Page 1: Keshav Nagar, Pune · 2020-05-30 · Florida Watercolor –October’18 ‘B’ BUILDING: • RCC work completed up to terrace slab. Lift machine room & overhead water tank bottom

Keshav Nagar, Pune

Page 2: Keshav Nagar, Pune · 2020-05-30 · Florida Watercolor –October’18 ‘B’ BUILDING: • RCC work completed up to terrace slab. Lift machine room & overhead water tank bottom

Florida Watercolor – October’18

‘A’ BUILDING:

• RCC completed for 1st, 2nd & 3rd slab

• Block work completed for 1st floor

• Internal plaster completed for 1st floor

• External plaster 50% complete for 1st floor

• Toilet internal concealed plumbing completed for 1st floor

• Toilet internal floor plumbing completed for 1st floor

• 30% work complete for 1st floor toilet waterproofing

• 50% work complete for 1st floor toilet granite door framing

• 80% work complete for 1st floor concealed electrical work

• 1st floor wall & ceiling gypsum work-in-progress

Page 3: Keshav Nagar, Pune · 2020-05-30 · Florida Watercolor –October’18 ‘B’ BUILDING: • RCC work completed up to terrace slab. Lift machine room & overhead water tank bottom

Florida Watercolor – October’18

‘B’ BUILDING:

• RCC work completed up to terrace slab. Lift machine room & overhead water tank bottom slab work-in-

progress

• Block work completed up to 12th floor. Work-in-progress for 13th floor, 14th floor & parapet

• Internal plaster completed up to 12th floor

• External plaster- 60% complete for north side & 70% complete for flat terrace

• Toilet internal concealed plumbing & floor plumbing completed up to 12th floor

• Toilet waterproofing work- completed up to 7th floor. 50% work complete for 8th floor and 40% complete

for 9th, 10th & 11th floor

• Toilet granite door & window framing work completed up to 6th floor & 50% complete for 7th floor

• Concealed electrical work completed up to 10th floor

• Wall & ceiling gypsum completed up to 8th floor & 70% complete fro 9th floor

• Toilet tiling dado complete up to 6th floor

• Kitchen platform work 70% complete up to 4th floor & 40% complete for 5th floor