Leed, green buildings and what\'s ahead

73
The dot indicates that the slide is presented by Bob Bajko 1

description

An overview of LEED for building owner/manager. Including time line of a LEED EB O+M and CI project and updates reagrding LEED v4 (2012)

Transcript of Leed, green buildings and what\'s ahead

Page 1: Leed, green buildings and what\'s ahead

The dot indicates that the slide is presented by Bob Bajko

1

Page 2: Leed, green buildings and what\'s ahead

Germany

Joined HSB 2008 to lead sustainability efforts

Projects  throughout the US and Europe

Design as well as consulting

All rating systems and low to high level of LEED

Educational and work background: architecture, engineering, real estate consulting, investment and management

Want to use my knowledge today to make you more comfortable with LEED and also tackle some of myths around LEED

2

Page 3: Leed, green buildings and what\'s ahead

Some of you may have participated in the survey, which we sent out last year. To hear from you about what you would like to learn about LEED. 

Wide range of topics. One of them was the economical benefits of LEED. Short overview, so much more, resource will be available online

Before I get into the next charts. This based on CoStar data. One of the largest if not the largest company in the US collecting data about RE sales, rents, buildings.largest company in the US collecting data about RE sales, rents, buildings.

The last couple of years this data was studied to see how LEED and Energy Star buildings are actually performing. This is real data

One of the questions was, who is actually seeking green/LEED space? LEED is trending up in all market segments but particularly in the legal and finance firms. Actually 1/3 of those “ ” t t“green” tenants

3

Page 4: Leed, green buildings and what\'s ahead

This chart reflects what has happened with the increase in demand for green space. 

LEED buildings outperform non LEED buildings in rent despite the economical downturn.

4

Page 5: Leed, green buildings and what\'s ahead

In October 2011 for the first time we had more existing buildings LEED certified then new construction. Not really a surprise, especially looking at the regional market.

McGraw Hill estimates a growth of in green retrofits/renovations from 25% market share to 33% by 2015

The new and existing building markets are quickly getting into LEED. 

LEED EBOM outlast LEED NC in Nov by 15 million sqft. 

5

Page 6: Leed, green buildings and what\'s ahead

Well that might be true in New York, LA or Chicago, but we are in Cleveland. That’s usually the argument I hear a lot when talking about this data.

And yes it’s not the same everywhere. However as you can see here Cleveland is quickly upping it’s games. 

6

Page 7: Leed, green buildings and what\'s ahead

Chicago is know for being a sustainable city with lots of LEED buildings.

This is Chicago vs. Cleveland now

Pay attention to the numbers per million people.

The numbers for Cleveland are much higher for memberships, employees and for ES buildings and registered projects compared to Chicago.

This is Chicago about 4‐5 year ago. Lots of interest, Energy Star as the first step towards being green and has a high amount of LEED projects in the making. In Chicago as well as CA or NY the first push came from state and local government. That’s what we can see here in Cleveland also. 

LEED is coming to Cleveland, actually is already here

7

Page 8: Leed, green buildings and what\'s ahead

LEEDs current status in the region and the building industry

8

Page 9: Leed, green buildings and what\'s ahead

9

Page 10: Leed, green buildings and what\'s ahead

10

Page 11: Leed, green buildings and what\'s ahead

USGBC  ‐ governing body, develops the rating system, “they make the laws”

GBCI – executing body, reviews LEED documentation, administers credentials, “they make sure we follow them”

The USGBC was founded first and started the GBCI 

LEED certification process is ISO 9001 certified 

11

Page 12: Leed, green buildings and what\'s ahead

12

Page 13: Leed, green buildings and what\'s ahead

Ratings system groups – very similar credits / prerequisites and the same LEED Accredited professional (AP) designation

Important to remember buildings are certified and people are accredited

13

Page 14: Leed, green buildings and what\'s ahead

Ratings system groups – very similar credits / prerequisites and the same LEED Accredited professional (AP) designation

Important to remember buildings are certified and people are accredited

14

Page 15: Leed, green buildings and what\'s ahead

Tenant or owner occupied doesn’t matter for those rating systems. LEED commercial interior is for an interior build‐out with no major changes to the main HVAC system or building envelope. So this is what you will typical use when your client or potential tenant asks for a LEED certified space.

