    Capacity Planning

    6

    For Operations Management, 9ebyKrajewski/Ritzman/Malhotra 2010 Pearson Education

    PowerPoint Slides

    by Jeff Heyl

  • 5/22/2018 Krajewski Om9 Ppt 06

    2/38

    62Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Planning Capaci ty

    Capacity is the maximum rate of output of aprocess or system

    Accounting, finance, marketing, operations,purchasing, and human resources all need

    capacity information to make decisions.Accounting needs to provide cost information

    needed to evaluate expansion decisions.

    Finance performs the financial analysis of the

    proposed capacity expansion decision investmentsand raises funds to support them.

    Marketing provides demand forecasts needed toindentify capacity gaps.

  • 5/22/2018 Krajewski Om9 Ppt 06

    3/38

    63Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Planning Long -Time Capaci ty

    1. Long-term capacity planning

    A. Deals with investment in new facilities andequipment

    B. Plans cover a minimum of two years into thefuture

    C. When choosing a capacity strategy, managersmust consider questions such as the following

    How much of a cushion is needed to handle variableor uncertain demand?

    Should we expand capacity ahead of demand, or waituntil demand is more certain?

  • 5/22/2018 Krajewski Om9 Ppt 06

    4/38

    64

    Planning Long -Time Capaci ty

    2. Measures of capacity and utilizationA. Output measures of capacity

    are best utilized when applied to individual processeswithin the firm

    when the firm provides a relatively small number ofstandardized services and products

    B. Input measures of capacity

    Generally used in low-volume, flexible processes

    C. Utilization The degree to which equipment, space, or workforce is

    currently being used.

  • 5/22/2018 Krajewski Om9 Ppt 06

    5/38

    65

    Planning Long -Time Capaci ty

    Expressed as a percentage:

    The average output rate and the capacity must bemeasured in the same terms.

    Utilization = 100%Average output rate

    Maximum capacity

  • 5/22/2018 Krajewski Om9 Ppt 06

    6/38

    66Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Capac ity and Scale

    3. Economies of scaleA. Occur when the average unit cost of a service

    or good can be reduced by increasing itsoutput rate.

    B. Four principle reasons Spreading fixed costs

    Reducing construction costs

    Cutting costs of purchased materials

    Finding process advantages

  • 5/22/2018 Krajewski Om9 Ppt 06

    7/3867Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Capac ity and Scale

    4. Diseconomies of scaleA. Occur when the average per unit costs

    increases as the facilityssize increases

    B. Excessive size can bring complexity, loss of

    focus, and inefficiencies that raise the averageunit cost.

    C. A less agile organization loses the flexibilityneeded to respond to changing demand.

    D. Many large companies become so involved inanalysis and planning that they innovate lessand avoid risk.

  • 5/22/2018 Krajewski Om9 Ppt 06

    8/3868Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Capac ity and Scale

    Figure 6.1Economies and Diseconomies of Scale

    250-bedhospital

    500-bedhospital

    750-bedhospital

    Output rate (patients per week)

    Averageunit

    cost

    (dollarsperpatient)

    Economiesof scale Diseconomiesof scale

  • 5/22/2018 Krajewski Om9 Ppt 06

    9/3869Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Capaci ty Tim ing and Sizing Strateg ies

    Three dimensions to capacity strategy: sizingcapacity cushion, timing and sizingexpansions, and linking process capabilityand other operating decisions.

    1. Sizing capacity cushions:

    Capacity cushions are the amount of reservecapacity a process uses to handle suddenchanges.

