Laporan Progres Bulanan Periode I SIBADES HMS ITB 2011
-
Upload
darajatbnoviadi -
Category
Documents
-
view
56 -
download
5
Transcript of Laporan Progres Bulanan Periode I SIBADES HMS ITB 2011
LAPORAN PROGRES BULANAN PERIODE I: 1 – 27 OKTOBER 2011
Disusun dalam rangka memenuhi laporan progres bulanan
untuk PT Perkebunan Nusantara VIII tahun 2011/2012.
Nama Proyek : Pembangunan Ruang Kelas, WC, dan Gudang
Nama Lokasi : SDN Puncak Raya
Desa : Margaluyu
Kecamatan : Pangalengan
Kabupaten : Bandung
Provinsi : Jawa Barat
Tahun Proyek : 2011
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Laporan Progres Bulanan / Periode I: 1 – 27 Oktober 2011 Nama Proyek : Pembangunan Ruang Kelas, WC, dan Gudang Tahun 2011/2012
Lokasi Proyek : SDN Puncak Raya
Desa : Margaluyu
Kecamatan : Pangalengan
Kabupaten : Bandung
Provinsi : Jawa Barat
Dalam laporan progres bulanan ini berisikan laporan progres mingguan yang berasal dari pengawas warga setempat dan laporan mingguan keuangan dan pembelian material yang berasal dari bendahara. Rincian isi laporan progres bulanan adalah sebagai berikut:
1. Laporan progres pekerjaan minggu 1 – 4 yang berasal dari pengawas warga setempat. 2. Daftar pembelian material dan alat per minggu. 3. Laporan keuangan yang berisikan pembelian material dan pengeluaran bagi kebutuhan pembangunan fisik. 4. Laporan progres bedasarkan volume pekerjaan yang telah dikerjakan (kurva S). 5. Dokumentasi progres pembangunan
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Laporan Progres Mingguan
Minggu ke-1 Periode 01-06 Oktober 2011
No HariMulai Kerja
Selesai Kerja
Jumlah Pekerja
Cuaca Keterangan
Cerah
9 orang Cerah
16.00 WIB
07.00 WIB 16.00 WIB
Kegiatan Yang Dilakukan
1 Sabtu 01/10/2011
2 Minggu 02/10/2011
Pemasangan Bow-plank
Galian untuk Pondasi
Cerah
Cerah
9 orang Cerah
8 orang Cerah
07.00 WIB 16.00 WIB
9 orang
9 orang
1. Pembuatan Lantai Kerja2. Pemindahan batu kali
07.00 WIB 16.00 WIB
07.00 WIB 16.00 WIB
07.00 WIB 16.00 WIB
07.00 WIB
9 orang
Galian untuk Pondasi
Galian untuk Pondasi
Galian untuk Pondasi dan peberian pasir dasar
6 Kamis 06/10/2011
3 Senin 03/10/2011
4 Selasa 04/10/2011
5 Rabu 05/10/2011
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Minggu ke-2 Periode 08-13 Oktober 2011
No HariMulai Kerja
Selesai Kerja
Jumlah Pekerja
Cuaca Keterangan
6 Kamis 13/10/2011Pasang Batu Pondasi
07.00 WIB 16.00 WIB 9 orang Baik
4 Selasa 11/10/2011 Pasang Batu Pondasi 07.00 WIB 16.00 WIB 9 orang Baik
5 Rabu 12/10/2011 Pasang Batu Pondasi 07.00 WIB 16.00 WIB 9 orang Baik
2 Minggu 09/10/2011 Galian Pondasi 07.00 WIB 16.00 WIB 9 orang Baik
3 Senin 10/10/2011 Galian Pondasi 07.00 WIB 16.00 WIB 9 orang Baik
Kegiatan Yang Dilakukan
1 Sabtu 08/10/2011 Galian Pondasi 07.00 WIB 16.00 WIB 9 orang Baik
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Minggu ke-3 Periode 15-20 Oktober 2011
