ANALISA HARGA SATUAN PEKERJAAN : BETON DINDING MUTU K-300 / M3
HARGA SAT. JUMLAH(Rp.) (Rp.)
I UPAH - Cor, perataan, curing & pembersihan 1.000 m3 50,000.00 50,000.00
II BAHAN - Ready mixed concrete K-250, batu split 1.030 m3 885,500.00 912,065.00
III ALAT - Kereta sorong, talang, vibrator & alat bantu lainnya 1.000 m3 5,000.00 5,000.00
Total 967,065.00 Overhead, PPh & Contractor Fee. : (12 %) 116,047.80
Total 1,083,112.80 Rounded 1,083,112.80
ANALISA HARGA SATUAN PEKERJAAN : WATERPROOFING INTEGRAL 2,00 ltr / M3
HARGA SAT. JUMLAH(Rp.) (Rp.)
I UPAH - Pasang Waterproofing Integral 1.000 m3 5,000.00 5,000.00
II BAHAN - Waterproofing integral ex. SIKA type Visconcrete 10 single component 2.000 liter/m3 50,000.00 100,000.00 konsumsi 2,00 ltr/m3
III ALAT
Total 105,000.00 Overhead, PPh & Contractor Fee. : (12 %) 12,600.00
Total 117,600.00 Rounded 117,600.00
NO. URAIAN PEKERJAAN VOLUME SATUAN
NO. URAIAN PEKERJAAN VOLUME SATUAN