    A. Average utilization rates for any resourceshould not get close to 100 percent over thelong term.

    Capacity cushion = 100%Average Utilization rate (%)

  • 5/22/2018 Krajewski Om9 Ppt 06

    10/38610

    Capaci ty Tim ing and Sizing Strateg ies

    B. When average utilization rates approach 100% itis usually a signal: Need to increase capacity Decrease order acceptance to avoid poor

    customer service or declining productivity

    C. Appropriate size varies by industry Utilization rates tend to be higher in capital-

    intensive industries and low cushions arepreferred

    Large cushions are particularly vital for front-office processes where customers expect fastdelivery times

    Large cushions are necessary when futuredemand is uncertain, particularly if resourceflexibility is low

  • 5/22/2018 Krajewski Om9 Ppt 06

    11/38611

    Capaci ty Tim ing and Sizing

    Strategies

    Factors Leading to Large Capacity Cushions When demand is variable, uncertain, or product mix

    changes

    When finished goods inventory cannot be stored

    When customer service is important

    When capacity comes in large increments

    When supply of material or human resources is uncertain

    Factors leading to small capacity cushions

    Unused capacity costs money. Large cushions hide inefficiencies, absenteeism, and

    unreliable material supply.

    When subcontractors are available to handle demandpeaks

  • 5/22/2018 Krajewski Om9 Ppt 06

    12/38612

    Capaci ty Tim ing and Sizing

    Strategies2. Timing and sizing expansions

    A. Expansionist strategy

    Economies of scale may reduce fixed cost per unit

    Might increase the firms market share or act as a form ofpreemptive marketing

    B. Wait-and-see strategy

    Lags behind demand, relying on short-term peak capacityoptions (overtime, subcontractors) to meet demand

    Lower financial risk associated with overly optimistic

    demand forecast Lower risk of a technological advancement making a new

    facility obsolete

    Higher risk of losing market share

    C. An intermediate strategy, could be to fo l low theleader, expanding when others do

  • 5/22/2018 Krajewski Om9 Ppt 06

    13/38613Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Capaci ty Tim ing and Sizing

    Planned unusedcapacity

    Time

    Capac

    ity

    Forecast of capacityrequired

    Time betweenincrements

    Capacityincrement

    (a) Expansionist strategy

    Figure 6.2Two Capacity Strategies

  • 5/22/2018 Krajewski Om9 Ppt 06

    14/38614Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Time

    Capac

    ity

    (b) Wait-and-see strategy

    Planned use ofshort-term options

    Time betweenincrements

    Capacityincrement

    Capaci ty Tim ing and Sizing

    Forecast of capacityrequired

    Figure 6.2Two Capacity Strategies

  • 5/22/2018 Krajewski Om9 Ppt 06

    15/38615Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Link ing Capaci ty

    Linking process capacity and otheroperating decisions

    Capacity decisions should be linked to

    processes and supply chains throughout theorganization

    Important issues are:

    competitive priorities,

    quality,

    process design

  • 5/22/2018 Krajewski Om9 Ppt 06

    16/38616Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Systemat ic App roach to Long -Term

    Capaci ty Decis ions

    1. Estimate future capacity requirements

    2. Identify gaps by comparing requirementswith available capacity

    3. Develop alternative plans for reducing thegaps

    4. Evaluate each alternative, both qualitativelyand quantitatively, and make a final choice

  • 5/22/2018 Krajewski Om9 Ppt 06

    17/38617Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Systemat ic App roach

    Step 1 is to determine the capacity requiredto meet future demand using anappropriate planning horizon

    Output measures based on rates ofproduction

    Input measures may be used when

    Product variety and process divergence is high

    The product or service mix is changing

    Productivity rates are expected to change

    Significant learning effects are expected

  • 5/22/2018 Krajewski Om9 Ppt 06

    18/38618Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Systemat ic App roach

    For one service or product processed atone operation with a one year time period,the capacity requirement, M, is

    Capacity

    requirement =

    Processing hours required for years demand

    Hours available from a single capacity unit(such as an employee or machine) per year,

    after deducting desired cushion

    M=Dp

    N[1(C/100)]

    where

    D= demand forecast for the year (number of customers serviced orunits of product)

    p= processing time (in hours per customer served or unit produced)

    N= total number of hours per year during which the process operates

    C= desired capacity cushion (expressed as a percent)

  • 5/22/2018 Krajewski Om9 Ppt 06

    19/38619Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Systemat ic App roach

    Setup times may be required if multipleproducts are produced

    Capacityrequirement =

    Processing and setup hours required foryears demand, summed over all services

    or productsHours available from a single capacity unitper year, after deducting desired cushion

