LEGAL COMPLIANCE - flp.co.za Presentations/2011... · O c c u p a t i o n al H e a l t h An d S a f...
Transcript of LEGAL COMPLIANCE - flp.co.za Presentations/2011... · O c c u p a t i o n al H e a l t h An d S a f...
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
LEGAL COMPLIANCEOFALL
HAZARDOUS LOCATIONSINTERMS OF THE
OCCUPATIONAL HEALTH AND SAFETY ACT
Presented by: MEL WILMANSHazardous Locations Consultant
Act 85 of 1993
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
TOPICS• A.) INTRODUCTION
• B.) HAZLOC LEGAL REQUIREMENT i.t.o OHS Act. (Act 85 of 1993)
• B.1) Act (Definitions)• B.2) Responsibilities
• C.) CERTIFICATE OF COMPLIANCE (E.I.R.)• C.1) History of the C.o.C• C.2) Authority for issuing the C.o.C (as per SANS 10142-1 Annex P)• C.2) What is a certificate of compliance ?• C.3) Why must a C.o.C be issued ?• C.4) When must it be issued ?• C.5) What supporting documentation must submitted with certificate?• C.6) Who can issue the C.o.C ?• C.7) Record keeping
• D.) INSPECTIONS - HAZLOC (PLANT) (E.M.R. Section 8 and SANS10086-1)
• D.1) Management actions• D.2) Plant
• E.) SERIOUS CONCERNS (Limitations with legislation)• E.1) Engineering Staff• E.2) Registered persons• E.3) Registered M.I.E’s
• F.) SUMMARY / CONCLUSION
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
T H E C O M P L I A N C E O F A NE L E C T R I C A L I N S TA L L AT I O N
I S T H E OW N E R ’ SR E S P O N S I B I L I T Y ( E . I . R 2 0 0 9 ) .
T H I S AC C O U N TA B I L I T YC A N N OT B E H A N D E D O R
D E L I G AT E D T O S U B - O R D I N AT E S
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
OCCUPATION HEALTH
AND SAFETY ACT
OCCUPATION HEALTH
AND SAFETY ACT(Act 85 of 1993)
IN TERMS OF
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
- Section 39 of the ACT
MUST PROVE, by having
RECORDS, of
COMPLIANCE
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
ELECTRICALINSTALLATION
REGULATION
ELECTRICALINSTALLATION
REGULATIONWiring of premises (2009)
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
“point of consumption”
D E F I N I T I O N S
“point of control”
“point of outlet”
“point of supply”
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
B.2) RESPONSIBILITY
(1) The user or the lessor of theelect r ica l insta l la t ion, as the case maybe, shal l be responsib le for the safety ,
safe use and maintenance of theelect r ica l insta l la t ion he or she uses or
leases and, except for work aspermi t ted in regulat ion 11 (3) , shal l not
tamper with or al low any tamperingon any insta l la t ion whether or not acer t i f icate of compl iance has been
issued
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
Cable gland Ex e,but motor Ex d ???
Name platemissing
Open entryhole
Dent on cooling fanrestrict air flow
GENERAL CONDITIONUNSAFE FOR USE
Manufacturer ID plate (noinformation)
FLAMEPATH ?
Rust
Cover bolt missing
PROOF THAT NOINSPECTIONS , ORPROPER CLEANINGWERE EVER DONE ONUNIT
UNIT INSTALLEDIN A ZONE 21
LOCATION
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
IN SHORT:
Each user of an electr icalinstal lat ion is RESPONSIBLE for the
safe use and maintenance, of theinstal lat ion under his/her control ,
and WILL have a VALID cert i f icate ofcompliance for every such
instal lat ion.