There are two kinds:

LEED CI Retail applicable to stores, banks, restaurants, spas AND LEED CI for basicallyLEED CI Retail applicable to stores, banks, restaurants, spas AND LEED CI for basically anything but that. 

This ratings system also considers furniture. We will be exploring it in detail in our next session.

15

Page 16: Leed, green buildings and what\'s ahead

Here is one of our projects for CIGNA insurance, an office in Pittsburgh. 

CIGNA is occupying almost the whole building. We did the interior renovation of the lobby and office space.

16

Page 17: Leed, green buildings and what\'s ahead

Existing building – Operation & Maintenance is probably the other rating system, which you are going to be confronted with. 

It’s also the only rating system, which expires after 5 years. 

You look at actual performance rather than the design of the building.

It’s for all use types as shown on the left.

17

Page 18: Leed, green buildings and what\'s ahead

The so called Performance period is the measuring stick for this certification. You basically monitor how good your are doing. For the initial certification  3‐12 months and a recertification 12 months long.

Your first step in order to get certified is to collect water and energy consumption data for one full year. That’s the basis for the Energy Star rating.  If you haven’t achieved the minimum efficiency, then you have to improve first and then track your energy data again for a whole year. 

Then start implementing your other policies like green cleaning, recycling.

In the start up phase you also want to evaluated your HVAC systems to confirm, if you can achieve the required outside air. 

Al t bli h th LEED h kli t d l LEED tifi d Sil G ld Pl tiAlso establish the LEED checklist and your goal: LEED certified, Silver, Gold, Platinum 

This can be a rather lengthy process.  

18

Page 19: Leed, green buildings and what\'s ahead

The IMG center started in 2007 with the process of LEED certification. It got certified in fall last 2011. 

Also if you have a multi tenant building than you to engage the tenants in order to get the building certified. From my experience the tenants usually like the idea of making a difference. You just have to inform them about what’s going on and how they can help. We facilitate meetings with tenants to initiate the process and get them excited. The more engage, the better the results.

19

Page 20: Leed, green buildings and what\'s ahead

We saw all the rating systems. The LEED volume program is for companies, which made LEED their standard.

The logos on the right are all companies, which are participating in the LEED Volume program. So if they are your client then chances are they want a LEED certified building or space. This program is available for LEED NC, CI, NC/CI Retail and EB O+M

20

Page 21: Leed, green buildings and what\'s ahead

For existing buildings it’s an ongoing verification of compliance, which also ensures recertification

21

Page 22: Leed, green buildings and what\'s ahead

22

Page 23: Leed, green buildings and what\'s ahead

23

Page 24: Leed, green buildings and what\'s ahead

This is what you want to achieve at the end of your certification. The plaque. You might know already there are different levels:Certified, Silver, Gold , Platinum.. The level depends on the points achievedThe numbers below the plaque are the number of projects in Ohio. Most projects now are Gold. 

24

Page 25: Leed, green buildings and what\'s ahead

LEED in Structured in mandatory requirements: MPRs and Prerequisites AND selective credits

Those credits and prerequisites are organized in categories, which are …

You will be seeing the categories more often during the presentation

25

Page 26: Leed, green buildings and what\'s ahead

LEED in Structured in mandatory requirements: MPRs and Prerequisites AND selective credits

Those credits and prerequisites are organized in categories, which are …

You will be seeing the categories more often during the presentation

26

Page 27: Leed, green buildings and what\'s ahead

This is a typical LEED CI score card. 

Prerequisites and Credits are separated into categories based on the area of concern, which they cover

Name categories

27

Page 28: Leed, green buildings and what\'s ahead

There are mandatory and selective elements in LEED. I’ll now talk about the mandatory ones.

28

Page 29: Leed, green buildings and what\'s ahead

There are 7 requirements in total. We have paraphrased the MPRs for you.

the three more tricky ones are highlighted here.

29

Page 30: Leed, green buildings and what\'s ahead

Number 3: Must use a reasonable site boundary

This sounds easy. It is means one project equals one owner. You need to included all areas, which belong to the project and get used during the project. You also can’t certify just a part of a building, unless you comply with certain rules.

30

Page 31: Leed, green buildings and what\'s ahead

Must comply with minimum occupancy rates

1 FTE – Full time equivalent Employee needs to work or live in your building. A parking garage is not eligible for certification. However your building can included parking levels. 

