LO-1A-1

download LO-1A-1

of 62

Transcript of LO-1A-1

  • 8/13/2019 LO-1A-1

    1/62

  • 8/13/2019 LO-1A-1

    2/62

    Project, Defined

    Aprojectis an endeavor to accomplish a specific objective througha unique set of interrelated tasks and the effective utilization of

    resources.

    It has a well-defined objective stated in terms of scope, schedule, and

    costs. Project s are born when a need is identified by the customer the

    people or organization willing to provide funds to have the need

    satisfied.

    It is the people (project manager and project team), not the procedures

    and techniques, that are critical to accomplishing the project objective.

    Procedures and techniques are merely tools to help the people do their

    jobs.

  • 8/13/2019 LO-1A-1

    3/62

    Examples of Projects

    Planning a wedding

    Designing and implementing a computer system

    Hosting a holiday party

    Designing and producing a brochure

    Executing an environmental clean-up of a contaminated site

    Holding a high school reunion

    Performing a series of surgeries on an accident victim

  • 8/13/2019 LO-1A-1

    4/62

  • 8/13/2019 LO-1A-1

    5/62

    Phases of the Project Life Cycle 1

    The first phase involves the identification of a

    need, problem, or opportunity.

    The need and requirements are usually written by the customer into

    a document called a request for proposal (RFP).

  • 8/13/2019 LO-1A-1

    6/62

  • 8/13/2019 LO-1A-1

    7/62

    Phases of the Project Life Cycle 3

    The third phase is performing the project.

    Different types of resources are utilized

    Results in the accomplishment of the project objective

  • 8/13/2019 LO-1A-1

    8/62

  • 8/13/2019 LO-1A-1

    9/62

    The Project Management Process

    The project management process means planning the work andthen working the plan. 7 steps of planning

    1. Clearly define the project objective.

    2. Divide and subdivide the project scope into major pieces3. Define the specific activities for each piece (work package)

    4. Graphically portray the activities that need to be performed fro each workpackage in order to accomplish the project objectivein the form ofnetwork diagram.

    5. Make a time estimate for how long it will take to complete each activity resources needed.

    6. Make a cost estimate for each activity.

    7. Calculate a project schedule and budget to determine whether the projectcan be completed within the required time, with the allotted founds, andwith the available resources.

  • 8/13/2019 LO-1A-1

    10/62

    Project Control Process

  • 8/13/2019 LO-1A-1

    11/62

    Work Breakdown Structure (WBS)

    The second step is to determine whatactivities need to be performed.

    A list of all the activities must be developed. The WBS is a hierarchical tree of end items tobe accomplished.

    A work item is one small piece of the project.

    Awork packageis the lowest-level item.

    http://upload.wikimedia.org/wikipedia/commons/e/eb/Work_Breakdown_Structure_of_Aircraft_System.jpg
  • 8/13/2019 LO-1A-1

    12/62

    http://upload.wikimedia.org/wikipedia/commons/e/eb/Work_Breakdown_Structure_of_Aircraft_System.jpghttp://upload.wikimedia.org/wikipedia/commons/e/eb/Work_Breakdown_Structure_of_Aircraft_System.jpg
  • 8/13/2019 LO-1A-1

    13/62

    Microsoft Project WBS

  • 8/13/2019 LO-1A-1

    14/62

    1. Start new project

    Turn on the Project Guide

    On the Toolsmenu, click Options, and then click the Interface

    tab.

    In the Project Guide settingssection, select the DisplayProject Guidecheck box.

    Manually set up a new project

  • 8/13/2019 LO-1A-1

    15/62

    ProjectProject Information

    orViewTurn on project guide

    http://office.microsoft.com/en-us/project/HA102639631033.aspx

    http://office.microsoft.com/en-us/project/HA102639631033.aspxhttp://office.microsoft.com/en-us/project/HA102639631033.aspxhttp://office.microsoft.com/en-us/project/HA102639631033.aspxhttp://office.microsoft.com/en-us/project/HA102639631033.aspx
  • 8/13/2019 LO-1A-1

    16/62

    Tools - Options

  • 8/13/2019 LO-1A-1

    17/62

  • 8/13/2019 LO-1A-1

    18/62

    2. Tasks

    There are four major types of tasks:

    1. Summary tasks - contain subtasks and their related

    properties

    2. Subtasks- are smaller tasks that are a part of a

    summary task

    3. Recurr ing tasks - are tasks that occur at regular

    intervals

    4. Milestones- are tasks that are set to zero duration

    and are like interim goals in the project

  • 8/13/2019 LO-1A-1

    19/62

    Add tasks

  • 8/13/2019 LO-1A-1

    20/62

    Insert new task

  • 8/13/2019 LO-1A-1

    21/62

    Outlining tasks

  • 8/13/2019 LO-1A-1

    22/62

    ToolsOptions - check Show project summary task

  • 8/13/2019 LO-1A-1

    23/62

  • 8/13/2019 LO-1A-1

    24/62

    Predecessor

  • 8/13/2019 LO-1A-1

    25/62

    Tasks can be linked in four ways

    Finish-StartFS Predecessor finishes and the other

    starts

    Start-FinishS-F Task begins at the same time as its

    predecessor

    Finish-FinishF-F Both tasks finish at the same time

    Start-StartS-S Start of the predecessor determines

    when the other starts

  • 8/13/2019 LO-1A-1

    26/62

    Constraints

    Certain tasks need to be completed within a

    certain date.

    Intermediate deadlines may need to be

    specified.

    By assigning constraints to a task you can

    account for scheduling problems.

    There are about 8 types of constraints andthey come under the flexible or inflexible

    category.

  • 8/13/2019 LO-1A-1

    27/62

  • 8/13/2019 LO-1A-1

    28/62

    3. Managing task

  • 8/13/2019 LO-1A-1

    29/62

    Defining a Timeline

    Find an optimistic value, D(o),

    a pessimistic value, D(p) and

    a realistic value, D(r) .

    Then: Duration = ( D(o) + D(p) + 4 x D(r) ) / 6

  • 8/13/2019 LO-1A-1

    30/62

    The importance of tracking progress

    Techniques to manage projects effectively: Critical Path Management (CPM)and

    Program Evaluation and Review Techniques (PERT).

    They are similar and you will now often find the technique referred to as:CPM/PERT.

    The technique involves using network models to trace the links betweentasks and to identify the tasks which are critical to meeting the deadlines.Once you've identified the critical path, any delay on any part of the criticalpath will cause a delay in the whole project.It is where managers must concentrate their efforts.

    In MS Project, you use the Tracking Ganttdiagram to show the criticalpath in red and you can see the PERT diagram by looking at the Networkview.

    http://www.profsr.com/msproject/msproj05.htmhttp://www.profsr.com/msproject/msproj05.htmhttp://www.profsr.com/msproject/msproj05.htmhttp://www.profsr.com/msproject/msproj05.htmhttp://www.profsr.com/msproject/msproj05.htmhttp://www.profsr.com/msproject/msproj05.htm
  • 8/13/2019 LO-1A-1

    31/62

    Gantt Chart Viewcritical path

    A Gantt chartis a type of bar chartthat illustrates a

    project schedule.

    Critical path: ViewMore views - Detail Gant

    http://en.wikipedia.org/wiki/Bar_charthttp://en.wikipedia.org/wiki/Schedule_(project_management)http://en.wikipedia.org/wiki/Schedule_(project_management)http://en.wikipedia.org/wiki/Bar_chart
  • 8/13/2019 LO-1A-1

    32/62

    PERT diagram - Network view

  • 8/13/2019 LO-1A-1

    33/62

    Views

    Views allow you to examine your project from

    different angles based on what information you want

    displayed at any given time.

    You can use a combination of views in the same

    window at the same time.

    Project Views are categorized into two types:

    Task Views (5 types)

    Resource Views (3 types)

  • 8/13/2019 LO-1A-1

    34/62

    Saving a baseline

    Baseline plan: The original project plans used to

    track progress on a project.

    The baseline plan is a snapshot of your schedule at

    the time that you save the baseline and includes

    information about tasks, resources, and assignments.

    You can set a baseline for your project, enabling you

    to compare your progress with the original plan and

    any additional baselines you set at milestonesthroughout your project.

  • 8/13/2019 LO-1A-1

    35/62

    Saving a Baseline

    ToolsTrackingSave Baseline

    http://office.microsoft.com/home/video.aspx?assetid=ES102776241033&width=1024&height=768&startindex=0&CTT=11&Origin=HA102751251033&app=WINPROJ&ver=12

    http://office.microsoft.com/home/video.aspx?assetid=ES102776241033&width=1024&height=768&startindex=0&CTT=11&Origin=HA102751251033&app=WINPROJ&ver=12http://office.microsoft.com/home/video.aspx?assetid=ES102776241033&width=1024&height=768&startindex=0&CTT=11&Origin=HA102751251033&app=WINPROJ&ver=12http://office.microsoft.com/home/video.aspx?assetid=ES102776241033&width=1024&height=768&startindex=0&CTT=11&Origin=HA102751251033&app=WINPROJ&ver=12http://office.microsoft.com/home/video.aspx?assetid=ES102776241033&width=1024&height=768&startindex=0&CTT=11&Origin=HA102751251033&app=WINPROJ&ver=12
  • 8/13/2019 LO-1A-1