B.2) RESPONSIBILITY
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
OF ALL PERSONS INVOLVED IN HAZLOC PROCESS
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
MANAGEMENT ( A N D / O R G M R 2 . 1 )
SYSTEM ENGINEER ( R E S P O N S I B L EP E R S O N )
REGISTERED PERSON (S) M . I . E ’ S
ENGINEERING , MAINTENANCE ANDOPERATING STAFF
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
• Enforcement and maintaining of a l llegal requirements
• Area classi f icat ion Approval
• Personnel (Training, Appointments)
• Budget
• Lead by example
MANAGEMENT ( and/or GMR 2.1)
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
• All Plants ( ful ly compliant)
• Documentation and Certi f icate ofcompliance (per area)
• All modif icat ions wel l control led
• Inspection and maintenanceschedules in place
• Regular feedback to management
• Development and implementation ofprocedures and standards
SYSTEM ENGINEER (R.Person)
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
• Test and issuing of C .o.C’s
• Assist with area c lassi f icat ions
• Inspections (al l types)
• Involved in plant maintenance
• Supervise / Control e lectricalmodif icat ions
REGISTERED PERSON(s) M.I.E’s
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
• Design approved modif icat ions
• Preser vat ion of documentat ion andcert i f i cat ions
• Mainta in standards & requirements
• Electronic capture of lega ldocumentat ion
• Operate p lant as per OEM requirements
Engineering, Maintenance andOperating staff
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
OHS Act and Codes of
Practice
OHS Act and Codes of
Practice(Act 85 of 1993)
IN TERMS OF
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
C.) Certificate of Compliance - Section 9
C.4) Process for issuing a C.o.C
C.6) Why is a C.o.C needed ?
C.9) Who may issue a C.o.C ?C.8) What documents must support the C.o.C ?
C.10) When can a C.o.C be issued ?
C.7) What test is required to issue a C.o.C ?
C.11) C.o.C on a low energy(IS) system ?
C.2) Owner responsibility
C.5) What does the C.o.C consist off?
C.1) History of the C.o.C
C.3) What is a C.o.C ?
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
E.I.R of 1992 introduced the new C.o.C, single page, also The introduction of the ‘new accredited person’ or also known as
the wireman Responsibility shift from municipality inspectors to accredited
persons, but.. Window period of 2 years to register for new M.I.E’s to fill gap,
C.1) History of C.o.C
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
The requirements for the FIRST Master Installation Electricianswas:
• Registered Installation electrician for 2 years• Proof of experience (5 years) in hazloc environment• Letter from employer to validate experience in classified plants• ?????
C.1) History of C.o.C (cont.)
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
( 1 . ) S u b j e c t t o t h e p r o v i s i o n s o fs u b - r e g u l a t i o n ( 3 ) e v e r y u s e r o r
l e s s o r o f a n e l e c t r i c a l i n s t a l l a t i o n ,a s t h e c a s e m a y b e , s h a l l h a v e a n
o r i g i n a l v a l i d c e r t i f i c a t e o fc o m p l i a n c e i n t h e f o r m o f a n n e x u r e4 , w h i c h s h a l l b e a c c o m p a n i e d b y at e s t r e p o r t i n t h e f o r m a t a p p r o v e d
b y t h e c h i e f i n s p e c t o r , i n r e s p e c t o fe v e r y s u c h e l e c t r i c a l i n s t a l l a t i o n :
C.2) Owner Responsibility
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
I t ’ s a d e c l a r a t i o n o fs a f e t y i s s u e d b y a
c o m p e t e n t ( r e g i s t e r e d )p e r s o n i n t e r m s o f t h ei n s t a l l a t i o n h e / s h e i s
r e s p o n s i b l e a f t e re l e c t r i c a l i n s t a l l a t i o n
w o r k w a s d o n e .
C.3) What is a C.o.C ??
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
T Y P E o f I N S T A L L A T I O N
EXISTING PLANT
Conduct detailed Risk Assessment (followclassification process). Does the RAconstitutes that the plant MUST beclassified in terms of SANS 10108
NEW PLANT
Conduct C.o.C required testing and completedocumentation, complete with TEST REPORT
Have certified Ex Equipment been installed
Ex Equipment in order (all with valid certifiedcertificates, documentation)
NO
Replace non-approved equipmentwith certified type;
all repairs /replacements must
be in line withstandards and
installed bycompetent staff
Apply rules fornormal
electricalinstallations..