No HariMulai Kerja
Selesai Kerja
Jumlah Pekerja
Cuaca Keterangan
Baik2. Memotong besi
9 orang Baik
6 Kamis 20/10/20111. Pengecoran dan membuka bekisting
07.00 WIB 16.00 WIB 9 orang
5 Rabu 19/10/2011 07.00 WIB 16.00 WIB
2. Pengecoran Pondasi Tapak
9 orang Baik
9 orang Baik
Pengecoran Pondasi Tapak
Membongkar hasil cor yang salah dan mengecor kembali
4 Selasa 18/10/2011 07.00 WIB 16.00 WIB
3 Senin 17/10/2011 1. Pemasangan besi (merangkai besi) 07.00 WIB 16.00 WIB
9 orang Baik2. Pasang Batu Pondasi Gudang
2 Minggu 16/10/2011 07.00 WIB 16.00 WIB 9 orang
16.00 WIB
BaikPasang Pondasi Gudang
Kegiatan Yang Dilakukan
1 Sabtu 15/10/2011 1. Menyelesaikan Pekerjaan Galian 07.00 WIB
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Minggu ke-4 Periode 22-27 Oktober 2011
No HariMulai Kerja
Selesai Kerja
Jumlah Pekerja
Cuaca Keterangan
Kendala : Ketersediaan air yang terhambat
6 Kamis 27/10/2011Pasang Batu Kali
07.00 WIB 16.00 WIB 9 orang BaikMerangkai Besi
4 Selasa 25/10/2011 07.00 WIB 16.00 WIB 9 orang Baik
5 Rabu 26/10/2011 07.00 WIB 16.00 WIB 9 orang Baik
Pasang Batu Kali dan PengecoranMerangkai Besi
Pasang Batu Kali dan PengecoranMerangkai Besi
2 Minggu 23/10/2011 Pasang Batu Kali dan Pengecoran 07.00 WIB 16.00 WIB 9 orang Baik
3 Senin 24/10/2011 Pasang Batu Kali dan Pengecoran 07.00 WIB 16.00 WIB 9 orang BaikMerangkai Besi
Kegiatan Yang Dilakukan
1 Sabtu 22/10/2011 Pasang Batu Kali 07.00 WIB 16.00 WIB 9 orang Baik
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Daftar Pembelian Alat dan Material
Minggu Ke-1 No Nama Barang, Merk, Type, Jenis yang digunakan Volume Satuan 1 Batu Kali 37 m3 2 Pasir Urug 11,2 m3 3 Pasir Hitam 22,5 m3 4 Seplit 2 m3 5 Kaso 6*6*200 20 Step 6 Semen 55 zak 7 Air 9000 liter 8 Benang Nilon 6 gulungan 9 Kikir 2 buah
10 Water pas 25 meter 11 Besi 6 mm 1 lente 12 Batu gosok 1 buah 13 Pensil 6 buah 14 Jerigen 1 buah 15 Pegangan cangkul 4 buah
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
16 Cangku 4 buah 17 Sekop 2 buah 18 Pembengkok besi 10 mm 1 buah 19 Pembengkok besi 12 mm 1 buah 20 Mesin sagu 1 buah 21 Terpal 4*6 1 buah 22 Terpa 8*12 1 buah 23 Ram kawat (saringan) 1 buah 24 Sarung tangan 8 buah 25 Boot 12 buah 26 Helm 8 buah 27 P3K 1 buah 28 Benang 5 m 29 Paku 7 1 kg 30 Paku 5 1 kg
Minggu Ke-2 No Nama Barang, Merk, Type, Jenis yang digunakan Volume Satuan 1 Batu belah 25,5 m3 2 Pasir Hitam 22,5 m3 3 Seplit 6,2 m3 4 Papan 2/20*300 35 lembar
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
5 Semen 155 zak 6 Air 10000 Liter 7 Pasir Beton 5,44 m3
Minggu Ke-3
Minggu Ke-4
No Nama Barang, Merk, Type, Jenis yang digunakan Volume Satuan1 Batu kali 9.3 m32 Bata Press 16760 buah3 Pasir Hitam 21.2 m34 Pasir Beton 9.4 m45 Seprit 9.4 m56 Besi Pondasi Kelas 700 kg7 Besi D8 Polos 169 batang8 Besi D10 Ulir 162 batang9 Besi D13 Ulir 104 batang
