Contractor’s design.information relevant to the Contractor’s design.

Page 8: Nr 3 M Wahlgren ESCL Presentation 060825 MW

Mikael Wahlgren Mikael Wahlgren NCC Construction Sverige ABNCC Construction Sverige AB

Comments to Clause Comments to Clause 4.10 – Site Data (cont.)4.10 – Site Data (cont.)In the Silver Book:In the Silver Book:

The Contractor is responsible for verifying data - particularly, verifying The Contractor is responsible for verifying data - particularly, verifying and interpreting all data on subsurface and hydrological conditions, and interpreting all data on subsurface and hydrological conditions, including environmental aspects. including environmental aspects.

Carefully scrutinise the precise extent to which the exceptions offered Carefully scrutinise the precise extent to which the exceptions offered under Sub-Clause 5.1. under Sub-Clause 5.1.

The disclaimer covers any information provided during the The disclaimer covers any information provided during the performance of the Works - the Contractor cannot rely on information performance of the Works - the Contractor cannot rely on information provided by the Employer during the execution of the Contract.provided by the Employer during the execution of the Contract.

FIDIC recognise that, the Silver Book is not suitable for use where FIDIC recognise that, the Silver Book is not suitable for use where “there is insufficient time or information for tenderers to “there is insufficient time or information for tenderers to scrutinise and check the Employer's Requirements or for them scrutinise and check the Employer's Requirements or for them to carry out their designs, risk assessment studies and to carry out their designs, risk assessment studies and estimating” - estimating” - FIDIC's alternative is the Yellow Book. FIDIC's alternative is the Yellow Book.

Page 9: Nr 3 M Wahlgren ESCL Presentation 060825 MW

Mikael Wahlgren Mikael Wahlgren NCC Construction Sverige ABNCC Construction Sverige AB

Clause 4.12 (new Red Book & Clause 4.12 (new Red Book & Yellow Book) – Unforeseeable Yellow Book) – Unforeseeable Physical ConditionsPhysical Conditions““In this Sub-Clause, “physical conditions” means natural physical In this Sub-Clause, “physical conditions” means natural physical conditions and man-made and other physical obstructions and pollutants, conditions and man-made and other physical obstructions and pollutants, which the Contractor encounters at Site when executing the Works, which the Contractor encounters at Site when executing the Works, including sub-surface and hydrological conditions but excluding climatic including sub-surface and hydrological conditions but excluding climatic conditions.conditions.

If the contractor encounters adverse physical conditions which he If the contractor encounters adverse physical conditions which he considers to have been Unforeseeable, the Contractor shall give notice to considers to have been Unforeseeable, the Contractor shall give notice to the Engineer as soon as possible.the Engineer as soon as possible.

This notice shall describe the physical conditions, so they can be This notice shall describe the physical conditions, so they can be inspected by the Engineer, and shall set out the reasons why the inspected by the Engineer, and shall set out the reasons why the Contractor considers them to be Unforeseeable (means not reasonably Contractor considers them to be Unforeseeable (means not reasonably foreseeable by an experienced contractor by the date for submission of foreseeable by an experienced contractor by the date for submission of the Tender). The Contractor shall continue executing the Works, using the Tender). The Contractor shall continue executing the Works, using such proper and reasonable measures as are appropriate for the physical such proper and reasonable measures as are appropriate for the physical conditions, and shall comply with any instructions which the Engineer conditions, and shall comply with any instructions which the Engineer may give. If an instruction constitutes a Variation (means any change to may give. If an instruction constitutes a Variation (means any change to the Works, which is instructed or approved as a variation), under Clause the Works, which is instructed or approved as a variation), under Clause 13 [Variations and Adjustments] shall apply.13 [Variations and Adjustments] shall apply.

Page 10: Nr 3 M Wahlgren ESCL Presentation 060825 MW

Mikael Wahlgren Mikael Wahlgren NCC Construction Sverige ABNCC Construction Sverige AB

Clause 4.12 (new Red Book & Clause 4.12 (new Red Book & Yellow Book) – Unforeseeable Yellow Book) – Unforeseeable Physical Conditions (cont.)Physical Conditions (cont.)If and to the extent that the Contractor encounters physical conditions If and to the extent that the Contractor encounters physical conditions which are Unforeseeable, gives such a notice, and suffers delay and/or which are Unforeseeable, gives such a notice, and suffers delay and/or incurs Cost by the Contractor, whether on or off the Site, including incurs Cost by the Contractor, whether on or off the Site, including overhead and similar charges, but does not include profit) due to these overhead and similar charges, but does not include profit) due to these conditions, the Contractor shall be entitled subject to Sub-Clause 20.1 conditions, the Contractor shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claim] to:[Contractor’s Claim] to:

(a)(a) an extension of time for any such delay, if completion is or will be an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], delayed, under Sub-Clause 8.4 [Extension of Time for Completion], andand

(b)(b) Payment of any such Cost, which shall be included in the Contract Payment of any such Cost, which shall be included in the Contract Price.Price.