HAZLOC Committeeto classify by applyingClassification Process
to required Zoning,and has managementapprove classification
of areasHave all non-compliances be rectified and is the plant
ready to be tested to have a VALID C.o.C issued
Compile all documentation (drawings, test certificates, OEMinstructions, inspection schedules.) per area, into plant file
NO
BUT, never inspected - Re-certify ExEquipment or replace with new approved type
YESAre VALID C.o.C’sissued & available @all points of control
Have all HIGH risk areas been classified, andbeen approved by Management
NOYESYES
YESYES
NO
YES
YES
NO
NO
Plant owner can relax for now, but compliance status MUST bemaintained, by regular inspections, and by competent staff.
All modifications MUST also be well managed and documented
NO
NO
YES
NO
YES
YES
NOTE:
Inform managementabout the risk of
possible explosionsand their
responsibilities
NO
Planned inspections program developedand linked to maintenance system
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
T Y P E o f I N S T A L L A T I O N
EXISTING PLANT
Conduct detailed Risk Assessment (follow classification process), onthe new plant taking into account, the possibility of an uncontrolled
explosion happening..
Does the RA constitutes that the plant MUST be classified in terms ofSANS 10108
NEW PLANT
Conduct C.o.C required testing and completedocumentation, complete with TEST REPORT
Ex Equipment in order (all with valid certificates, testreports, etc.)
Refer back tosuppliers. Replace un-approved equipmentwith certified type, allrepairs / replacements
must be in line withapplicable standards
Apply rules for normalelectrical installations..
HAZLOC Committee toclassify by applying
Classification Processto required Zoning,
and has managementapprove classification
of areasHave all non-compliances be rectified and is the plantready to be tested to have a VALID C.o.C issued
Compile all documentation (drawings, test, IAcertificates, OEM instructions, inspection
schedules.) per area, into plant file
YES
Have all possible HIGH risk areasbeen classified, and approved by
Management
NOYESYES
YES
NO
YES
YES
NO
NO
NO
YES
NO
NOTE:
Inform management about the risk ofpossible explosions and their
responsibilities
NO
YES
Plant owner can relax for now, but compliance status MUST bemaintained, by regular inspections, and by competent staff.
All modifications MUST also be well managed and documented
Planned inspections programdeveloped and linked to
maintenance system
Will approved Ex Equipment been installed, as perengineering specifications
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
Section 1 – Location (physical details)
Section 2 – Installation (technical info)
Section 3 - Description of Installation (quantities)
Section 4 - Inspection and Testing
Section 5 – Responsibility (design, material, construction, MIE)
C.5) Info on C.o.C
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
It’s a legal requirement, issued by a registered person
Ensure compliance of the electrical installation
Peace of mind for management to maintain safety integrity
Electrical Supplier may request it (Eskom, Municipality, etc)
Basic principle for a safe electrical environment
Chief Inspector of Machineries prescribed format of proof
C.6) Why a C.o.C ?
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
Back to basics:
OHM’s LAW
C.7) What tests?
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c tO c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
Earth ing and bonding (Test 1 & 2)
Ear th fau l t loop impedance (Test 4)
Insulat ion Resis tance (Test 7)
Vol tages (no load, fu l l load, fur thestconnect ion) (Test 8 ,9,10)
Vol tage Neutra l to Ear th (Test 5)
C.7) What tests are required?
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
The test report (as required by the E.I.R)
The calibration certificates of all used test equipment
Additional certificate (section 8.8.2) for a hazardous location
The attached Hazloc classification report & approval
All installed equipment’s OEM certification & local IA certification
Detail scope of project or upgrade (modification)
All supporting documentation (drawings, schematics)
The M.I.E’s proof of registration @ D.o.L
C.8) Supporting documents?
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c tO c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
O N LY a c o m p e t e n tp e r s o n r e g i s t e r e d a s aM . I . E a n d a p p o i n t e d b yt h e C h i e f I n s p e c t o r o f
M a c h i n e r y
C.9) Who can issue?
