Transcript of Naresh kumar ppt
![Page 1: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/1.jpg)
JAIPUR INSTITUTE OF ENGINEERING AND MANAGEMENT, GADOTA, JAIPUR
PRESENTATION ON “ C.C.ROAD ”
1
Submitted to:Mr. Sanwar Mal MitharwalHOD (CE)
Presented by:Naresh KumarB.Tech4 th year (CE)
2015-16
![Page 2: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/2.jpg)
2
PPT ON SUMMER TRAINING NARESH KUMAR CIVIL ENGG. 7TH SEM 12EJMCE016
![Page 3: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/3.jpg)
3
Public Works Department Rajasthan Bayana(Bharatpur) Kapoora Malooka
![Page 4: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/4.jpg)
Construction of Cement Concrete Road
![Page 5: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/5.jpg)
5
![Page 6: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/6.jpg)
6
Using mix Concrete , there some Point to construct the road :-
1. Preparation of base2. Form working3. Preparation of subgrade4. Watering of base5. Joints6. Material mix & placing7. Compaction
![Page 7: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/7.jpg)
7
8. Finishing of surface8A. Floating8B. Belting8C. Brooming9. Curing10. Joint filling11. Edging12. Open to traffic
![Page 8: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/8.jpg)
8
1. Preparation of subgrade
1. Rolling on sub grade by roller2. Filling the granular soil in the weak part
and pot holes3. Correct the soil coat , Camber ,
longitudinal slop When concrete direct laid on subgrade, For preventing the water-seepaging into the soil , used water proof paper on entire length.
![Page 9: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/9.jpg)
9
![Page 10: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/10.jpg)
10
2. Preparation of base Choose any one type of base1. W.B.M. base As base material of W.B.M. Road; stone ballast, concrete 10-15cm layer are used. For bonding between concrete slab & W.B.M. used 1:2 cement wash on W.B.M.2. Concrete base On the road used 10cm Cement concrete(1:2:4) or lime concrete(16:32:64)
![Page 11: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/11.jpg)
11
3. Granular medium material layer 10-15cm composite layer of sand , moorum , bajri are used for better drainage facilities4. Stabilization soil
![Page 12: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/12.jpg)
12
3. Form work Material for form work- Wooden sheets, battens, plywood, fibre hard board, steel plates, angles, rope, minerals.
1. before using form work, it should free from all type material like as dust ,cement. 2. To placing the concrete in appropriate depth used 2.5-5cm thick and 3mtr long wooden sheeting.
![Page 13: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/13.jpg)
13
3. The depth of wooden block must be same as level of slab thick. 4. After 24hrs form work displaced next length of road.
![Page 14: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/14.jpg)
14
4. Watering of base
If base is dryThan using the sprinkling process on it properly after that placing the concrete.
![Page 15: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/15.jpg)
15
5. JOINTS
Where is necessary to provide transverse, Longitudinal joints; there wedge of woods, metals fix on level of concrete. After setting of concrete it should be pull out. If provided the dowel bar in joints, bars should be fit at right position.
![Page 16: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/16.jpg)
16
6. Material mix & placing
Mixer is equipment that mix the concrete using distinct amount of cement , concrete, sand and water. Concrete slab should have more than 5-10cm thick cause of drying.Used two type mixer-1. Batch mixer- at site, used for small road construction2. Continuous mixer- Continuous mixer used for large construction . if distance is more from site , mix concrete transported at site within setting time.
![Page 17: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/17.jpg)
17
![Page 18: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/18.jpg)
18
Two methods generally used in placing of concrete-1. Alternate bay method- Placed the concrete on both side of road alternatively like as1,3,5… part at one side and 2,4,6… part other side . 1st side 2nd sideThis method have slow process due to road traffic problems.
![Page 19: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/19.jpg)
19
2. Continuous bay method- construct one side of road regularly, if completed some part of first side than construct other side. this method have fast process without no obstruction of traffic
![Page 20: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/20.jpg)
20
7. Compaction
Purpose of compaction is that to pull out air from void and make concrete harden. Compaction done by- 1.mechanically surface vibrator 2. manually hand tempers
![Page 21: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/21.jpg)
21
8. Finishing of surface1.Floating- For levelling the surface use floating, scree-ding , power trowel. So that there is no acceptable more than 3mm variation in concrete level surface.2.Belting- For making surface clean used belting process. Belt is nothing but a 15-30cm thick sheets of canvass which have more length than road.
![Page 22: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/22.jpg)
22
![Page 23: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/23.jpg)
23
3. Brooming- Brooming is the process in which we made rough surface parallel to road by brush. It useful in avoiding slip & comfortable travelling on road . the depth of line on road no more than 1.5mm.
![Page 24: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/24.jpg)
24
9. Curing
Curing is the name of increasing the hydration process of cement. after setting the concrete , curing process done till 14-28days.
![Page 25: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/25.jpg)
25
Some method of curing are-1.Shading concrete works2. Covering with hessian & gunny bags3. Sprinkling of water4.By ponding5. Membrane curing6. Steam curing
![Page 26: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/26.jpg)
26
![Page 27: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/27.jpg)
27
10. Filling joint
After drying road, clean the joints and fill the shelling compound or hot bitumen . also bitumen fill road bank.
![Page 28: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/28.jpg)
28
11. Edging
To protect damaging the sides of concrete pavements used over burnt brick work. in place of brick, provided kerb of pre mix concrete.
![Page 29: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/29.jpg)
29
12. OPEN TO TRAFFIC
Generally after a month, road should be open to traffic. If used rapid hardening cement it take 7 days to open traffic.
![Page 30: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/30.jpg)
30
![Page 31: Naresh kumar ppt](https://reader035.fdocument.pub/reader035/viewer/2022070510/58a76bee1a28ab99238b4df3/html5/thumbnails/31.jpg)
31
THANK YOU