MRP ccm.pdf

download MRP ccm.pdf

of 16

Transcript of MRP ccm.pdf

  • 8/14/2019 MRP ccm.pdf

    1/16

    rel. 3 2008/01/24Solving Efeso 1999

    Material Requirements Planning

  • 8/14/2019 MRP ccm.pdf

    2/16

    - 2 -MRP Solving Efeso 1999

    Material flow management is based on apredefined schedule which takes into

    account demand and manufacturing leadtime

    Componentmanufacturing

    Componentwarehouse

    Kit assembly

    FP assembly

    Kit warehouse

    Finished product warehouse

    T i m e

    a n d

    q u a n t i t

    y

    Order forecast

    Orders

    Material

    Flows:

    Material Requirements Planning - 'Push' systems (M.R.P.)

  • 8/14/2019 MRP ccm.pdf

    3/16

    - 3 -MRP Solving Efeso 1999

    Material Requirements Planning

    It is based on the net requirements calculated by exploding, atcomponent level, certain predetermined finished product productionplans.

    It requires each dependent-demand component or material (child) tobe ordered or manufactured based on the corresponding independent-demand component/set (parent) requirement.

  • 8/14/2019 MRP ccm.pdf

    4/16

    - 4 -MRP Solving Efeso 1999

    Material Requirements Planning

    What it is

    An MRP system is a decision-makingsupport tool which - by processing datareported in the Master ProductionSchedule - provides a complete pictureof:

    What (which sets/subsets/parts/rawmaterials are needed to makefinished products)

    How much

    When to purchase/manufacture

    Working principles

    It explodes the production orderplan stemming from the MPS and itsuggests a time schedule for all bill-of-material levels (semi-finishedproducts, components, externalmaterials)

    It synchronises activities andlogistic flows inside and outside ofthe production unit

    It keeps semi-finished productstock levels at a minimum (WIP)

    It inputs Capacity RequirementsPlanning

  • 8/14/2019 MRP ccm.pdf

    5/16

    - 5 -MRP Solving Efeso 1999

    Assemble to stockIndustry Type

    MRP: Industry Application and Expected Benefits

    Examples Expected BenefitsCombines multiple parts into a finishedproduct, which is then stocked in inventory to satisfycustomer demand. Examples: watches, tools, appliances.

    High

    Make to stock

    Assemble to order

    Make to order

    Process

    Low

    High

    High

    Medium

    Items are manufactured by machine rather thanassembled from parts. These are standard stock itemscarried in anticipation of customer demand. Examples:piston rings, electrical switches.

    A final assembly is made from standard options thatthe customer chooses. Examples: trucks, generators,engines.

    Items fabricated or assembled completely to customerspecification. Examples: turbine generators, heavy

    machine tools.

    Industries such as foundries, rubber and plastics,speciality paper, chemicals, paint, drug, foodprocessor.

  • 8/14/2019 MRP ccm.pdf

    6/16

    - 6 -MRP Solving Efeso 1999

    Master Production ScheduleIt indicates how much and when to produce:

    finished products spare parts direct-sale materials and parts

    Product structure (Bill of materials)Multi-levelFor each level of the bill of materials it defines:

    links utilisation coefficient offset adjustment

    Inventory level in warehouses and departmentsPhysical stock

    Safety inventory

    Running orders (released to production or to asupplier)

    Booked quantityReorder policy

    Batch size

    Manufacturing time schedule

    External material and componentpurchase order schedule

    Customer order processability

    Abnormality and problemreporting:

    expediting expired orders

    anticipating a previouslyreleased order

    cancelling an order that hasalready been sent to thesupplier

    M.R.P.

    Material Requirements Planning (M.R.P.)

    Output

    informationInput data

  • 8/14/2019 MRP ccm.pdf

    7/16

    - 7 -MRP Solving Efeso 1999

    The system generates so-called

    'Order proposals (planned orders)'- (status = P) -

    These are subsequently analysed by theprogrammer and turned into

    'Confirmed orders'- (status = F) -

    which can no longer be automaticallymodified by the system, but only directly by

    the programmer.

    Material Requirements Planning - M.R.P. order types

  • 8/14/2019 MRP ccm.pdf

    8/16

    - 8 -MRP Solving Efeso 1999

    Design andtechnicalchanges

    MaterialRequirements

    Planning

    Orderportfolio

    ForecastsProduction

    capacityplanning Material

    movements

    MasterProductionSchedule

    Bill of materialsCyclesLead times...

    Stock

    BookedOrders...

    Productstructure

    Inventorylevel

    Order processability andcritical points

    Staff MeansSuppliers

    Sales

    New ordersExpeditingDelays...

    Supply Production

    Order loadingPrioritiesExpeditingLoads...