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
When the M.I.E is satisfied and confirmed that all defectshave been cleared, and accepted by the owner
When all documentation have been obtained
All test results within required values
The installation adhered to the requirements of therequired codes of practice,
All IS loops have been approved and verified
C.10) When ?
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
A C . O . C . w i l l b e n o t b e r e q u i r e d f o r t h ef o l l o w i n g c a s e s , b u t t a k e n o t e o f t h e
s p e c i f i c c o m p e t e n c e r e q u i r e m e n t s i ne a c h c a s e f o r h a z a r d o u s l o c a t i o n s .
C.11) C.o.C on low energy systems
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
4 - 2 0 m A I n t r i n s i c s a f e E x i ( o r E xe , d , n , m , p , e t c ) l o o p s i n t o h a z a r d o u sl o c a t i o n s ( Z o n e 0 , 1 , 2 , o r 2 0 , 2 1 , 2 2 )N o C O C r e q u i r e d , b u t i n s t a l l a t i o na n d d o c u m e n t a t i o n m u s t b e s i g n e do f f b y a p e r s o n c o m p e t e n t i nH a z a r d o u s l o c a t i o n s , a n d n o r m a lQ A / Q C .
4 - 2 0 m A n o n - I S l o o p s i n t o s a f e a r e a -N o C O C r e q u i r e d , n o r m a l Q A / Q C .
C.11) C.o.C on l.e systems (cont.)
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
2 4 V D C ( o r a n y o t h e r l o w e r t h a n 5 0 V )i n s t r u m e n t l o o p s ( e . g . S o l e n o i d s ) i n t oh a z a r d o u s a r e a
- N o C O C r e q u i r e d , b u t i n s t a l l a t i o na n d d o c u m e n t a t i o n m u s t b e s i g n e do f f b y a p e r s o n c o m p e t e n t i nH a z a r d o u s l o c a t i o n s , a n d n o r m a lQ A / Q C .
2 4 V D C ( o r a n y o t h e r l o w e r t h a n5 0 V ) i n s t r u m e n t l o o p s ( e . g .S o l e n o i d s ) i n t o s a f e a r e a
- N o C O C r e q u i r e d , n o r m a l Q A / Q C
C.11) C.o.C on l.e systems (cont.)
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
1 1 5 V A C ( o r a n y o t h e r h i g h e r t h a n5 0 V ) i n s t r u m e n t l o o p s ( e . g . s o l e n o i d s )i n t o h a z a r d o u s a r e a
- C O C r e q u i r e d w i t h H a z a r d o u sL o c a t i o n a d d i t i o n a l f o r m s i g n e d o f fb y a M a s t e r I n s t a l l a t i o n E l e c t r i c i a n( r e g i s t e r e d w i t h t h e D O L ) , a n dn o r m a l Q A / Q C .
1 1 5 V A C ( o r a n y o t h e r h i g h e r t h a n5 0 V ) i n s t r u m e n t l o o p s ( e . g . s o l e n o i d so r E / I i n t e r f a c e ) i n t o s a f e a r e a- C O C r e q u i r e d , a n d n o r m a l Q A / Q C .
C.11) C.o.C on l.e systems (cont.)
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
2 4 V D C , 1 1 5 V A C ( o r a n y o t h e r ) p o w e rs u p p l y f e e d i n t o h a z a r d o u s a r e a- C O C r e q u i r e d w i t h H a z a r d o u sL o c a t i o n a d d i t i o n a l f o r m s i g n e d o f f b ya M . I . E ( r e g i s t e r e d w i t h t h e D O L ) , a n dn o r m a l Q A / Q C .
2 4 V D C o r 1 1 5 V A C ( o r a n y o t h e r )p o w e r s u p p l y f e e d i n t o s a f e a r e a- C O C r e q u i r e d a n d n o r m a l Q A / Q C . "
C.11) C.o.C on l.e systems (cont.)
