HARGA DASAR SATUAN UPAH - docshare04.docshare.tips
Transcript of HARGA DASAR SATUAN UPAH - docshare04.docshare.tips
![Page 1: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/1.jpg)
HARGA HARGA SATUANNo. SATUAN SATUAN PER HARI
( Rp.) ( Rp.)
1. Pekerja Jam2. Pekerja Tak Terlatih Jam3. Tukang Jam4. Kepala Tukang Jam5. M a n d o r Jam6. Operator Jam7. Pembantu Operator Jam8. Sopir / Driver Jam9. Pembantu Sopir / Driver Jam10. Mekanik Jam11. Pembantu Mekanik Jam
HARGA DASAR SATUAN UPAH
U R A I A N
![Page 2: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/2.jpg)
HARGANo. SATUAN SATUAN
( Rp.)
1 Pasir Pasang m³2 Pasir Beton (Kasar) m³3 Pasir Halus (untuk HRS) m³4 Pasir Urug (ada unsur lempung) m³5 Pasir Urug m³6 Batu Kali m³7 Batu Bata Buah8 Batu Belah / Kerakal m³9 S i r t u m³10 Bahan Tanah Timbunan m³11 Bahan Pilihan m³12 Batu Kapur m³13 Agregat Kasar m³14 Agregat Halus m³15 Agregat Pecah Mesin 0-5 mm m³16 Agregat Pecah Mesin 5-10 & 10-20 mm m³17 Agregat Pecah Mesin 20-30 mm m³18 F i l l e r Kg19 Bahan Agr.Base Kelas A m³20 Bahan Agr.Base Kelas B m³21 Bahan Agr.Base Kelas C m³22 Chipping m³23 Chipping (kg) m³24 Semen / PC (50kg) Zak25 Semen / PC (kg) Kg26 Semen Berwarna Kg27 Besi Beton Kg28 Kawat Beton Kg29 Kawat Bronjong Kg30 P a k u Kg31 Baja Tulangan (Polos) Kg
HARGA DASAR SATUAN BAHAN
U R A I A N
![Page 3: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/3.jpg)
HARGANo. SATUAN SATUAN
( Rp.)U R A I A N
32 Baja Tulangan (Ulir) Kg33 Kawat Las Dos34 Pipa Baja Kg35 Baja Struktur Kg36 Baja Bergelombang Kg37 Kayu Perancah m³38 Cerucuk Dolken Ø 8 - 10 cm Btg39 Cerucuk Dolken Ø 10 - 15 cm Btg40 Multipleks uk. 122 x 242 x 12 mm Lbr41 Multipleks uk. 122 x 242 x 9 mm Lbr42 Triplek Lbr43 Kayu Acuan m³44 Beton Ready Mix K-125 m³45 Beton Ready Mix K-175 m³46 Beton Ready Mix K-225 m³47 Beton Ready Mix K-300 m³48 Beton Ready Mix K-350 m³49 Beton Ready Mix K-400 m³50 Beton Ready Mix K-500 m³51 Aspal Emulsi Kg52 Aspal Kg53 Asbuton Halus Ton54 Asphalt Trade Base ( ATB ) Ton55 Laston ( Asphalt Concrete ) Ton56 Hot Roll Sheet ( HRS ) Ton57 Sand Sheet Ton58 Kerosen / Minyak Tanah Ltr59 B e n s i n Ltr60 S o l a r Ltr61 Minyak Pelumas / Olie Ltr62 Minyak Fluks Ltr63 Pipa Galvanis Dia 3" m'64 Pipa Galvanis Dia 1" m'65 Pipa Galvanis Dia 1,5" m'
![Page 4: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/4.jpg)
HARGANo. SATUAN SATUAN
( Rp.)U R A I A N
66 Pipa Galvanis Dia 2" m'67 Pipa Galvanis Dia. 1.6" Batang68 Pipa Porus m'69 Pipa Beton Precast tdk Bertulang Ø 30 cm, 125 cm Buah70 Pipa Beton Precast tdk Bertulang Ø 40 cm, 125 cm Buah71 Pipa Beton Precast tdk Bertulang Ø 50 cm, 125 cm Buah72 Pipa Beton Precast tdk Bertulang Ø 60 cm, 250 cm Buah73 Pipa Beton Precast tdk Bertulang Ø 80 cm, 250 cm Buah74 Pipa Beton Precast tdk Bertulang Ø 90 cm, 250 cm Buah75 Pipa Beton Precast tdk Bertulang Ø 100 cm, 250 cm Buah76 Pipa Beton Precast Bertulang Ø 30 cm, 250 cm Buah77 Pipa Beton Precast Bertulang Ø 40 cm, 250 cm Buah78 Pipa Beton Precast Bertulang Ø 50 cm, 250 cm Buah79 Pipa Beton Precast Bertulang Ø 60 cm, 250 cm Buah80 Pipa Beton Precast Bertulang Ø 70 cm, 250 cm Buah81 Pipa Beton Precast Bertulang Ø 80 cm, 250 cm Buah82 Pipa Beton Precast Bertulang Ø 90 cm, 250 cm Buah83 Pipa Beton Precast Bertulang Ø 100 cm, 250 cm Buah84 Pipa Beton Precast Bertulang Ø 120 cm, 250 cm Buah85 Pipa Beton Precast Bertulang Ø 130 cm, 250 cm Buah86 Pipa Beton Precast Bertulang Ø 150 cm, 250 cm Buah87 Cat Kg88 Cat Marka (Non Thermoplas) Kg89 Cat Marka (Thermoplastic) Kg90 Plastik Filter m²91 Geotextile m²92 Thinner Ltr93 Glass Bead Kg94 Pelat Rambu (Eng. Grade) Buah95 Pelat Rambu (High I. Grade) Buah96 Rel Pengaman m'97 Gebalan Rumput m²98 Mata Kucing Buah99 Kansteen 15.25.40 Buah