    M=

    [Dp+ (D/Q)s]product 1+ [Dp+ (D/Q)s]product 1+

    + [Dp+ (D/Q)s]product n

    N[1(C/100)]

    whereQ= number of units in each lots= setup time (in hours) per lot

  • 5/22/2018 Krajewski Om9 Ppt 06

    20/38620Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Est imat ing Capaci ty Requ irements

    EXAMPLE 6.1

    A copy center in an office building prepares bound reports fortwo clients. The center makes multiple copies (the lot size) ofeach report. The processing time to run, collate, and bind eachcopy depends on, among other factors, the number of pages.The center operates 250 days per year, with one 8-hour shift.

    Management believes that a capacity cushion of 15 percent(beyond the allowance built into time standards) is best. Itcurrently has three copy machines. Based on the followingtable of information, determine how many machines are neededat the copy center.

    Item Client X Client Y

    Annual demand forecast (copies) 2,000 6,000

    Standard processing time (hour/copy) 0.5 0.7

    Average lot size (copies per report) 20 30

    Standard setup time (hours) 0.25 0.40

  • 5/22/2018 Krajewski Om9 Ppt 06

    21/38621Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Est imat ing Capaci ty Requ irements

    SOLUTION

    M=[Dp+ (D/Q)s]product 1+ [Dp+ (D/Q)s]product 1+ + [Dp+ (D/Q)s]product n

    N[1(C/100)]

    =[2,000(0.5) + (2,000/20)(0.25)]client X+ [6,000(0.7) + (6,000/30)(0.40)]client Y

    [(250 day/year)(1 shift/day)(8 hours/shift)][1.0 - (15/100)]

    = = 3.125,305

    1,700

    Rounding up to the next integer gives a requirement offour machines.

  • 5/22/2018 Krajewski Om9 Ppt 06

    22/38622Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Systemat ic App roach

    Step 2 is to identify gaps betweenprojected capacity requirements (M) andcurrent capacity

    Complicated by multiple operations andresource inputs

    Step 3 is to develop alternatives

    Base case is to do nothing and suffer theconsequences

    Many different alternatives are possible

  • 5/22/2018 Krajewski Om9 Ppt 06

    23/38623Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Systemat ic App roach

    Step 4 is to evaluate the alternatives

    Qualitative concerns include strategic fit anduncertainties

    Quantitative concerns may include cash flowsand other quantitative measures

  • 5/22/2018 Krajewski Om9 Ppt 06

    24/38624Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Evaluat ing the A lternat ives

    EXAMPLE 6.2

    Grandmothers Chicken Restaurant is experiencing a boom inbusiness. The owner expects to serve 80,000 meals this year.Although the kitchen is operating at 100 percent capacity, thedining room can handle 105,000 diners per year. Forecasteddemand for the next five years is 90,000 meals for next year,

    followed by a 10,000-meal increase in each of the succeedingyears. One alternative is to expand both the kitchen and thedining room now, bringing their capacities up to 130,000 mealsper year. The initial investment would be $200,000, made at theend of this year (year 0). The average meal is priced at $10, andthe before-tax profit margin is 20 percent. The 20 percent figure

    was arrived at by determining that, for each $10 meal, $8 coversvariable costs and the remaining $2 goes to pretax profit.

    What are the pretax cash flows from this project for the nextfive years compared to those of the base case of doingnothing?

  • 5/22/2018 Krajewski Om9 Ppt 06

    25/38625Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Evaluat ing the A lternat ives

    SOLUTION

    Recall that the base case of doing nothing results in losing allpotential sales beyond 80,000 meals. With the new capacity, thecash flow would equal the extra meals served by having a130,000-meal capacity, multiplied by a profit of $2 per meal. Inyear 0, the only cash flow is$200,000 for the initial investment.

