Jesper Mansson - The LM 88.4P Blade
-
Upload
sandia-national-laboratories-energy-climate-renewables -
Category
Technology
-
view
112 -
download
1
Transcript of Jesper Mansson - The LM 88.4P Blade
Select one of
the 3 title pages
and delete the
others.
Please do not
create new title
pages by using
the layouts Title
1 – 3 as these
layouts do not
contain the
necessary
graphic
elements.
If you insert or
change a picture
and it covers
other graphic
elements, you
can right click
the picture and
select ”Bring to
back”.
By
Select one of
the 3 title pages
and delete the
others.
Please do not
create new title
pages by using
the layouts Title
1 – 3 as these
layouts do not
contain the
necessary
graphic
elements.
If you insert or
change a picture
and it covers
other graphic
elements, you
can right click
the picture and
select ”Bring to
back”.
THE LM 88.4P BLADE
Sandia Blade Work Shop 2016
Jesper Månsson
1
The
early years
2004 61.5 m blade
introduced
(world’s longest
blade at the time)
1996 1st generation
Lightning-Protection
Vortex generators
2003 FutureBlade
technology
2002 Pre-bending
1999 VARTM
vacuum infusion
technology
2012 73.5 m blade
introduced
(world’s longest
blade at the time)
If you insert or
change a picture
and it covers
other graphic
elements, you
can right click
the picture and
select ”Bring to
back”.
If you insert or
change a picture
and it covers
other graphic
elements, you
can right click
the picture and
select ”Bring to
back”.
The LM 88.4P
Vindeby
LM 61.5P
LM 73.5P
LM 88.5P
LM offshore milestones
Offshorewind.biz
LM 88.4P
Developed in cooperation with
ADWEN for the AD 8-180
1. We have to have the blade
“optimized”.
2. We have to generate the optimal &
validated design for the turbine as
a whole.
3. We have to have the right material
technology - validated.
4. We have to have the right
solutions for the size of the blade.
5. Technologies need to be ready for
serial production.
What is the challenge to make 88.4?
1. Optimized by matching Aerodynamics, Loads, Geometry & Structure
2. Technology Material, Coupon and Component Validation Program
9
3. LM 88.4 P – Size matters LM 88.4 P vs. LM 73.5 P
LM 88.4 P vs. LM 73.5 P
LM 88.4 P vs. LM 42.1 P
LM 88.4 P vs. LM 42.1 P
LM 88.4 P vs. LM 61.5 P/P2
LM 88.4 P vs. LM 42.1 P
Where the LM 73.5 P stops, the LM 88.4 P
still has 2m of chord.
QD-01282/A2
10
STANDARDISATION
Processes and materials
Economy of Scale
MODULARISATION
Submodules
Different Technologies
AUTOMATION/LINES
Submodules
Stations setup
?
World class industrialization
I
III
IV
II
What do we gain with pFMEA ?
Risk management
Prevention planning
Prioritized CI project
What do we gain?
The Control Plan methodology support the manufacture of quality products according to customer requirements.
12
Manufacturing Control Blade manufacturing process operations
Extreme load test completed at Blaest
Thank you !