![Page 5: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/5.jpg)
HARGANo. SATUAN SATUAN
( Rp.)U R A I A N
100 Kansteen 13.20.40 Buah101 Kansteen 15.28.40 Buah102 Kansteen 20.25.60 Buah103 Kansteen 30.25.50 Buah104 Paving Block 8.10.20 m²105 Paving Block 8.10.20 (Press Hydraulix / Press Mesin) m²106 Paving Block 6.10.20 (Press Hydraulix / Press Mesin) m²107 Matras Concrete Buah108 Marmer Buah109 Keramik Berwarna 30 x 30 m²110 Plastic Sheet m²111 Concrete Treated Base (CTB) m³112 Gorong² Buis Beton, Ø 30 cm ; P = 100 cm m'113 Gorong² Buis Beton, Ø 40 cm ; P = 100 cm m'114 Gorong² Buis Beton, Ø 50 cm ; P = 100 cm m'115 Gorong² Buis Beton, Ø 60 cm ; P = 100 cm m'116 Gorong² Buis Beton (1/2), Ø U 30 cm ; P = 100 cm m'117 Gorong² Buis Beton (1/2), Ø U 40 cm ; P = 100 cm m'118 Gorong² Buis Beton (1/2), Ø U 50 cm ; P = 100 cm m'119 Gorong² Buis Beton (1/2), Ø U 60 cm ; P = 100 cm m'120 Kawat Bronjong Pabrikasi 0,5 x 1 x 2 m Buah121 Karung Buah122 Box Culvert BC 400 x 400 HD Buah123 Box Culvert BC 500 x 500 HD Buah124 Box Culvert BC 600 x 600 HD Buah125 Box Culvert BC 800 x 800 HD Buah126 Box Culvert BC 1000 x 1000 HD Buah127 Box Culvert BC 1200 x 1200 HD Buah128 Box Culvert BC 1400 x 1400 HD Buah129 Box Culvert BC 1500 x 1500 HD Buah130 Saluran Terbuka Tipe U-Ditch 300/300 ; P = 120 cm Buah131 Saluran Terbuka Tipe U-Ditch 400/400 ; P = 120 cm Buah132 Saluran Terbuka Tipe U-Ditch 500/500 ; P = 120 cm Buah133 Saluran Terbuka Tipe U-Ditch 600/600 ; P = 120 cm Buah
![Page 6: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/6.jpg)
HARGANo. SATUAN SATUAN
( Rp.)U R A I A N
134 Saluran Terbuka Tipe U-Ditch 800/800 ; P = 120 cm Buah135 Saluran Terbuka Tipe U-Ditch 800/1000 ; P = 120 cm Buah136 Saluran Terbuka Tipe U-Ditch 800/1200 ; P = 120 cm Buah137 Saluran Terbuka Tipe U-Ditch 1000/1000 ; P = 120 cm Buah138 Saluran Terbuka Tipe U-Ditch 1200/1200 ; P = 120 cm Buah139 Saluran Terbuka Tipe U-Ditch 1400/1400 ; P = 120 cm Buah140 Saluran Terbuka Tipe U-Ditch 1500/1500 ; P = 120 cm Buah141 Saluran Terbuka Tipe U-Ditch 1600/1600 ; P = 120 cm Buah142 Sheet Pile Corrugated Type W-325-A-1000 P : 8-13, K-700 m'143 Sheet Pile Corrugated Type W-325-B-1000 P : 8-14, K-700 m'144 Sheet Pile Corrugated Type W-350-A-1000 P : 9-15, K-700 m'145 Sheet Pile Corrugated Type W-350-B-1000 P : 10-15, K-700 m'146 Sheet Pile Corrugated Type W-400-A-1000 P : 10-16, K-700 m'147 Sheet Pile Corrugated Type W-400-B-1000 P : 11-16, K-700 m'148 Sheet Pile Corrugated Type W-450-A-1000 P : 11-17, K-700 m'149 Sheet Pile Corrugated Type W-450-B-1000 P : 12-17, K-700 m'150 Flat Sheet Pile, K-700 m'151 Tiang Pancang Type A2-300 - 6 s/d 8, Segmen Bottom m'152 Tiang Pancang Type A2-300 - 6 s/d 8, Segmen Bottom Pencil m'153 Tiang Pancang Type A2-300 - 6 s/d 8, Segmen Middle m'154 Tiang Pancang Type A2-400 - 6 s/d 8, Segmen Bottom m'155 Tiang Pancang Type A2-400 - 6 s/d 8, Segmen Bottom Pencil m'156 Tiang Pancang Type A2-400 - 6 s/d 8, Segmen Middle m'157 Pipa PVC D 15 cm / 6" m'158 Mur Baut Kg159 Besi Plat Strip Kg160 Baja Anyaman Kg161 Section Steel Kg162 Fitting & Support / Reducer Buah163 Non Shrinkage Mortar Kg164 Epoxy Premarking Ltr165 Epoxy Adhesive Ltr166 Bearing Pad Elastomer Uk. 350 x 400 x 39 Buah167 Expansion Joint Type Asphaltic Plug m'