    In year 1, the 90,000-meal demand will be completely satisfiedby the expanded capacity, so the incremental cash flow is(90,00080,000)($2) = $20,000. For subsequent years, thefigures are as follows:

    Year 2: Demand = 100,000; Cash flow = (100,00080,000)$2 = $40,000

    Year 3: Demand = 110,000; Cash flow = (110,00080,000)$2 = $60,000

    Year 4: Demand = 120,000; Cash flow = (120,00080,000)$2 = $80,000

    Year 5: Demand = 130,000; Cash flow = (130,00080,000)$2 = $100,000

  • 5/22/2018 Krajewski Om9 Ppt 06

    26/38626Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Evaluat ing the A lternat ives

    If the new capacity were smaller than the expected demand inany year, we would subtract the base case capacity from thenew capacity (rather than the demand). The owner shouldaccount for the time value of money, applying such techniquesas the net present value or internal rate of return methods (seeSupplement F, Financial Analysis, in myomlab). For instance,

    the net present value (NPV) of this project at a discount rate of10 percent is calculated here, and equals $13,051.76.

    NPV = 200,000 + [(20,000/1.1)] + [40,000/(1.1)2] +[60,000/(1.1)3] + [80,000/(1.1)4] + [100,000/(1.1)5]

    = $200,000 + $18,181.82 + $33,057.85 + $45,078.89 +$54,641.07 + $62,092.13

    = $13,051.76

  • 5/22/2018 Krajewski Om9 Ppt 06

    27/38627Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Solved Problem 2

    The base case for Grandmothers Chicken Restaurant (seeExample 6.2) is to do nothing. The capacity of the kitchen in thebase case is 80,000 meals per year. A capacity alternative forGrandmothers Chicken Restaurant is a two-stage expansion.This alternative expands the kitchen at the end of year 0, raisingits capacity from 80,000 meals per year to that of the dining

    area (105,000 meals per year). If sales in year 1 and 2 live up toexpectations, the capacities of both the kitchen and the diningroom will be expanded at the end of year 3 to 130,000 meals peryear. This upgraded capacity level should suffice up throughyear 5. The initial investment would be $80,000 at the end ofyear 0 and an additional investment of $170,000 at the end of

    year 3. The pretax profit is $2 per meal. What are the pretaxcash flows for this alternative through year 5, compared withthe base case?

  • 5/22/2018 Krajewski Om9 Ppt 06

    28/38

    628Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Solved Problem 2

    SOLUTIONTable 6.1 shows the cash inflows and outflows. The year 3 cashflow is unusual in two respects. First, the cash inflow fromsales is $50,000 rather than $60,000. The increase in sales overthe base is 25,000 meals (105,00010,000) instead of 30,000meals (110,00080,000) because the restaurants capacity falls

    somewhat short of demand. Second, a cash outflow of $170,000occurs at the end of year 3, when the second-stage expansionoccurs.

    The net cash flow for year 3 is $50,000$170,000 =$120,000.

  • 5/22/2018 Krajewski Om9 Ppt 06

    29/38

    629Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Solved Problem 2

    TABLE 6.1 | CASH FLOWS FOR TWO-STAGE EXPANSION AT GRANDMOTHERS CHICKEN RESTAURANT

    Year

    ProjectedDemand

    (meals/yr)

    ProjectedCapacity

    (meals/yr)

    Calculation of Incremental Cash FlowCompared to Base Case

    (80,000 meals/yr)

    CashInflow

    (outflow)

    0 80,000 80,000 Increase kitchen capacity to 105,000 meals = ($80,000)

    1 90,000 105,000 90,00080,000 = (10,000 meals)($2/meal) = $20,000

    2 100,000 105,000 100,00080,000 = (20,000 meals)($2/meal) = $40,000

    3 110,000 105,000 105,00080,000 = (25,000 meals)($2/meal) = $50,000

    Increase total capacity to 130,000 meals = ($170,000)

    ($120,000)

    4 120,000 130,000 120,00080,000 = (40,000 meals)($2/meal) = $80,000

    5 130,000 130,000 130,00080,000 = (50,000 meals)($2/meal) = $100,000

  • 5/22/2018 Krajewski Om9 Ppt 06

    30/38

    630Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Solved Problem 2

    NPV = 80,000 + (20,000/1.1) + [40,000/(1.1)2][120,000/(1.1)3] +[80,000/(1.1)4] + [100,000/(1.1)5]

    = $80,000 + $18,181.82 + $33,057.85$90,157.77 +$54,641.07 + $62,092.13

    = $2,184.90

    For comparison purposes, the NPV of this project at a discountrate of 10 percent is calculated as follows, and equals negative$2,184.90.