No Nama Barang, Merk, Type, Jenis yang digunakan Volume Satuan1 Bata Press 13000 buah2 Pasir Hitam 11,5 m33 Batu Kali 8,9 m34 Stampel Rotasi 9 buah
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Laporan Keuangan Laporan Keuangan yang berasal dari bendahara yang berisikan pengeluaran bagi pembangunan fisik untuk 3 minggu. Minggu ke-1 (01-06 Oktober 2011), minggu ke-2 (08-13 Oktober 2011), minggu ke-3 (15-20 Oktober 2011), dan minggu ke-4 (22-27 Oktober 2011) Berikut laporan tersebut
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
No Kegiatan Divisi Uang Keluar 1 Cangkul 4pcs Logistik 140,000Rp 2 Sekop 2pcs Logistik 90,000Rp 3 Mesin Sugu Logistik 20,000Rp 4 Terpal 4x6 m Logistik 275,000Rp 5 Gergaji Besi 2pcs Logistik 120,000Rp 6 Ram Ayak 2m Logistik 22,000Rp 7 Pembengkok Besi 2pcs Logistik 20,000Rp 8 Sticker Glossy 5pcs Logistik 30,000.00Rp 9 Sepatu Boot 4pcs Logistik 300,000Rp
10 Helm Proyek 8pcs Logistik 120,000Rp 11 Sarung tangan 8pcs Logistik 24,000Rp 12 Sepatu Boot wing 4pcs Logistik 200,000Rp 13 Kotak P3k + isi Logistik 29,000Rp 14 Jerigen 20L 4pcs Logistik 75,000Rp 15 Kaso 2m 20pcs Logistik 100,000Rp 16 Benang 2pcs Logistik 10,000Rp 17 Terpal 8x12 Logistik 400,000Rp 18 Garpu 1pcs Logistik 45,000Rp 19 Papan 2.5cm 7pcs Logistik 70,000Rp 20 Paku 1kg 7/1/2 5/1/2 Logistik 13,000Rp 21 Doram 4pcs Logistik 30,000Rp 22 Bola Kasur 5pcs Logistik 12,500Rp 23 Batu Kali 37 m3 Logistik 4,440,000Rp 24 Pasir Hitam 11.2m3 Logistik 1,344,000Rp 25 Semen 3roda 55sak Logistik 3,107,500Rp 26 Kerikil (Split) 2m3 Logistik 360,000Rp 27 Sepatu boot 1pc Logistik 50,000Rp
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
28 Helm Proyek 1pc Logistik 15,000Rp 29 Sarung tangan 4pcs Logistik 12,000Rp 30 Kawat beton 5kg Logistik 90,000Rp 31 Ember 2pcs Logistik 10,000Rp 32 Gegep 3pcs Logistik 45,000Rp 33 Palu 2pcs Logistik 26,000Rp 34 Batu Unting Logistik 17,500Rp 35 Jerigen 35L 2pcs Logistik 60,000Rp 36 Patlot 6pcs Logistik 6,000Rp 37 Benang no9 4pcs Logistik 20,000Rp 38 Kikir 2pcs Logistik 44,000Rp 39 Batu Gosok Logistik 10,000Rp 40 2/20 9m 15pcs Logistik 217,500Rp 41 2/20 3m 420m3 35pcs Logistik 507,500Rp 42 Truk Logistik 700,000Rp 43 Semen 3roda 155sak Logistik 8,757,500Rp 44 Pasir Hitam 22.4m3 Logistik 2,688,000Rp 45 Kerikil (Split) 6.2m3 Logistik 1,116,000Rp
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
46 Pasir Beton Kamojang 5.4m3 Logistik 1,026,000Rp 47 Batu Kali 25.5m3 Logistik 3,060,000Rp 48 Pemotong besi Muller Engineering 1,000,000.00Rp 49 Kunci pembengkok besi 5pcs Engineering 390,000.00Rp 50 Baja Tulangan Ulir Dia. 13mmx12mm Logistik 9,708,442Rp 51 Bata Press Garut 6500 buah Logistik 3,445,000Rp 52 Pasir Hitam 21,2 m3 Logistik 2,544,000Rp 53 Bata Press Garut 10260 buah Logistik 5,437,800Rp 54 Pasir Beton Kamojang 4.4m3 Logistik 1,786,000Rp 55 Kerikil Split 9,4 m3 Logistik 1,692,000Rp 56 Baja Tulangan Ulir Dia.13mmx12m Logistik 9,708,442Rp 57 Bata Press Garut 6500 buah Logistik 3,445,000Rp 58 Pasir Hitam 21,2 m3 Logistik 2,544,000Rp 59 Bata Press Garut 10260 buah Logistik 5,437,800Rp 60 Pasir Beton Kamojang 4.4m3 Logistik 1,786,000Rp 61 Kerikil Split 9,4 m3 Logistik 1,692,000Rp
