It's not a bug, it's a feature!
-
Upload
sharepoint-project-conference-adriatics -
Category
Technology
-
view
696 -
download
4
description
Transcript of It's not a bug, it's a feature!
SHAREPOINT AND PROJECT CONFERENCE ADRIATICS 2013
ZAGREB, NOVEMBER 27-28 2013
It’s Not A Bug. It’s A Feature!IGOR SLIŠKOVIĆ, PROTERON CONSULTING
sponsors
About The Presentation• Motive: experiencing the same pattern over and over
again – MS Project is used for developing initial schedule and is later forgotten (apart from printed Ghantt chart over PM’s desk)• Diagnose: Key MS Project features are contra intuitive. • Prescription: Show and teach a few basic principles in
schedule development and tracking that represent the best practice• The Goal: give you more time managing your project
and less time managing MS Project• KPI: never to hear from participants of this session the
sentence so common –” MS Project doesn’t calculate correctly when …”• Format: mostly demonstration (8 slides and 4
demonstrations)
Sequence Of Activities
WBS Developme
ntTask Entry Task
SequencingAssigning Resources
Tracking Actuals
Tracking Project Status
Closing Project
BAD HABITS 1 – TASK CONSTRAINTS
Theorem
We will let Project do the scheduling. We will just provide
necessary information.
Flexible Constraints And Deadlines• Three types of constraints:
• Flexible (As Soon As Possible, As Late As Possible)• Semi Flexible (Start No Earlier Than, Finish No …)• Inflexible (Must Start On, Must Finish On)
• USE ONLY FLEXIBLE CONSTRAINTS: setting fixed date on the task in your schedule doesn’t help it to happen in reality. Actually, it makes your schedule static and increases the risk of missing some dates• Deadlines: compromise for the fixed data problem
• Clear indication that we are late • Keeping the schedule dynamic
• [GO BACK TO DEMO AND SHOW HOW IT SHOULD HAVE BEEN DONE]
BAD AND GOOD HABITS - RESOURCES
Resources• Never change start and finish date of a task because of
the resource availability or over allocation• Use• Resource Calendar• Leveling delay (indirectly used with MS Project commands)
• [Semi Best Practice] If possible, use one resource one task rule• Yes, in Project Server environment, resource calendar
exceptions can be integrated with HR or other applications managing resource availability.• Even Exchange Out Of Office can be used as a source of
exception!!
Tracking Progress - Introduction• What are we tracking?• Hours spent by a resource on a task• How close are we to finishing the task
• Do we track when exactly the time was spent on the task?• What “how close to finish means”• How many days will it take?• How much work will it take?
• What are we measuring success against?• Baseline
• What does % Complete field mean?
TRACKING PROGRESS
Tracking progress• Don’t use % Complete as your standard
• Doesn’t set Actual Start other than planned• Cannot show the task is late• Might use it as a shortcut
• Always have at least 2 baselines: initial and current. Saving new baseline is done as a part of the controlled process.• If you use Project Server use Work done per period (timephased)• Keep your schedule neat – no remaining work in the past and
actual work in future.
Reporting On Progress• What if you notice that:• You are under budget?• More resources have been used on your project than planned
by that day?
Is it a good or a bad thing?
Dont’ know – use Earned Value
EARNED VALUE – (IF TIME PERMITS)
questions?
thank you.