How to Create S-Curve by MS Project 2010

57

Click here to load reader

Transcript of How to Create S-Curve by MS Project 2010

Page 1: How to Create S-Curve by MS Project 2010

1Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

OS-MSP-001Rev.: 01 / 1-06-2016

How to Create S-Curve by MS Project 2007 & 2010

Page 2: How to Create S-Curve by MS Project 2010

2Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Sample of Visual in excel

Page 3: How to Create S-Curve by MS Project 2010

3Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

This article is to explain Project Management Concept as a quick reference through step by step guidance using MS Project 2007 or 2010

The targeted audience is a beginner to the project management and experienced with MS Project in early version

Guide line

Page 4: How to Create S-Curve by MS Project 2010

4Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

1. Start Project2. Plan the Tasks3. Assign resources4. Project Baseline set up5. Update progress6. Forecast Information7. Step by Step to S-Curve by using Visual Report

(Export to Excel8. Close Project

Table of Contents

Page 5: How to Create S-Curve by MS Project 2010

5Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Prior to start the project planning, Project manager should be identified, who can set up a project plan in MS project 2010

Step-1: Start Project

1. Create a new Project File

To create a new blank project in Project, click the file tab. Click new

Page 6: How to Create S-Curve by MS Project 2010

6Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

2. Set project start date

Go to Project tab. Click Project information

Step-1: Start Project

Page 7: How to Create S-Curve by MS Project 2010

7Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-1: Start Project3. Define Project Calendar

Go to Project tab. Click Change Working time

Page 8: How to Create S-Curve by MS Project 2010

8Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-1: Start Project4. Save the Project file

Go to Tab file, select save as with Project Name or Job Order running number

Page 9: How to Create S-Curve by MS Project 2010

9Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

In the planning stage, we need to achieved project’s goals. To do this, we have to identify the project’s milestone, deliverables and tasks.

This plan can be use work breakdown structure (WBS).

Step-2: Plan the Tasks

Page 10: How to Create S-Curve by MS Project 2010

10Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-2: Plan the Tasks1. Enter Task Click View tab. In the Task View groups,

click Gantt Chart. In the Task Name fields, enter tasks.

Page 11: How to Create S-Curve by MS Project 2010

11Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-2: Plan the Tasks2. Decide how you want to Schedule Task

In Project 2010, we can schedule tasks manually or automatically. Select schedule method after enter a new tasks by clicking in the Task Mode column:-Note: New Tasks manually set by default in Option Tab

Page 12: How to Create S-Curve by MS Project 2010

12Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-2: Plan the Tasks3. Outline Tasks Create task hierarchy including tasks and

milestones under summary task, which can be represent phase or other work divisions.Click the Task tab. In the Schedule group select Indent or Outdent button• Tip: if you created a summary task with

duration, start or finish date, then the tasks that fall under the summary task will not be rolled up to this summary tasks.

Page 13: How to Create S-Curve by MS Project 2010

13Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-2: Plan the Tasks

Page 14: How to Create S-Curve by MS Project 2010

14Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

4. Enter Durations Click the Duration field for a task and enter a Duration. Two way to entering a duration:-

Mutually Schedule task A number or text like

“Tomorrow” or “Next after roll shell” etc.

Auto Schedule task Number only, 3d=3 Days,

0d=milestone, 6? is an estimate duration.

Note: Both can selected in the Task Mode

Step-2: Plan the Tasks

Page 15: How to Create S-Curve by MS Project 2010

15Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-2: Plan the Tasks

Page 16: How to Create S-Curve by MS Project 2010

16Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-2: Plan the Tasks5. Link Tasks to show relationships

Click the Task tab, in the View Group click Gantt Chart. Select the tasks that you want to link then click the Link Tasks button in the Schedule group, or move a mouse to bar chart press and drack down to tasks that you want to link.To change the default Finish-to-Start (FS), double click the link line and change.

Page 17: How to Create S-Curve by MS Project 2010

17Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-2: Plan the Tasks

Page 18: How to Create S-Curve by MS Project 2010

18Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Assignments are the associations between specific tasks and the resources needed to completed them. We can assign more than one resources to a tasks.

We can assign work resources (People), material (Plates, Shell etc.) and cost (THB) to tasks.

Step-3: Assign Resources

Page 19: How to Create S-Curve by MS Project 2010

19Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-3: Assign Resources1. Add Resources to Project

Click the Task Tab, in the Views dropdown list select Resources Sheet. In the Resources Name filed, type the name of resources that we’ll use in this project.