    Material Requirements Planning Structure

  • 8/14/2019 MRP ccm.pdf

    9/16

    - 9 -MRP Solving Efeso 1999

    Bill ofmaterials

    Production schedule(order plan)

    Lead time

    Batchproduction

    Stock

    Usagescraps

    Manuf.explosion

    Launchdates

    OrdersNet

    requirements

    Grossrequirements

    Production scraps

    Master Production Schedule

    A

    B C

    D E B D

    D E

    Starting from the independent-demand item production plan(bottom-level codes), MRP calculates gross and net quantity

    and schedule requirements for all necessarymaterials/components by exploding each level of the bill ofmaterials

    Material Requirements Planning: logical procedure

  • 8/14/2019 MRP ccm.pdf

    10/16

    - 1 0 -MRP Solving Efeso 1999

    The route for the MRP procedure

    1. Collect the current stocks, runningorders, booked stocks

    2. Evaluate how much to order internallyand externally1. Evaluate the stock during the previous

    period2. Collect the planned replenishments and

    gross requirements3. Calculate the stock for actual period

    1. Define the order quantity andthe offset factor

    2. Plan the reorder quantity

    1. Anticipate the date order2. Explode the gross requirement of highlevel components

    1. Collect the availability of bill of materialsand all management information (leadtime - order policy-provenance)

    2. Explode the products bill of materialsand schedule it based on lead time

    1. Choice the optimal batch production(Fixed EOQ, L4L, Dynamic EOQ)

    Assign the order issues Assign the order issues66

    Net requirementNet requirement44

    Gross requirementGross requirement11

    Plan replenishmentsPlan replenishments22

    Evaluate the stockEvaluate the stock33

    Set the batch productionSet the batch production55

  • 8/14/2019 MRP ccm.pdf

    11/16

    - 1 1 -MRP Solving Efeso 1999

    Material Requirements Planning - Requirement explosion

    X

    C

    Z Y

    Item "A"Stock:Safety inventory:% production scrap:Supply time.:Reorder policyE.O.Q.:

    10%

    170 pcs50 pcs

    3 periodsFixed E.O.Q.150 pcs

    Link Coeff. Offset factor (at assembly)

    A - BA - C

    21

    + 10%-----

    A

    B

    ---150--150-150-Order plan to be issued

    773333778840----Net re quirements

    150--150-150----Lot-sized re quirements

    ---150--150-150-Gross requirements of C from A

    ---330--330-330-Gross requirements of B from A

    -------48--Orders in progress

    7733337788552211--Scrap adjusted re quirements

    7030307080502010--Availability adjusted requirements

    00000002060120Initial availability

    70303070805020304060Gross Total Requirements

    20202020301010101010Gross External Requirements

    50101050504010203050Gross Internal Requirements

    10987654321Item "A"Periods

  • 8/14/2019 MRP ccm.pdf

    12/16

    - 1 2 -MRP Solving Efeso 1999

    Material Requirements Planning procedure

    All the procedure's steps aretotally electronic.

    A data processing of 100.000codes lasts about 10 minutes

    Dont assume that the firstdata processing is

    necessarily correct! Its veryimportant to run several

    simulations to satisfyyourself as well as the

    Master Production Schedule

    Exercises

  • 8/14/2019 MRP ccm.pdf

    13/16

    - 1 3 -MRP Solving Efeso 1999

    Requirement on top of available stock for period 1, given an orderedquantity (for orders which have been already released) higher than zero(orders to be processed now)

    Requirement on top of available stock for periods prior to the processingdate, given an ordered quantity (for orders which have already beenreleased) higher than zero (orders which should have been processedin the past)

    Net current requirement for future period: PROCESSING DATE+LEAD TIME (orders to be issued now)

    Net current requirement for periods prior to PROCESSING DATE +LEAD TIME (orders which should have been issued in the past)

    No requirement on top of available stock up to PROCESSING DATE +n PERIODS, given an ordered quantity higher than zero (over-ordering)

    CHECK

    REORDER

    EXPEDITING

    ALARM

    DELAY

    Material Requirements Planning - Reporting (a few examples)

  • 8/14/2019 MRP ccm.pdf

    14/16

    - 1 4 -MRP Solving Efeso 1999

    ?

    INPUT OUTPUT

    Material Requirements PlanningBasic problem posed by MRP

    Too complex (requires too much information)

    It requires a lot of 'discipline'

    It is not problem solving oriented

    It is difficult to understand correlations

  • 8/14/2019 MRP ccm.pdf

    15/16

    - 1 5 -MRP Solving Efeso 1999

    Then (and only then) our M.R.P. is going to work perfectly.What should be done?

    Conditions for obtaining the minimum theoretical inventorywith MRP

    If...1. Forecasts are good...

    2. and well 'mixed' with orders

    3. The Bill of materials is updated

    4. All production cycles are updated andcorrect

    5. Lead times do not change even in caseof absenteeism

    6. Lead times are never forced out of thesystem (the boss does not say 'I'll seeto it')

    7. Orders leave on time

    8. and we are sure they were received

    9. and meanwhile the lead time has notchanged

    10. and meanwhile the BOM has notchanged.

    11. Warehouse data is reliable

    12. Data on W.I.P. is reliable

    13. Nobody 'steals' materials14. 100% quality scraps are recorded

    15. There is plenty of stock

    16. Murphy is not holding it against us

    17. .... (miscellaneous) ....

  • 8/14/2019 MRP ccm.pdf

    16/16

    - 1 6 -MRP Solving Efeso 1999

    Overall discipline!

    MRP only when needed!

    Streamline!

    Reduce BOM levels.

    Reduce number of

    warehouses/buffersReduce Lead times

    Reduce number of suppliers

    JIT production islands

    Avoid bottlenecks and manage 'onsite'

    The information system may be oneof the bottlenecks!

    C

    A

    B

    B

    C

    Product A

    A

    B

    C

    A

    B

    C

    the factory should not be a maze

    but rather a highway

    in otherwords...

    Material Requirements Planning - What should be done?