80,491,484Rp
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Laporan Progres Bedasarkan Volume Pekerjaan (kurva S) dan SDM yang digunakan Minggu Ke-1 (01-06 Oktober 2011)
Minggu Ke-2 (08-13 Oktober 2011)
No Uraian Pekerjaan Hasil Pekerjaan Material yg Digunakan Volume1 Persiapan dan pembersihan Lahan 300 m2
Pekerjaan Pondasi:2 Pemasangan Bowplank 76 m3 Galian Pondasi 114 m3
Uraian Minggu Ini S/d Minggu IniMandor 1 orang 6 12Tukang 4 orang 23 23Laden 4 Orang 24 24
Jumlah Pekerja
No Uraian Pekerjaan Hasil Pekerjaan Material yg Digunakan Volume1 Pemasangan Pondasi 31,92 m3 Batu belah 32 m3
Pasir 11 m3Semen 62 zak
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Minggu Ke-3 (15-20 Oktober 2011)
Uraian Minggu Ini S/d Minggu IniMandor 1 orang 6 12Tukang 4 orang 24 47Laden 4 Orang 24 48
Jumlah Pekerja
No Uraian Pekerjaan Hasil Pekerjaan Material yg Digunakan Volume1 Galian Tanah Pondasi 43,2 m32 Pasangan Batu Kali 12 m3 Batu Kali 10,3 m3
Pasir Urug Hitam 6 m3Semen 20 sak
3 Cor Beton Pondasi 7,3 m3 Besi 700 kgPasir Beton 5,5 m3
Semen 49 sak
Uraian Minggu Ini S/d Minggu IniMandor 1 orang 6 18Tukang 4 orang 24 71Laden 4 Orang 24 72
Jumlah Pekerja
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Minggu Ke-4 (22-27 Oktober 2011)
No Uraian Pekerjaan Hasil Pekerjaan Material yg Digunakan Volume1 Pasangan Batu Kali(kelas,wc,dan gudang) 23.32 m3 semen 49 sak
Batu Kali 56 m32 Pondasi Tapak(Wc dan gudang)+ngecor 1.5 m3 Pasir 0.47 m3
Agregat 0.84 m33 Pekerjaan Sloof Kelas 24x8m=192m3 sengkang d 8 248 m
16x8m=128m3 angkur d 10 24 mbaja d 13 320 m
Uraian Minggu Ini S/d Minggu IniMandor 1 orang 6 24Tukang 4 orang 24 95Laden 4 Orang 24 96
Jumlah Pekerja
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Dokumentasi Progres Pembangunan
Minggu Ke-1
Gambar 1.1 Acara Penjelasan Teknis Gambar 1.2 Acara Penyerahan Alat dan Material Gambar 1.3 Ruang Penyimpanan Material
Gambar 1.4 Pak Entis (Mandor) Gambar 1.5 Pak Ade Gambar 1.6 Pak Rahmat Gambar 1.7 Pak - Gambar 1.8 Pak Eya Gambar 1.9 Pak -
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Gambar 1.9 Pak Dadi Gambar 1.10 Pak - Gambar 1.11 Pak - Gambar 1.12 Pak Ade Gambar 1.13 Pak Endan Gambar 1.14 Pak Alan
Gambar 1.15 Galian Gambar 1.16 Pengukuran Gambar 1.17 Lahan Siap Dibangun Gambar 1.18 Lahan Penyimpanan Material
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Minggu Ke-2
Gambar 2.1 Area Pondasi Gambar 2.2 Tulangan Pondasi Tapak Gambar 2.3 Pondasi Menerus
Gambar 2.4 Penurunan Material Besi Gambar 2.5 Stok Semen Gambar 2.6 Alat Mixer