    36/62

    RESOURCES

  • 8/13/2019 LO-1A-1

    37/62

  • 8/13/2019 LO-1A-1

    38/62

  • 8/13/2019 LO-1A-1

    39/62

    Fields in the Resource Sheet may be blank or contain different types of information

    depending on the type of resource. For example, a work resource doesn't have a Materiallabel, and costs are calculated initially as dollars per hour. Material resources have a costper unitper pound, gallon, or pieceand the Material label field defines the units. Costresources receive a value only when you assign them to tasks.

  • 8/13/2019 LO-1A-1

    40/62

  • 8/13/2019 LO-1A-1

    41/62

  • 8/13/2019 LO-1A-1

    42/62

    Use the Detail Gantt view to find

    slack (float)

    On the Viewmenu, click More Views.

    In the Viewslist, click Detail Gantt, and then

    click Apply. On the Viewmenu, point to Table, and then

    click Schedule. In the chart portion of the

    view, slack appears as thin bars to the right of

    tasks, with slack values adjoining the regularGantt bars.

  • 8/13/2019 LO-1A-1

    43/62

  • 8/13/2019 LO-1A-1

    44/62

    To shorten a project schedule

    Reduce duration of activities on critical path

    More resources

    Change their scope

  • 8/13/2019 LO-1A-1

    45/62

  • 8/13/2019 LO-1A-1

    46/62

  • 8/13/2019 LO-1A-1

    47/62

  • 8/13/2019 LO-1A-1

    48/62

    Create a budget for your project

    Step 1: Create budget resources for your

    project

    Step 2: Assign the budget resources to the

    project summary task

    Step 3: Enter values for the budget resources

    Step 4: Categorize resource costs according

    to their budget type Step 5: Group resources to view how they

    compare against the budget

  • 8/13/2019 LO-1A-1

    49/62

    Step 1: Create budget resources for

    your project

    Create Budget-Travel and Budget-Labor on your resource

    sheet

    ViewResource Sheet

  • 8/13/2019 LO-1A-1

    50/62

    Checkthe check

    box forBudget

  • 8/13/2019 LO-1A-1

    51/62

    Step 2: Assign the budget resources

    to the project summary task

    Gent chart viewToolsOptionsViewTabShow

    project summary task(check box)

    Task is added to the top of the project list. Select this task.

    Click on Button Assign Resources Select the two budget resources you created earlier and

    click Assign

  • 8/13/2019 LO-1A-1

    52/62

    Step 3: Enter values for the budget

    resources

    ViewResource Usage view

    Add Budget Cost and Budget Work fields (columns):

    InsertColumnBudget Cost and Budget Work

    Add values for travel and Labor cost

  • 8/13/2019 LO-1A-1

    53/62

  • 8/13/2019 LO-1A-1

    54/62

    Step 4: Categorize resource costs

    according to their budget type

    Create custom filed (column)

    Open Resource Sheet view

    ToolsCustomizeFields

    Choose Resource text filed and rename: Budget Type

  • 8/13/2019 LO-1A-1

    55/62

    Select OptionButton: Roll down unless

    manually enteredAdd field to the resource sheet view: InsertcolumnchooseBudget Type column ( you can now identify your resources as laboror travel

  • 8/13/2019 LO-1A-1

    56/62

    S G i h

  • 8/13/2019 LO-1A-1

    57/62

    Step 5: Group resources to view how

    they compare against the budget

    Resource Usage view

    ProjectGroup by: No GroupCustomize Group By -

    Select the Budget Type field

  • 8/13/2019 LO-1A-1

    58/62

  • 8/13/2019 LO-1A-1

    59/62

    Viewing Project Cost Information

    Right click the Select All button and click Cost

    Or

    ViewTable: EntryCost

  • 8/13/2019 LO-1A-1

    60/62

    Reports

    Cost Report: Reports - ReportsCostsCash Flow:

    EditColumn list

    Project Summary report: ReportsOverviewProject

    Summary

  • 8/13/2019 LO-1A-1

    61/62

    Resource Usage Report

  • 8/13/2019 LO-1A-1

    62/62

    Current Activity Reports