31

Page 32: Leed, green buildings and what\'s ahead

Must comply with minimum occupancy rates

For LEED EBOM the requirements is at least 50% occupied. That gets tricky, as shown here. This building wasn’t meeting the requirements since April 2010. This often gets overlooked, but makes LEED impossible.

32

Page 33: Leed, green buildings and what\'s ahead

Energy and Water Usage Reporting

When you LEED certify a project, you establish a relationship with the USGBC, which we continue on even after construction is finished and you have your plaque. The USGBC is paying close attention to how LEED buildings are performing. So they can further develop LEED based on the data.

That means projects are required to report their consumption and this carries over withThat means projects are required to report their consumption and this carries over with ownership.

The only exemption are LEED CI projects without separate metering for the LEED project space.

__________

Also keep in mind that the reporting starts with 50% occupancy, submit not more than 2 months after that and then every month. You can use the Energy Star portfolio manager to do that.

33

Page 34: Leed, green buildings and what\'s ahead

34

Page 35: Leed, green buildings and what\'s ahead

Prerequisites are required for every project in the selected rating system. Vary based on rating system

This is LEED NC and it’s prerequ per category. 

The prerequisite for Sustainable Site is pretty straight forward. You are basically required to apply the requirements for an EPA permit to all projects, no matter what size.

35

Page 36: Leed, green buildings and what\'s ahead

The water efficiency prerequisite is applicable to all rating systems.

You will need to be 20% below the new code with new and existing fixtures that includes fixtures in or outside the space. 

Retrofits are very likely to be necessary, even if you have already more efficient fixtures.

Low flow vs. regular in new installations  are rather inexpensive.

36

Page 37: Leed, green buildings and what\'s ahead

In our most recently finished project we replaced these existing fixtures, which automatic, low flow fixtures. These are hydropower, which means they do not require batteries (most building manager don’t like to change batteries all the time. Also lots of toxic waste) nor are they hard wired. So no cutting up the wall, new electric. 

This is a very manageable investment, which pays of quick. This installation will reduce the water consumption of those restrooms by more than 40%. 

37

Page 38: Leed, green buildings and what\'s ahead

Commissioning is another prerequisite applicable to all rating system. 

The commissioning agent, a third party engineer, checks our design and the installation on site. That’s beneficial to the owner or tenant because, he makes sure that those fancy CO2 sensors are actually connected to the BAS and reduced the air into the space, when it’s unoccupied. 

Also CFC free refrigerants need to be used. That includes IT room equipment.Also CFC free refrigerants need to be used. That includes IT room equipment.

38

Page 39: Leed, green buildings and what\'s ahead

For LEED EBOM Existing buildings: is based on the actual energy consumption for 1 year. The Energy Star is the result, which also factors in the use, operating hours and weather, so you can compare data. 

LEED CI  has some extra requirements, which you need to discuss with your clients. Their PCs, monitors need to be ES rated, at least 50% and you will need the information about that equipment in order to prove it.

39

Page 40: Leed, green buildings and what\'s ahead

Two things: have a recycling contract, make sure it covers also glass and metals and plastic.

AND

Have enough room to facilitate the program

40

Page 41: Leed, green buildings and what\'s ahead

Indoor Environmental Quality

No smoking allowed in and around the building

Here is a tricky one and this one can get really expensive.

LEED requires you to meet ASHRAE 62.1 2007 , not the standard applicable at year built.

This standard describes the amount of outside air required for a space. Before you even think LEED, you need to make sure you meet this or what it is going to cost you to meet the requirement. 

In existing buildings you most likely run into problems, when increasing occupancy load, if you have old equipment, if you install better air filter. So you may not be able to meet the 2007 standard without expensive replacements, larger ducts or high‐tech controls.

For building owners that means, know how much outside air can be delivered to your space or building.