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Gambar 2.7 Pembayaran Upah Pekerja Gambar 2.8 Perakitan Besi Gambar 2.9 Proses Pengecoran
Gambar 2.10 Proses Konstruksi
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Minggu Ke-3
Gambar 3.1 Proses Pengisian Progress Gambar 3.2 Pemasangan Tulangan Gambar 3.3 Tulangan Pondasi Setempat
Gambar 3.4 Pondasi Menerus Gambar 3.5 Galian WC Gambar 3.6 Form Progres
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Gambar 3.7 Pondasi Menerus Gambar 3.8 Bata Press Garut Gambar 3.9 Agregat Kecil
Gambar 3.10 Pasir beton (Kamojang) dan pasang Gambar 3.11 Agregat Besar Gambar 3.12 Bar Bender
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Gambar 3.13 Pondasi Gambar 3.14 Baja Polos (D8) dan Ulir (D10 & D13) Gambar 3.15 Bekisting
Gambar 3.16 Sengkang Gambar 3.17 Uji Beton
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Minggu Ke-4
Gambar 3.1 Kayu Pasang (kusen) Gambar 3.2 Material di gudang Gambar 3.3 Pemasangan bekisting sloof
Gambar 3.4 Pengecoran Sloof Gambar 3.5 Pondasi Tapak Gambar 3.6 Tulangan Kolom
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Gambar 3.7 Uji Slump Beton Gambar 3.8 Sampel Uji Beton Gambar 3.9 Molen Pengaduk Beton Segar
Gambar 3.19 Pemasangan Tulangan Sloof
SIPIL BANGUN DESA 2011 HIMPUNAN MAHASISWA SIPIL INSTITUT TEKNOLOGI BANDUNG
Jalan Ganesha 10 Bandung 40132 Jawa Barat Phone +62852.2024.2485 (Fardy | Ketua SIBADES HMS-ITB 2011)
Email [email protected] Website hms.si.itb.ac.id/sibades
Kurva S
Progres Pekerjaan s/d 27 Oktober 2011: 17%
NO NAMA KEGIATAN KODE DURASI BIAYA BOBOT (%)
hari juta,Rp 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 281 Demolishing Bangunan Existing A1 5 1.6 7.745204085 1.55 1.55 1.55 1.55 1.55
2 Pembersihan Lapangan A2 4 1.6 7.745204085 1.94 1.94 1.94 1.94
3 Pendirian Lahan Material A3 4 1.6 7.745204085 1.94 1.94 1.94 1.94
4 Pengukuran dan Bow-Plank A4 1 1.6 7.745204085 7.75
5 Sourcing Air Pembangunan A5 1 1.6 7.745204085 7.75
6 Pekerjaan Pondasi Ruang Kelas, WC, dan Gudang B6 18 6.329 30.63698979 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70
7 Pekerjaan Sloof ruang kelas, gudang, dan WC B7 4 6.329 30.63698979 7.66 7.66 7.66 7.66
20.658 100
Plan/ Rencana 1.5 3.5 5.4 5.4 5.4 17.4 0.0 1.7 1.7 1.7 1.7 1.7 1.7 0.0 1.7 1.7 1.7 1.7 1.7 1.7 0.0 1.7 1.7 9.4 9.4 9.4 9.4 0.0
Kumulatif Plan 1.5 5.0 10.5 15.9 21.3 38.7 38.7 40.4 42.1 43.8 45.5 47.2 48.9 48.9 50.6 52.3 54.0 55.7 57.4 59.2 59.2 60.9 62.6 71.9 81.3 90.6 100 100
Progres/Aktual 1.5 3.5 3.5 3.5 3.5 0.0 0.0 9.7 16.7 1.7 1.7 1.7 1.7 0.0 1.7 1.7 1.7 1.7 1.7 1.7 0.0 1.7 1.7 9.4 9.4 9.4 9.4 0.0
Kumulatif Progres 1.5 5.0 8.5 12.0 15.5 15.5 15.5 25.2 41.9 43.6 45.3 47.0 48.7 48.7 50.4 52.1 53.8 55.5 57.2 58.9 58.9 60.6 62.3 71.7 81.0 90.4 100 100
minggu 1 minggu2 minggu3 minggu4
Plan
Progres