    On a purely monetary basis, a single-stage expansion seemsto be a better alternative than this two-stage expansion.However, other qualitative factors as mentioned earlier must beconsidered as well.

  • 5/22/2018 Krajewski Om9 Ppt 06

    31/38

    631Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Too ls fo r Capaci ty Plann ing

    Waiting-line modelsUseful in high customer-contact processes

    Supplement C, Waiting Lines is a fullertreatment of the models

    Simulation

    Can be used when models are too complex forwaiting-line analysis

    Decision trees

    Useful when demand is uncertain andsequential decisions are involved

  • 5/22/2018 Krajewski Om9 Ppt 06

    32/38

    632Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Wait ing Line Models

    Figure 6.3POMS for Windows Output for Waiting Lines during Office Hours

  • 5/22/2018 Krajewski Om9 Ppt 06

    33/38

    633Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Dec ision Trees

    1

    Low demand [0.40]

    High demand [0.60]

    Low demand [0.40]

    High demand [0.60]

    $70,000

    $220,000

    $40,000

    $135,000

    $90,000Dont expand

    Expand

    2

    Figure 6.4A Decision Tree for Capacity Expansion

    $135,000

    $109,000

    $148,000

    $148,000

  • 5/22/2018 Krajewski Om9 Ppt 06

    34/38

    634Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Solved Problem 1

    You have been asked to put together a capacity plan for a

    critical operation at the Surefoot Sandal Company. Yourcapacity measure is number of machines. Three products(mens, womens, and childrens sandals) are manufactured.The time standards (processing and setup), lot sizes, anddemand forecasts are given in the following table. The firmoperates two 8-hour shifts, 5 days per week, 50 weeks per year.

    Experience shows that a capacity cushion of 5 percent issufficient.

    a. How many machines are needed?

    b. If the operation currently has two machines, what is the

    capacity gap?

    Time Standards

    ProductProcessing

    (hr/pair)Setup

    (hr/pair)Lot size

    (pairs/lot)Demand Forecast

    (pairs/yr)

    Mens sandals 0.05 0.5 240 80,000

    Womens sandals 0.10 2.2 180 60,000

    Childrens sandals 0.02 3.8 360 120,000

  • 5/22/2018 Krajewski Om9 Ppt 06

    35/38

    635Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Solved Problem 1

    SOLUTION

    a. The number of hours of operation per year, N, is N= (2shifts/day)(8 hours/shifts) (250 days/machine-year) = 4,000hours/machine-year

    The number of machines required, M, is the sum of machine-hour requirements for all three products divided by the

    number of productive hours available for one machine:

    M=[Dp+ (D/Q)s]men+[Dp+ (D/Q)s]women+ [Dp+ (D/Q)s]children

    N[1 - (C/100)]

    =

    [80,000(0.05) + (80,000/240)0.5] + [60,000(0.10) + (60,000/180)2.2]+ [120,000(0.02) + (120,000/360)3.8]

    4,000[1 - (5/100)]

    = = 3.83 or 4 machines14,567 hours/year

    3,800 hours/machine-year

  • 5/22/2018 Krajewski Om9 Ppt 06

    36/38

    636Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Solved Problem 1

    b. The capacity gap is 1.83 machines (3.832). Two more

    machines should be purchased, unless managementdecides to use short-term options to fill the gap.

    The Capacity Requ irements Solver in OM Explorer confirmsthese calculations, as Figure 6.5 shows, using only theExpected scenario for the demand forecasts.

  • 5/22/2018 Krajewski Om9 Ppt 06

    37/38

    637Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall.

    Solved Problem 1

  • 5/22/2018 Krajewski Om9 Ppt 06

    38/38