For broker/tenant representatives, ask early on: Can your building meet ASHRAE 62.1‐2007

41

Page 42: Leed, green buildings and what\'s ahead

42

Page 43: Leed, green buildings and what\'s ahead

Different credit categories and their examples

43

Page 44: Leed, green buildings and what\'s ahead

Two kinds of credits: percentage based (achievement) AND prescriptive credits (meet all requirements and get the credit points)

44

Page 45: Leed, green buildings and what\'s ahead

SS 4.2 Bicycle Storage and changing rooms, certain percentage (5% for LEED NC, CI) of FTE will have bike racks provided, showers

SS 4.4 Parking availability: e.g. provide only as much as required parking spaces, don’t add new parking

SS 2 Development Density: many services and residential units close to the site. Encourages walking

45

Page 46: Leed, green buildings and what\'s ahead

Indoor plumbing AND outdoor irrigation

Typical:

Drip irrigation

Drought resistant plants

Rain water harvesting

Low flow fixtures

Waterless urinals

46

Page 47: Leed, green buildings and what\'s ahead

Not just energy efficiency 

Also controls to improve efficiency (M&V)

The photo shows a programmable thermostat and a CO2 sensor for demand controlled ventilation

Use of alternative/ renewable energy

47

Page 48: Leed, green buildings and what\'s ahead

All about materials

Reuse, Recycled, Renewable

Construction waste recycling provider in the region are very good and can recycled up to 100%

If you can’t reuse materials, use materials with recycled content and renewable materials like cork bamboolike cork, bamboo

48

Page 49: Leed, green buildings and what\'s ahead

This category is about the well being of occupants in the space.  Best direct benefit for occupants.

People like having daylight and views. They are healthier if the air quality is better, so use low emitting materials and prevent construction work from interfering with occupied areas.

The pictures shows a temporary fan put in place during construction, to vent the space separately and remove VOCs

49

Page 50: Leed, green buildings and what\'s ahead

Innovation and Design Category: gain points for overachievement of existing credits for instance 30% recycled content; also new /other strategies e.g. educational programs with signage and case studies

Regional priority Credits:

Extra points for achieving selected credits. The selection is based on the location.

50

Page 51: Leed, green buildings and what\'s ahead

LEEDs current status in the region and the building industry

Cleveland is great to gain Site Selection credits (good public transport, density) and material & resource (recycling and sustainable products)

Still room for improvement in Energy Efficiency 

51

Page 52: Leed, green buildings and what\'s ahead

All the documentation for the credits is provided to an online platform, called LEED Online. It’s not just an FTP site it’s also an interactive tool with pdfs, which will need to be filled out.

52

Page 53: Leed, green buildings and what\'s ahead

53

Page 54: Leed, green buildings and what\'s ahead

The soft costs

$900 for registering the project

$2,500 minimum and up to 25,000 max for reviewing the documents.

The consulting fees depend on type, size, number of phases, level of certification.

54

Page 55: Leed, green buildings and what\'s ahead

55

Page 56: Leed, green buildings and what\'s ahead

I have a new client and they are interested in LEED certified space.  What should I do first? You already took the first step. Being here today will give you the confidence to ask the right questions.  You should consider location for access to public y p g y g y g q ptransportation and community services or the age of the property which could provide insight into the type of systems and fixtures already in place. Or you can always ask an experienced LEED professional for guidance.

I have a short list of potential buildings.  How do I narrow it down?Prepare a list of LEED related questions to determine early on how each property will meet the prerequisites.   How efficient are the plumbing fixtures? Can the HVAC system deliver enough fresh air? Does one property stand out as being more LEED 'friendly'. Property owners, you need to prepare for those questions.

I want to sign the lease but need the assurance that the project will be on time and on budget.There should be a LEED checklist filled out to define the anticipated credits and scope, with a detailed summary of how the building is going to comply with the prerequisites.  All parties should be made aware of any items that may affect the budget or schedule and how they will be dealt with.  The checklist should be attached as an exhibit to the lease because it is often referenced throughout the design and construction of the projectshould be attached as an exhibit to the lease because it is often referenced throughout the design and construction of the project. 

OK. The lease is signed now you can start designing the space. Is there anything else I need to do?The project should be registered with the GBCI and about halfway into the design phase the commissioning agent will have to bebrought on board.

What’s a commissioning agent again? Why do we need him and who hires him?The commissioning agent is a third party engineer hired to verify the design and construction drawings and eventually the contractors work. He is required to be independent from the project design team and is typically hired by the landlord and is part of the contract for construction.

Let’s start construction. What does the general contractor need to consider?The GC received should have received specifications for the LEED work during the bid process. This is important to prepare them for the work and to define their responsibilities.  First, they will need to put waste recycling in place and a management plan to prevent indoor air quality issues for other tenants. This will be tracked throughout the construction process.  They will also be critical in the documentation and submittal process. 

56

Page 57: Leed, green buildings and what\'s ahead

7

The project is done. So where is my plaque?  

