ANALISA HARGA SATUAN PEKERJAAN : BETON DINDING MUTU K-300 / M3 HARGA SAT. JUMLAH (Rp.) (Rp.) I UPAH - Cor, perataan, curing & pembersihan 1.000 m3 50,000.00 50,000.00 II BAHAN - Ready mixed concrete K-250, batu split 1.030 m3 885,500.00 912,065.00 III ALAT - Kereta sorong, talang, vibrator & alat bantu lainnya 1.000 m3 5,000.00 5,000.00 Total 967,065.00 Overhead, PPh & Contractor Fee. : (12 %) 116,047.80 Total 1,083,112.80 Rounded 1,083,112.80 ANALISA HARGA SATUAN PEKERJAAN : WATERPROOFING INTEGRAL 2,00 ltr / M3 HARGA SAT. JUMLAH (Rp.) (Rp.) I UPAH - Pasang Waterproofing Integral 1.000 m3 5,000.00 5,000.00 II BAHAN - Waterproofing integral ex. SIKA type Visconcrete 10 single component 2.000 liter/m3 50,000.00 100,000.00 konsumsi 2,00 ltr/m3 III ALAT Total 105,000.00 Overhead, PPh & Contractor Fee. : (12 %) 12,600.00 Total 117,600.00 Rounded 117,600.00 NO. URAIAN PEKERJAAN VOLUME SATUAN NO. URAIAN PEKERJAAN VOLUME SATUAN

description

wtret4et

Transcript of K300 sika6

Page 1: K300 sika6

ANALISA HARGA SATUAN PEKERJAAN : BETON DINDING MUTU K-300 / M3

HARGA SAT. JUMLAH(Rp.) (Rp.)

I UPAH - Cor, perataan, curing & pembersihan 1.000 m3 50,000.00 50,000.00

II BAHAN - Ready mixed concrete K-250, batu split 1.030 m3 885,500.00 912,065.00

III ALAT - Kereta sorong, talang, vibrator & alat bantu lainnya 1.000 m3 5,000.00 5,000.00

Total 967,065.00 Overhead, PPh & Contractor Fee. : (12 %) 116,047.80

Total 1,083,112.80 Rounded 1,083,112.80

ANALISA HARGA SATUAN PEKERJAAN : WATERPROOFING INTEGRAL 2,00 ltr / M3

HARGA SAT. JUMLAH(Rp.) (Rp.)

I UPAH - Pasang Waterproofing Integral 1.000 m3 5,000.00 5,000.00

II BAHAN - Waterproofing integral ex. SIKA type Visconcrete 10 single component 2.000 liter/m3 50,000.00 100,000.00 konsumsi 2,00 ltr/m3

III ALAT

Total 105,000.00 Overhead, PPh & Contractor Fee. : (12 %) 12,600.00

Total 117,600.00 Rounded 117,600.00

NO. URAIAN PEKERJAAN VOLUME SATUAN