KOPERASI UNIT DESA (KUD)
MINA SINAR LAUT Pabrik Es Balok
Jl. Pasir Baru, Sungai Limau
Page 1 of 5
Jurnal Pengontrolan Mesin
Hari : ............... Tanggal : .........................
Jam Suhu Oli Suct Disc Amp Volt Keterangan
08.00
09.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
![Page 2: Jurnal Pengontrolan Mesin](https://reader030.fdocument.pub/reader030/viewer/2022020208/55cf8f5c550346703b9b89f4/html5/thumbnails/2.jpg)
KOPERASI UNIT DESA (KUD)
MINA SINAR LAUT Pabrik Es Balok
Jl. Pasir Baru, Sungai Limau
Page 2 of 5
Hari : ............... Tanggal : .........................
Jam Suhu Oli Suct Disc Amp Volt Keterangan
08.00
09.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
![Page 3: Jurnal Pengontrolan Mesin](https://reader030.fdocument.pub/reader030/viewer/2022020208/55cf8f5c550346703b9b89f4/html5/thumbnails/3.jpg)
KOPERASI UNIT DESA (KUD)
MINA SINAR LAUT Pabrik Es Balok
Jl. Pasir Baru, Sungai Limau
Page 3 of 5
Hari : ............... Tanggal : .........................
Jam Suhu Oli Suct Disc Amp Volt Keterangan
08.00
09.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
![Page 4: Jurnal Pengontrolan Mesin](https://reader030.fdocument.pub/reader030/viewer/2022020208/55cf8f5c550346703b9b89f4/html5/thumbnails/4.jpg)
KOPERASI UNIT DESA (KUD)
MINA SINAR LAUT Pabrik Es Balok
Jl. Pasir Baru, Sungai Limau
Page 4 of 5
Hari : ............... Tanggal : .........................
Jam Suhu Oli Suct Disc Amp Volt Keterangan
08.00
09.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
![Page 5: Jurnal Pengontrolan Mesin](https://reader030.fdocument.pub/reader030/viewer/2022020208/55cf8f5c550346703b9b89f4/html5/thumbnails/5.jpg)
KOPERASI UNIT DESA (KUD)
MINA SINAR LAUT Pabrik Es Balok
Jl. Pasir Baru, Sungai Limau
Page 5 of 5
Hari : ............... Tanggal : .........................
Jam Suhu Oli Suct Disc Amp Volt Keterangan
08.00
09.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
Sei. Limau, 3 April 2015
Operator Pabrik ES Tim Surveyor
KUD Mina Sinar Laut
Indra Azril