At the completion of the work all documents from the construction phase will be need to be submitted for review. Approximately 3 months later you can expect the final results and the opportunity to buy your plaque.

57

Page 58: Leed, green buildings and what\'s ahead

58

Page 59: Leed, green buildings and what\'s ahead

59

Page 60: Leed, green buildings and what\'s ahead

60

Page 61: Leed, green buildings and what\'s ahead

Eligibility = letter of attestationd t d i d b i li t j t t h l ti hi t li tdated, signed by supervisor, client, project manager, teacher; relation ship to applicant

Eligibility requirements:Candidates must have experience in the form of EITHER documented involvement on a project registered or certified for LEED OR employment (or previous employment) in a sustainable field of work ‐Company related to environmentalism or green building industry‐ i.e. job title

OR engagement in (or completion of) an education program that addresses green building principles. ‐ LEED related educational course

Application fee: $50Exam fee (per exam appointment):Members and full‐time students: $150 All others: $200 CMP renewal fee: $50 every two years$ y y

61

Page 62: Leed, green buildings and what\'s ahead

LEED AP:

Application fee: $100Exam fee (per exam appointment): Combined exam: Members: $300 

Non‐members: $450 

Specialty exam only:* Members: $150 

Non‐members: $250 

CMP l f $50 tCMP renewal fee: $50 every two years

Fellow

Eligibility

Nominees must be LEED APs with specialty who have held the LEED AP credential for eight cumulative years. (The 2011 class will be from LEED APs who tested in 2001‐2002 and have enrolled or tested to earn the LEED(The 2011 class will be from LEED APs who tested in 2001 2002 and have enrolled or tested to earn the LEED AP with specialty credential.)

They must document a total of at least 10 years of experience in the green building field. 

Nominees will be required to submit an application package through the LEED Fellow online portal. 

Nomination

Nominees for the LEED Fellow will be nominated by their peers. 

Nominators must be LEED APs with specialty with at least 10 years of experience in the green building field.

Nominators must provide four endorsers who will verify the nominee’s achievements.

62

Page 63: Leed, green buildings and what\'s ahead

The number of LEED APs is increasing rapidly in the region. 

63

Page 64: Leed, green buildings and what\'s ahead

Just like the Real Estate license, a LEED AP has to earn hours, by attending events like this one, project participation, committee work, ect.

64

Page 65: Leed, green buildings and what\'s ahead

65

Page 66: Leed, green buildings and what\'s ahead

66

Page 67: Leed, green buildings and what\'s ahead

1. People are accredited, buildings are certified

2. The USGBC develops the LEED rating system and the GBCI review certifications

67

Page 68: Leed, green buildings and what\'s ahead

3. BD+C, ID+C, EB O+M, ND, Homes  = 5

4. LEED – Commercial Interior is most appropriate since the certification has to be finished shortly after finished construction. LEED EBOM can be consider, if the tenant is occupying most of the building.

68

Page 69: Leed, green buildings and what\'s ahead

5. True. You can use LEED CI, which just certifies the space

6. C. report water and energy consumption is part of the MPR’s. 5 years; also possible answer D. LEED EBOM certifications expire after 5 years

69

Page 70: Leed, green buildings and what\'s ahead

7. False. The restrooms used by the tenant are also to be considered.

8. F all of it. A LEED CI project gets points for locating in a certified building (5 points), having a bus stop close by and therefore incoraging occupants to use the bus, will get you points (6 points for LEED CI), car pool parking in combination with limited parking gets you points, 

also locating in a high density location gains points (5 points)

A fitness center can help you provide the required showers and changing rooms for SS 4.2A fitness center can help you provide the required showers and changing rooms for SS 4.2 Bicycle storage and changing rooms (cleveland bike station, next to quicken loans arena)

70

Page 71: Leed, green buildings and what\'s ahead

9. D Collect energy consumption data. You need to know your Energy Star rating first. You may have to improve upon your rating.

10. C ‐5‐9% Research form McGraw Hill, the USGBC’s own research and our personal experience showed it’s 5‐9%. Our project had 5% increase in construction costs. The more experience the GC and design company the smaller the additional investment costs

71

Page 72: Leed, green buildings and what\'s ahead

11. C ASHRAE 2007, keep that in mind especially if you want to have a certified space in an existing building

12. That depends on who you ask!

72

Page 73: Leed, green buildings and what\'s ahead

73