After receiving such notice and inspecting and/or investigating these After receiving such notice and inspecting and/or investigating these physical conditions, the Engineer shall proceed in accordance with Sub-physical conditions, the Engineer shall proceed in accordance with Sub-Clause 3.5 [Determination] to agree or determine (i) whether and (if so) to Clause 3.5 [Determination] to agree or determine (i) whether and (if so) to what extent these physical conditions were Unforeseeable, and (ii) the what extent these physical conditions were Unforeseeable, and (ii) the matter described in sub-paragraphs (a) and (b) above related to this matter described in sub-paragraphs (a) and (b) above related to this extent.extent.

Page 11: Nr 3 M Wahlgren ESCL Presentation 060825 MW

Mikael Wahlgren Mikael Wahlgren NCC Construction Sverige ABNCC Construction Sverige AB

Clause 4.12 (new Red Book & Clause 4.12 (new Red Book & Yellow Book) – Unforeseeable Yellow Book) – Unforeseeable Physical Conditions (cont.)Physical Conditions (cont.)However, before additional Cost is finally agreed or determined However, before additional Cost is finally agreed or determined under sub-paragraph (ii), the Engineer may also review whether under sub-paragraph (ii), the Engineer may also review whether other physical conditions in similar parts of the Works (if any) were other physical conditions in similar parts of the Works (if any) were more favourable than could reasonably have been foreseen when more favourable than could reasonably have been foreseen when the Contractor submitted the Tender. If and to the extent that the Contractor submitted the Tender. If and to the extent that these more favourable conditions were encountered, the Engineer these more favourable conditions were encountered, the Engineer may proceed in accordance with Sub-Clause 3.5 [Determination] may proceed in accordance with Sub-Clause 3.5 [Determination] to agree or determine the reductions in Cost which were due to to agree or determine the reductions in Cost which were due to these conditions, which may be included (as deductions) in the these conditions, which may be included (as deductions) in the Contract Price and Payment Certificates. However, the net effect of Contract Price and Payment Certificates. However, the net effect of all adjustments under sub-paragraph (b) and all these reductions, all adjustments under sub-paragraph (b) and all these reductions, for all the physical conditions encountered in similar parts of the for all the physical conditions encountered in similar parts of the Works, shall not result in a net reduction in the Contract Price.Works, shall not result in a net reduction in the Contract Price.

The Engineer may take account of any evidence of the physical The Engineer may take account of any evidence of the physical conditions foreseen by the Contractor when submitting the Tender, conditions foreseen by the Contractor when submitting the Tender, which may be made available by the Contractor, but shall not be which may be made available by the Contractor, but shall not be bound, by any such evidence.”bound, by any such evidence.”

Page 12: Nr 3 M Wahlgren ESCL Presentation 060825 MW

Mikael Wahlgren Mikael Wahlgren NCC Construction Sverige ABNCC Construction Sverige AB

Clause 4.12 (Silver Book) Clause 4.12 (Silver Book) – Unforeseeable – Unforeseeable DifficultiesDifficulties ““Except as otherwise stated in the Contract: Except as otherwise stated in the Contract: (a)(a)the Contractor shall be deemed to have the Contractor shall be deemed to have

obtained all necessary information as to risks, obtained all necessary information as to risks, contingencies and other circumstances which contingencies and other circumstances which may influence or affect the Works;may influence or affect the Works;

(b)(b)by signing the Contract, the Contractor accepts by signing the Contract, the Contractor accepts total responsibility for having foreseen all total responsibility for having foreseen all difficulties and costs of successfully completing difficulties and costs of successfully completing the Works; and the Works; and

(c)(c) the Contract Price shall not be adjusted to take the Contract Price shall not be adjusted to take account of any unforeseen difficulties or costs.”account of any unforeseen difficulties or costs.”

