ANTI CORRUPTION ACTION PLAN (ACAP)RENCANA TINDAK ANTI KORUPSI (RTAK)
LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN SITE VISIT
PENGADAAN JASA PEKERJAAN KONSTRUKSI
Oleh:
WAKIL PENGAMAT DARI MASYARAKAT (WPM)Nama WPM : Hesti Aulia SariNama Paket : 11, Bantal – Muko-mukoProvinsi : Bengkulu
SEPTEMBER 2014
![Page 2: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/2.jpg)
Tembusan disampaikan kepada Yth.1. Kepala Balai Besar Pelaksanaan 1alanNasional II Provinsi Bengkulu2. Ketua Pokja SNVTPJN Wilayah 1Provinsi Bengkulu3. Arsip
Hesti Aulia Sari, ST
Ketua WPM Paket 11Bantal-Muko-muko
Demikianlah, atas perhatian dan kerjasamanya disampaikan terimakasih.
Dengan hormat,Sehubungan telah diadakannya Rapat Penjelasan tanggal 8 September 2014 danKunjungan Lapangan tanggal 9 September 2014, maka bersama ini kamisampaikan Laporan pemberian penjelasan (Aanwijzing) untuk Paket 11 Bantal -Muko-muko.
Kepada : Yth. Ketua Project Management Unit (PMU) WINRIPDirektorat Bina Program, Direktorat 1enderalBina MargaKementerian Pekerjaan Umum11.Pattimura 20, Kebayoran Barn, jakarta Selatan
NomorLampiran: 1 (Satu) berkasPerihal : Laporan Pemberian Penjelasan (Aanwijzing)
Bengkulu, 22 September 2014
![Page 3: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/3.jpg)
Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan Konstruksi
i
DAFTAR ISI
DAFTAR ISI i
I. PENDAHULUAN 1II. DATA PAKET, PQ DAN PENGUMUMAN PELELANGAN 3III. PENGAMATAN PELAKSANAAN RAPAT PENJELASAN AWAL
DAN KUNJUNGAN LAPANGAN/PRE-BID MEETING AND SITE VISIT 6IV. PENUTUP 9
DAFTAR LAMPIRAN ii
![Page 4: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/4.jpg)
ii
Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan Konstruksi
DAFTAR LAMPIRANLampiran 1. Surat Persetujuan atau No Objection Letter (NOL) PQ dari Bank Dunia
Lampiran 2. Surat Pengumuman Hasil PQ dan Berita Acara Sanggah (Bila Ada)
Lampiran 3. Pengumuman Undangan Lelang
Lampiran 4. Surat Undangan Pre-Bid Meeting + Site Visit
Lampiran 5. Berita Acara Aanwijzing / Minutes of Pre-Bid Meeting + Site Visit
Lampiran 6. Absensi Kehadiran Pada Kegiatan Pre-Bid Meeting dan Absensi Kehadiran Pada KegiatanKunjungan Lapangan/Site Visit
Lampiran 7. Foto Dokumentasi Kegiatan Pre-Bid Meeting dan Site Visit
![Page 5: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/5.jpg)
SEPTEMBER2014
Hesti Aulia Sari11 WINRIPBantal - Muko-mukoBengkulu
Nama WPMNomor PaketNama PaketProvinsi
LAPORAN HASIL PENGAMATANPROSES PENGADAAN JASA KONSTRUKSI
RENCANATINDAK ANTI KORUPSI (RTAK)ANTI-CORRUPTIONACTION PLAN (ACAP)
WESTERN INDONESIANATIONAL ROAbs IMPROVEMENTPROJECT (WINRIP)IBRO LOAN No. 8043-10
KEMENTERIAN PEKERJAAN UMUMDIREKTORAT JENDERAL BINA MARGADIREKTORAT BJNA PROGRAMPROJECT MANAGEMENT UNIT (PMU)
![Page 6: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/6.jpg)
![Page 7: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/7.jpg)
![Page 8: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/8.jpg)
![Page 9: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/9.jpg)
![Page 10: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/10.jpg)
![Page 11: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/11.jpg)
![Page 12: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/12.jpg)
![Page 13: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/13.jpg)
8Western Indonesia National RoadsImprovement Project (WINRIP)IBRDLoan No: 8043-/0
2.6. Foto dokumentasi tentang kondisi lapangan proyek.
2.5. Existing jalan:o lebar existing jalan 4,5-5 m. Kondisi drainase dipenuhi oleh tumbuhan liar, sehingga
air sulit untuk mengalir dan ada juga yang tidak memiliki drainase.o kondisi topografi/konturnya adalah daerah dataran rendah dan rawan abrasi.o kondisi rona lingkungan kiri/kanan jalan terdiri dari pemukiman, lokasi bisnis/pasar,
kebun, dan sawah.
Laporan Hasil Pengamatan Proses Pengadaan Iasa Konstruksi
![Page 14: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/14.jpg)
![Page 15: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/15.jpg)
![Page 16: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/16.jpg)
![Page 17: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/17.jpg)
LAMPIRAN I
SURAT PERSETUJUAN ATAU NO OBJECTION LETTER (NOL) PQDARI BANK DUNIA
![Page 18: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/18.jpg)
![Page 19: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/19.jpg)
LAMPIRAN II
SURAT PENGUMUMAN HASIL PQ DAN BERITA ACARASANGGAH (BILA ADA)
![Page 20: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/20.jpg)
![Page 21: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/21.jpg)
![Page 22: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/22.jpg)
LAMPIRAN III
PENGUMUMAN UNDANGAN LELANG
![Page 23: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/23.jpg)
![Page 24: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/24.jpg)
![Page 25: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/25.jpg)
LAMPIRAN IV
SURAT UNDANGAN PRE-BID MEETING + SITE VISIT
![Page 26: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/26.jpg)
![Page 27: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/27.jpg)
LAMPIRAN V
BERITA ACARA AANWIJZING/MINUTES OF PRE BID MEETING +SITE VISIT
![Page 28: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/28.jpg)
![Page 29: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/29.jpg)
![Page 30: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/30.jpg)
![Page 31: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/31.jpg)
![Page 32: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/32.jpg)
LAMPIRAN VI
ABSENSI KEGIATAN PRE-BID MEETING DAN SITE VISIT
![Page 33: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/33.jpg)
![Page 34: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/34.jpg)
![Page 35: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/35.jpg)
LAMPIRAN VII
DOKUMENTASI KEGIATAN PRE-BID MEETING
![Page 36: LAPORAN PEMANTAUAN KEGIATAN PRE-BID MEETING DAN …dms.winrip-ibrd.com/data/C1_BCENR/C1.11_Bantal-Mukomuko/C1.11.06... · Laporan Hasil Pengamatan Proses Pengadaan Jasa Pekerjaan](https://reader031.fdocument.pub/reader031/viewer/2022012914/5cc7e12788c993f00b8c9592/html5/thumbnails/36.jpg)
kegiatan Site Visit
kegiatan Pre-Bid Meeting