Kidurong Presentation 2

22

description

presentation work

Transcript of Kidurong Presentation 2

PROJECT INTRODUCTION

Project Executor : Pengarah Kerja Raya Sarawak Superintending : Regional Manager, JKR Officer Northern Regional Office,

Miri Contractor : METROBRITE ENGINEERING

SDN. BHD. Project Commence- : 16th January 2015 ment Date Project Scheduled Completion : 15th October 2016 Contract Period : 21 months Contract Amount : RM 71, 618, 000.00

SITE LOCATION PLAN

Scope of Works comprising of planning, preparation, construction and completion of the following :-

Road Construction Including site clearing, excavation and removal of unsuitable materials, cut and fill, imported suitable fill, spread and compact to the required formation level.Flexible Pavement Construction of proposed new carriageway including sub-base, road base and asphaltic concrete finishes, resurfacing existing carriageway, roundabout and junctions, crack sealing and patching works.Drainage Construction and completion of Reinforced Concrete Box and Pipe Culverts for extension of main road’s culverts), Surface Drainage facilities and associated ancillary works. Traffic Signal System Supply, install, testing and commissioning of Traffic Signal system.

SCOPE OF WORKS

Piling Works (Provisional) Comprising of installation of :-

200mm x 200mm RC Square Piles as foundation for RC Culverts 150mm x 150mm and 250mm x 250mm RC Square Piles as foundation for

piled embankment 355.6mm Micropiles for bridges foundation.

Road Furnitures Traffic Management Provision for full time traffic management team for the entire duration of the contract. Bridge Works Reinforced Concrete Works and other associated works for the construction and completion of :-

Sg. Similajau Bridge (B)- 90m length in 3 spans Sg. Similajau Bridge No. 3 (B) -45m length in 3 spans

Miscellaneous Works

SCOPE OF WORKS

Sylvester Rampai Ak Kudum

Tang Soon Huat Sepakat Geodrilling Freyssinet PSC Geospec Testing

Traffic Controller 1 Traffic Controller 2 Micropile Specialist

Post-Tensioning Works

Tester RC Piling Works

Hudson Ak Duncan Dundang

Ong Kah Ho Chan Yii Liang Voon Wen Hang Lau Kiiung Pew Wong Khing Boh

Supervisor for Traffic

Management Team

Supervisor for Emergency

Response Team

Drainage & Miscellaneous

Works

Bridge Works Supervisor

Road Works, Flexible Pavement & Road Furnitures

Traffic Signal System

Site Safety Supervisor

Traffic Management

Quantity SurveyorJenny Tiong Ching

ChingJohn Ha Tung Soon Chai Chang Kim

Project Engineer

Sh. Delaila Wan Abdillah

Lawrence Robert Tasser

NRM Environmental Consultant

Wong Ting KuiOswald Lau Puong

HoeJames Ha Tung Ing

Survey Development

Services

Safety Officer EMP/EMR Surveyor Site Manager QA/QC Engineer Contract Manager

Project ManagerIr. Wong Ting Yew

PROJECT TEAM

90 Days Critical Activities

1.Completion of site clearing and earthwork up to near 2 KM2.Completion of 6 culverts.3.Completion of bridge embankment pilings4.Completion of 15M precast beams production.

IDENTIFIED CRITICAL ACTIVITIES BASED ON WORK PROGRAM (90-DAYS)

Contactor has submitted Insurance Policies cover notes prior to site possession date for:- Workmen’s Compensation (Cover Note No. : AK 96234) Contractor’s All Risk (Cover Note No. : AK96233)

Contractor to notify plantation owner of intention to commence work and to clear the area up to construction limit.

Notification to relevant authorities with regard to utilities relocation.

HIGHLIGHTED ISSUES