Page 13: Nr 3 M Wahlgren ESCL Presentation 060825 MW

Mikael Wahlgren Mikael Wahlgren NCC Construction Sverige ABNCC Construction Sverige AB

Clause 4.12 (new Red Book & (new Red Book & Yellow Book) – Yellow Book) – Unforeseeable Physical Conditions

Unforeseeable” is a defined term = “not reasonably foreseeable by an experienced Contractor by the date of submission of the Tender”.

Entitlement to recover additional costs will not include profit.

Relief for cost and time due to unforeseeable “natural physical conditions and man made and other physical obstructions or pollutants” and “including subsurface and hydrological conditions”.

No relief due to impediments encountered off the site. Excludes climatic events. Engineer may take into account whether “other Physical

Conditions in similar parts of the Works (if any) were more favourable than could reasonably have been foreseen when the Contractor submitted its Tender”.

New concept that allows for the Contractor to provide evidence of the physical conditions foreseen in his tender calculation.

An alternative is to agree the foreseeable conditions beforehand.

Page 14: Nr 3 M Wahlgren ESCL Presentation 060825 MW

Mikael Wahlgren Mikael Wahlgren NCC Construction Sverige ABNCC Construction Sverige AB

Clause 4.12 (Silver Book) (Silver Book) – Unforeseeable – Unforeseeable DifficultiesDifficulties The language is uncompromising in the extreme and The language is uncompromising in the extreme and

its scope and application are much more wide-its scope and application are much more wide-ranging. ranging.

The consequential effects of all unforeseen difficulties The consequential effects of all unforeseen difficulties are passed to the Contractor, are passed to the Contractor, “Except as otherwise “Except as otherwise stated in thestated in the Contract”Contract”. .

The Contractor is to foresee and allow in the price for The Contractor is to foresee and allow in the price for every eventuality however unforeseeable! every eventuality however unforeseeable!

It is difficult to imagine a clause which would be more It is difficult to imagine a clause which would be more threatening to contractors - Contractors should threatening to contractors - Contractors should beware!beware!

Page 15: Nr 3 M Wahlgren ESCL Presentation 060825 MW

Mikael Wahlgren Mikael Wahlgren NCC Construction Sverige ABNCC Construction Sverige AB

Conclusion & final Conclusion & final notesnotesThe main reason for the diminishing The main reason for the diminishing

use of the FIDIC standard forms :use of the FIDIC standard forms : need quite substantive amendments;need quite substantive amendments; many law firms have produced and many law firms have produced and

promote their own bespoke contract promote their own bespoke contract forms; andforms; and

the number of competing standard the number of competing standard forms.forms.

Page 16: Nr 3 M Wahlgren ESCL Presentation 060825 MW

Mikael Wahlgren Mikael Wahlgren NCC Construction Sverige ABNCC Construction Sverige AB

Conclusion & final Conclusion & final notes (cont.)notes (cont.)Regions where FIDIC standard forms are used:Regions where FIDIC standard forms are used: projects in Africa and Asia.projects in Africa and Asia. projects financed by the World Bank.projects financed by the World Bank. Under US law, where the contractor has a duty to inspect, that duty Under US law, where the contractor has a duty to inspect, that duty

does not include taking its own soil borings. A contractor is entitled does not include taking its own soil borings. A contractor is entitled to rely on the borings provided by the Employer.to rely on the borings provided by the Employer.

The new Red and Yellow Book (clause 4.12) can give time and The new Red and Yellow Book (clause 4.12) can give time and money for unforeseen site conditions whereas Silver Book says money for unforeseen site conditions whereas Silver Book says largely the reverse – the Contract Price should not be adjusted for largely the reverse – the Contract Price should not be adjusted for unforeseen difficulties or cost. unforeseen difficulties or cost.

If the Silver clauses remain unchanged, contractors may try (if the If the Silver clauses remain unchanged, contractors may try (if the facts justify it) to claim for:facts justify it) to claim for:– site conditions on the basis that the Employer did not make site conditions on the basis that the Employer did not make

relevant data available (clause 4.10);relevant data available (clause 4.10);– ground conditions on the basis of inability to verify (clause ground conditions on the basis of inability to verify (clause

5.1(d)); and 5.1(d)); and – Force Majeure in extreme cases Force Majeure in extreme cases ((clause 19.1).clause 19.1).