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
ELECTRICALMACHINERY
REGULATION
ELECTRICALMACHINERY
REGULATIONS E C T I O N 9 - - E l e c t r i c a l M a c h i n e r y i n H a z a r d o u s L o c a t i o n s
( 2 0 1 1 )
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
ELECTRICAL MACHINERY REGULATION
Regulation 9.1 - Classification of potential areas– I d e n t i f y a l l p o t e n t i a l a r e a s– M a n a g e m e n t t o a p p r o v e c l a s s i f i c a t i o n
Regulation 9.8 - Inspection period– I n s p e c t e d a n d Te s t e d n o t e x c e e d i n g 2 4 m o n t h s o r
l e s s , a s r e q u i r e d
Regulation 9.9 - Competency and Records– C o m p e t e n t p e r s o n– T e s t c e r t i f i c a t e s , s c o p e o f w o r k , a r e a
c l a s s i f i c a t i o n , u p d a t e d p l a n t l a y - o u td r a w i n g s , a l l c e r t i f i e d e q u i p m e n tl i s t e d i n r e c o r d b o o k a n d t h eC e r t i f i c a t e o f c o m p l i a n c e f o r t h ei n s t a l l a t i o n
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
APPLICABLE CODES OF PRACTICE
SANS 10108 of 2007 (Ed 6)The c lass i f i cat ion of Hazardous Locat ions
SANS 60079 – 10-1 of 2008E lectr ica l equipment for explos ive gasatmospheres
SANS 1086 – 1 of 2003The insta l lat ion inspect ion and maintenanceof equipment used in explos ive atmospheres
SANS 10142 – 1 of 2006(Amdt 7)The wir ing of premises
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
SANS 10086 - 1SANS 10086 - 1T h e i n s t a l l a t i o n , i n s p e c t i o n a n d m a i n t e n a n c e o f
e q u i p m e n t u s e d i n ex p l o s i ve a t m o s p h e re s
Pa r t 1 : I n s t a l l a t i o n s i n c l u d i n g s u r f a c ei n s t a l l a t i o n s o n m i n e s
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
SECTION 1 SCOPE:T h e s t a n d a r d c o v e r s t h e
i n s t a l l a t i o n , i n s p e c t i o n a n dm a i n t e n a n c e o f e l e c t r i c a l a n d
m e c h a n i c a l e q u i p m e n t t o b e u s e d i na p p l i c a t i o n s i n c l u d i n g s u r f a c e
i n s t a l l a t i o n s o n m i n e s , i na t m o s p h e r e s t h a t m i g h t b e e x p l o s i v e
b e c a u s e o f t h e p r e s e n c e o f g a s e s ,v a p o u r s , m i s t , d u s t s o r f i b r e s t h a ta r e f l a m m a b l e i n t h e p r e s e n c e o f
a t m o s p h e r i c o x y g e n .
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
SECTION 12 INSPECTION & MAINTENANCEOF ELECTRICAL INSTALLATIONS IN
HAZARDOUS LOCATIONS :
S e c t i o n 1 2 . 1 . 1 D O C U M E N TAT I O N
S e c t i o n 1 2 . 1 . 2 Q UA L I F I C AT I O N O F P E R S O N N E L
S e c t i o n 1 2 . 1 . 3 I N S P EC T I O N S
S e c t i o n 1 2 . 1 . 1 0 G E N E R A L G U I DA N C E N OT E S TO T H EI N S P EC T I O N S C H E D U L E S
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
SECTION 12.1.1 DOCUMENTATION:
Up to date details of the following items shall be available:
a.) the classification of hazardous areas (see SANS 10108);(REPORT, DRAWINGS)
b.) the equipment group and temperature class;
c.) sufficient records to enable explosion-protected equipmentto be maintained in accordance with its type of protection (for
example, list and location of equipment, spares, technicalinformation); and
d.) the route of underground cables.