Page 20: How to Create S-Curve by MS Project 2010

20Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

2. Assign Resources to Tasks

In the Resources Tab, Click Assign Resources the click resources name then click assign

Step-3: Assign Resources

Page 21: How to Create S-Curve by MS Project 2010

21Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-3: Assign Resources3. Enter the Work Hours spending on Tasks

After assign a resources to the Tasks, work hours automatically show in a Work. If PM prefer control a Working hours, it can be change in in Work Field. Entering Work reflects real world scheduling.Go to Gantt Chart, right click on column then click Insert Columns type "WORK” to select the Work Columns

Page 22: How to Create S-Curve by MS Project 2010

22Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-3: Assign Resources

Page 23: How to Create S-Curve by MS Project 2010

23Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-3: Assign Resources

Page 24: How to Create S-Curve by MS Project 2010

24Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-3: Assign Resources4. Know the Work Tasks Type

After Assign a resources to Tasks, MS Project determine how to schedule the tasks based on the tasks type.(Manually tasks don’t use task type) durations may change as we assign resources to tasks.How tasks types workWork, duration and unit are determined by formula:-Work =Duration x Units

Page 25: How to Create S-Curve by MS Project 2010

25Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-3: Assign ResourcesIn a… If we revised

WorkIf we revised Duration

If we revised units

Fixed units tasks Duration changes Work changes Duration changesFixed work tasks Duration changes Units change Duration changesFixed duration tasks Units change Work changes Work changes

To set a default task type for the entire project, click the options. Go to Schedule group, in the default task type box shown fixed units as a default, we can change to Fixed Duration or Fixed Work

To change the task type for an individual, go to tasks tab in properties group click information or to tasks name double click it will appear.

Page 26: How to Create S-Curve by MS Project 2010

26Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-3: Assign Resources

Page 27: How to Create S-Curve by MS Project 2010

27Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-3: Assign Resources5. Identify factors effecting task schedules

We can use MS Project 2010 to help for understanding how changes one task can effect the rest of the project.Click the task tab then in the Schedule group click Inspect Task. A pane opens on the left showing the factors that affect the scheduling of selected task.Or double click in tasks name.

Page 28: How to Create S-Curve by MS Project 2010

28Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-3: Assign Resources

Page 29: How to Create S-Curve by MS Project 2010

29Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Create a baseline or interim plan is to compare between plan and actual.

Saving baseline plan enables to identify and solve discrepancy and plan more accurately for similar future projects.

Step-4: Set the Project Baseline

Page 30: How to Create S-Curve by MS Project 2010

30Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-4: Set the Project Base Line1. Save the baseline plan

After the plan is solidly in place for the finish date, budget and scope, we can submit a plan for approval.Once it has been approved, save the baseline plan.Click the Project tab, in Schedule group click Set Baseline

Page 31: How to Create S-Curve by MS Project 2010

31Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-4: Set the Project Base Line

Page 32: How to Create S-Curve by MS Project 2010

32Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-4: Set the Project Base Line2.View baseline data in Gantt Chart views

In Gantt chart view, move a mouse to gantt area, right click and select Bar Style.

Name Appearance Show for Task

Row From To

Base Plan (Custom)

Select bar shave and color

Select Normal 2 or 3 Baseline Start Baseline finish

Page 33: How to Create S-Curve by MS Project 2010

33Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-4: Set the Project Base Line3. View Baseline in a Table

Go to View tab, in Data group click to Table and select Variance or insert columns with custom field.

Page 34: How to Create S-Curve by MS Project 2010

34Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Updating the progress is the only way to ensure it stays on tracks as work is performed. The focus at this point is on managing changes, updating the schedule, tracking progress and communicating project information.

MS Project 2010 tracks 3 sets of date: Current, Baseline and Actual. When we set the baseline, current = baseline. when a task is 100% complete, current=actual.

Step-5: Update Progress

Page 35: How to Create S-Curve by MS Project 2010

35Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-5: Update Progress1. Manage Change

Managing changes involves modifying duration, date, dependencies, resource assignment or tasks based on requested changes or new information.Keep the current fields up to date and compare to baseline.

Page 36: How to Create S-Curve by MS Project 2010

36Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-5: Update Progress2. Track actual date and duration

It’s the best to decide on a single method for tracking progress. We can enter percentage complete, actual start and finish dates, actual remaining durations or actual and remaining work.Click the Task tab, select the task that we want to enter actual progress. In the Schedule group select the amount of progress done on the tasks.Default: 0%, 25%, 50%, 75%, 100%Note: we can put a number direct to %Complete field

Page 37: How to Create S-Curve by MS Project 2010

37Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-5: Update Progress3. Track Actual Hours and Cost

If we want to enter actual and remaining work hours or costs, use tracking table.Click View tab, in Data group point Table and select Tracking.Enter progress data in the Act. Work or Act. Cost field for the task. Program is determine if we put the actual start and actual finish or % Complete.