![Page 7: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/7.jpg)
HARGANo. SATUAN SATUAN
( Rp.)U R A I A N
168 Girder Type I, 20,60 m H = 70 cm Buah169 Girder Type I, 45,70 m H = 240 cm Buah
![Page 8: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/8.jpg)
1 ASPHALT MIXING PLANT2 ASPHALT FINISHER3 ASPHALT SPRAYER4 BULLDOZER 100-150 HP5 COMPRESSOR 4000-6500 L\M6 CONCRETE MIXER 0.3-0.6 M37 CRANE 10-15 TON8 DUMP TRUCK 3.5 TON9 DUMP TRUCK 10 TON
10 EXCAVATOR 80-140 HP11 FLAT BED TRUCK 3-4 M312 GENERATOR SET13 MOTOR GRADER >100 HP14 TRACK LOADER 75-100 HP15 WHEEL LOADER 1.0-1.6 M316 THREE WHEEL ROLLER 6-8 T17 TANDEM ROLLER 6-8 T.18 TIRE ROLLER 8-10 T.19 VIBRATORY ROLLER 5-8 T.20 CONCRETE VIBRATOR21 STONE CRUSHER22 WATER PUMP 70-100 mm23 WATER TANKER 3000-4500 L.24 PEDESTRIAN ROLLER25 TAMPER26 JACK HAMMER27 FULVI MIXER28 CONCRETE PUMP29 TRAILER 20 TON30 PILE DRIVER + HAMMER (2,5 Ton)31 PILE DRIVER + HAMMER (15 Ton)32 CRANE ON TRACK 35 TON
BIAYA SEWA ALAT
No. URAIAN HP KAPASITASALAT
TOTAL BIAYA SEWA ALAT /
JAM( Rp. )
![Page 9: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/9.jpg)
No. URAIAN HP KAPASITASALAT
TOTAL BIAYA SEWA ALAT /
JAM( Rp. )
33 WELDING SET34 BORE PILE MACHINE35 ASPHALT LIQUID MIXER36 TRONTON37 COLD MILLING38 ROCK DRILL BREAKER39 COLD RECYCLER40 HOT RECYCLER41 AGGREGAT (CHIP) SPREADER42 ASPHALT DISTRIBUTOR43 SLIP FORM PAVER44 CONCRETE BREAKER45 ASPHALT TANKER46 CEMENT TANKER47 CONCRETE MIXER (350)48 VIBRATING RAMMER49 TRUK MIXER (AGITATOR)50 BORE PILE MACHINE51 CRANE ON TRACK 75-100 TON52 BLENDING EQUIPMENT53 ASPHALT LIQUID MIXER54 TRUCK PICK UP55 CONCRETE CUTTER56 MINI BORE PILE MACHINE57 CRANE 100 - 150 TON58 LINE MARKER TRUCK59 FLAT BED TRUCK W/ CRANE 4 TON60 TRAVELLER BEAM SET61 HYDRAULIC JACK 150 TON62 SINGLE CAGE ELEVATOR (HOIST) 63 LAUNCHING GIRDER
![Page 10: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/10.jpg)
ITEM PEMBAYARAN : AGREGAT KASAR & HALUSJENIS PEKERJAAN : PENGADAAN AGREGAT KASAR & HALUSSATUAN PEMBAYARAN : M3
No. KODE KOEFISIEN SATUAN
I ASUMSI
II METHODE PELAKSANAAN
III PERHITUNGAN
ANALISA HARGA DASAR SATUAN BAHAN
U R A I A N
![Page 11: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/11.jpg)
ITEM PEMBAYARAN : AGREGAT KELAS AJENIS PEKERJAAN : PENGADAAN AGREGAT KELAS ASATUAN PEMBAYARAN : M3
No. KODE KOEFISIEN SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
ANALISA HARGA DASAR SATUAN BAHAN
U R A I A N
![Page 12: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/12.jpg)
ITEM PEMBAYARAN : AGREGAT KELAS BJENIS PEKERJAAN : PENGADAAN AGREGAT KELAS BSATUAN PEMBAYARAN : M3
No. KODE KOEFISIEN SATUAN
I ASUMSI
II URUTAN PEKERJAAN
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
ANALISA HARGA DASAR SATUAN BAHAN
U R A I A N
![Page 13: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/13.jpg)
ITEM PEMBAYARAN : AGREGAT KELAS BJENIS PEKERJAAN : PENGADAAN AGREGAT KELAS CSATUAN PEMBAYARAN : M3
No. KODE KOEFISIEN SATUAN
I ASUMSI
II METHODE PELAKSANAAN
III.1 PROSES PENCAMPURAN AGREGAT KELAS C
III.2 HARGA SATUAN BAHAN AGREGAT KELAS C