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
SECTION 12.1.2 QUALIFICATION OF PERSONNEL:
The inspect ion and maintenance o finsta l l a t ions sha l l be carr ied out on ly bycompetent personne l whose tra in ing hasinc luded instruct ion on the var ious types
of protect ion and insta l l a t ion pract ice ,re levant ru les and regu lat ions and the
genera l pr inc ip les o f area c lass i f i cat ion .
Appropr iate re fresher tra in ing sha l l beg iven to such personne l on a regu lar
bas i s .
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
SECTION 12.1.3 INSPECTIONS:Before plant or equipment in a
hazardous area is brought into service ,it shal l be given an init ia l inspection
and shal l subsequently be re- inspectedperiodical ly to ensure that theinstal lat ion is maintained in a
condit ion that is sat is factory forcontinued use
12.1.3.2 Types of inspection
12.1.3.3 Grades of inspection
Initial, Periodic, Sample and Special
Visual, Close & Detailed
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
SECTION 12.1.10 GENERAL GUIDANCE NOTESTO THE INSPECTION SCHEDULES:
a.) Equipment that is appropriate to area classification:b.) Equipment group is correct:c.) Equipment maximum surface temperature is correct:d.) Equipment circuit identificatione.) Cable entry devices.f.) Type of cable is appropriateg.) Sealing (trunking, ducts, pipes or conduits)h.) Overcurrent (protection):i.) Warning devices and signs
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
STAFF LIMITATIONSIN TERMS OF THE ELECTRICAL INSTALLATION REGULATIONS (2009)
FACTS !
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
Do not understand information required for a VALID C.o.C
Have never witnessed the required test conducted by acontractor, to validate the results !
Has never seen the new C.o.C format (six page)
Never read or understands the new EIR or the SANS 10142-1 Code
Their responsibility is un-known i.t.o the new regulation(especially in the electrical field)
Has never attended any training in this field (or practical's)
Don’t know that an A.I.A, or Competent Person MUST beappointed on all new installation above 25 kVA
E.1) Engineering StaffL I M I T A T I O N S - A B I L I T Y – A T T I T U D E - C O M M I T M E N T
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
Do not understand information required for a VALID C.o.C Don’t know what test results must be obtained, in order to
issue a VALID C.o.C Doesn’t have the correct calibrated test equipment to conduct
the required tests Never read or understand the new EIR or the SANS 10142-1 Code Doesn’t know their responsibility i.t.o the new regulations
Has never attended any training in this field (or practical's) Skill’s transfer does not happen….(WHY ??)
E.2) Registered Persons
Don’t know that an A.I.A, or Competent Person MUST beappointed on all new installation above 25 kVA
L I M I T A T I O N S - A B I L I T Y – A T T I T U D E - C O M M I T M E N T
Currently registered MIE’s and actively involved in industry only 5%
Not obliged to attended any (frequent) training sessions tostay abreast with new legislation or amendments to the codes
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
Have no future in their field of expertise – no professionalstatus (ECA)
E.3) Potential M.I.E’sL I M I T A T I O N S - A B I L I T Y – A T T I T U D E - C O M M I T M E N T
FINALLYNOT ENOUGH M.I.E’s FOR THE MASSIVE WORK LOAD !!!
Current D.o.L registration brochure limits the registration ofnew M.I.E’s, who is capable, highly skilled and experienced
What image does the MIE project in industries
Where should the focus be = technical qualification orpractical ability
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
CONCLUSIONUnderstand the legal requirements and adhere to it, as
soon as possible. (Ensure all required systems in place)
Conduct detailed RISK ASSESSMENT’s to ID areas ofconcern, and classify accordingly
Compile all proof of compliance documentation (meetings,plant walkdowns, inspections, reports, audits etc.)
Train, appoint and equip competent staff
Ensure full compliance by having valid C.o.C’s for all points ofcontrol (Db’s) for normal and specialized electrical installations.
Appoint effective competent people to maintain YOUR plants
Maintain your legal compliance responsibly. . . .
O c c u p a t i o n a l H e a l t h A n d S a f e t y A c t
Thank-you very much !
My Contact details:
Cell : 082 895 6741
Fax : (086) 658 8404
E-mail : [email protected]