Page 38: How to Create S-Curve by MS Project 2010

38Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-5: Update Progress

Page 39: How to Create S-Curve by MS Project 2010

39Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

MS Project 2010 provide many ways of built in report, but for us we have to Visual report to create S-Curve by export to Excel.

Step-6: View Report Information

Page 40: How to Create S-Curve by MS Project 2010

40Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-6: View Report Information1. Select a View MS Project 2010 has old and new views to

help you to see project information and report it to others. Click the View Tab, in either the Task Views group or Resources Views group, select the view you want to use. There’re many view but most useful ones include:-• Team planner View• Timeline View• Gantt Chart View• Calendar View

Page 41: How to Create S-Curve by MS Project 2010

41Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-6: View Report Information

Page 42: How to Create S-Curve by MS Project 2010

42Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-6: View Report Information

Page 43: How to Create S-Curve by MS Project 2010

43Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-6: View Report Information2. Customize a View

Select the view you want to customize and then on the Format tab click the type of view element you want to change, such as the bar style on the Gantt Chart or gridlines and time scales of any views.Tips & Tricks, if you want to filter, sort or group tasks prior to printing, click the View tab and then in the Data group, click sort, Filter or Group options.

Page 44: How to Create S-Curve by MS Project 2010

44Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-6: View Report Information3. Print a View or Report

Set up the current view that we want it to look when printed. Click the File Tab and then click Print. A preview part of the view to see the actual size of the view as it will be printed.

Page 45: How to Create S-Curve by MS Project 2010

45Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-6: View Report Information4. Generate a Report

In Report tab has many report to view information of project but we’re intent to create the S-Curve by using MS Project as a tools, we’ll focus on how to do it.Click the Project tab, go to Reports group, select Visual Report

Page 46: How to Create S-Curve by MS Project 2010

46Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-6: View Report Information Then select Task Usage After that click on View Then it will open to Excel

Page 47: How to Create S-Curve by MS Project 2010

47Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-7: Step by Step to S-Curve In Excel it will export Cost and Cumulative Cost on a

Task Usages Tab

Page 48: How to Create S-Curve by MS Project 2010

48Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Expand a Quarter column

Step-7: Step by Step to S-Curve

Page 49: How to Create S-Curve by MS Project 2010

49Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-7: Step by Step to S-Curve De-select Cost & Cumulative Cost Select Work and Cumulative Work

Page 50: How to Create S-Curve by MS Project 2010

50Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-7: Step by Step to S-Curve Go to Chart1 Tab

Page 51: How to Create S-Curve by MS Project 2010

51Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-7: Step by Step to S-Curve Select to a group of Cumulative bar Right click, then select Change Series Chart Type and

Select “Line”

Page 52: How to Create S-Curve by MS Project 2010

52Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-7: Step by Step to S-Curve It will appear a line on cumulative work The select a group of a small bar Right click and select a Format Data series Series Options lick on Secondary Axis

Page 53: How to Create S-Curve by MS Project 2010

53Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-7: Step by Step to S-Curve Click on bottom area of Graph (Time Scale) Then right click, select Format Axis Go to Alignment select Text Direction, Rotate All Text

270 or 90 degree as you like

Page 54: How to Create S-Curve by MS Project 2010

54Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-7: Step by Step to S-Curve Select line option or bar option as you want it

Page 55: How to Create S-Curve by MS Project 2010

55Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Just because your project is almost finished doesn’t mean that your work is done.

We still need to solve any final project detail and customer acceptance for final deliverables.

Conduct a “Lessons Learned” session, recording information about areas for improvement and best practices.

Make any final update to project plan. Finally archive the project plan according to our

organization’s guideline.

Step-8: Close the Project

Page 56: How to Create S-Curve by MS Project 2010

56Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Step-8: Close the Project1. Save a Project as a Template

After completing a project, we have to leverage what we’ve learned in the project by making it as a template for future projects.Click the File tab and Save As and then in the Save As Type box click Template.

Page 57: How to Create S-Curve by MS Project 2010

57Author: Ong-Art Sanpinit Electrical Charter Engineer วฟก. 1037

Thanks you

End