Keshav Nagar, Pune · 2020-05-30 · Florida Watercolor –October’18 ‘B’ BUILDING: • RCC...
Transcript of Keshav Nagar, Pune · 2020-05-30 · Florida Watercolor –October’18 ‘B’ BUILDING: • RCC...
Keshav Nagar, Pune
Florida Watercolor – October’18
‘A’ BUILDING:
• RCC completed for 1st, 2nd & 3rd slab
• Block work completed for 1st floor
• Internal plaster completed for 1st floor
• External plaster 50% complete for 1st floor
• Toilet internal concealed plumbing completed for 1st floor
• Toilet internal floor plumbing completed for 1st floor
• 30% work complete for 1st floor toilet waterproofing
• 50% work complete for 1st floor toilet granite door framing
• 80% work complete for 1st floor concealed electrical work
• 1st floor wall & ceiling gypsum work-in-progress
Florida Watercolor – October’18
‘B’ BUILDING:
• RCC work completed up to terrace slab. Lift machine room & overhead water tank bottom slab work-in-
progress
• Block work completed up to 12th floor. Work-in-progress for 13th floor, 14th floor & parapet
• Internal plaster completed up to 12th floor
• External plaster- 60% complete for north side & 70% complete for flat terrace
• Toilet internal concealed plumbing & floor plumbing completed up to 12th floor
• Toilet waterproofing work- completed up to 7th floor. 50% work complete for 8th floor and 40% complete
for 9th, 10th & 11th floor
• Toilet granite door & window framing work completed up to 6th floor & 50% complete for 7th floor
• Concealed electrical work completed up to 10th floor
• Wall & ceiling gypsum completed up to 8th floor & 70% complete fro 9th floor
• Toilet tiling dado complete up to 6th floor
• Kitchen platform work 70% complete up to 4th floor & 40% complete for 5th floor
‘A’ Building
‘B’ Building