ANALISA HARGA DASAR SATUAN BAHAN
U R A I A N
![Page 14: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/14.jpg)
ITEM PEMBAYARAN NO. : AGREGAT KELAS AJENIS PEKERJAAN : PENGADAAN AGREGAT KELAS ASATUAN PEMBAYARAN : M3
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Mandor (L03) jam
-
B. BAHAN
1. Agregat 20-30 M17 M3
2. Agregat 5-10 & 10-20 M16 M3
3. Pasir Urug M01e M3
JUMLAH HARGA BAHAN -
C. PERALATAN1. Wheel Loader E15 jam2. Blending Equpment E52 jam3. Alat Bantu Ls
JUMLAH HARGA PERALATAN -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH
ANALISAHARGA DASAR SATUAN BAHAN
![Page 15: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/15.jpg)
ITEM PEMBAYARAN NO. : AGREGAT KELAS BJENIS PEKERJAAN : PENGADAAN AGREGAT KELAS BSATUAN PEMBAYARAN : M3
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Mandor (L03) jam
-
B. BAHAN
1. Aggregat 20-30 M17 M3
2. Agg 5 - 10 & 10 - 20 M16 M3
3. Sirtu M08 M3
-
PERALATANWheel Loader E15 jamBlending Equpment E52 jamAlat Bantu Ls
-
JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA
ANALISAHARGA DASAR SATUAN BAHAN
JUMLAH
![Page 16: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/16.jpg)
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : Pasir PasangLokasi : QuarryTujuan : Lokasi Pekerjaan
HARGANo. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
II. URUTAN KERJA
III. PERHITUNGAN
![Page 17: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/17.jpg)
HARGANo. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
IV. HARGA SATUAN DASAR BAHANDI LOKASI BASE CAMP
![Page 18: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/18.jpg)
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : Pasir BetonLokasi : QuarryTujuan : Lokasi Pekerjaan
HARGANo. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
II. URUTAN KERJA
III. PERHITUNGAN
![Page 19: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/19.jpg)
HARGANo. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
IV. HARGA SATUAN DASAR BAHANDI LOKASI PEKERJAAN
![Page 20: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/20.jpg)
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : Pasir UrugLokasi : QuarryTujuan : Lokasi Pekerjaan
HARGANo. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
II. URUTAN KERJA
III. PERHITUNGAN
![Page 21: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/21.jpg)
HARGANo. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
IV. HARGA SATUAN DASAR BAHANDI LOKASI PEKERJAAN
![Page 22: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/22.jpg)
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : Batu KaliLokasi : QuarryTujuan : Lokasi Pekerjaan
HARGANo. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
II. URUTAN KERJA
III. PERHITUNGAN
![Page 23: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/23.jpg)
HARGANo. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
IV. HARGA SATUAN DASAR BAHANDI LOKASI PEKERJAAN
![Page 24: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/24.jpg)
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : Batu BelahLokasi : QuarryTujuan : Lokasi Pekerjaan
HARGANo. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
II. URUTAN KERJA
III. PERHITUNGAN
![Page 25: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/25.jpg)
HARGANo. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
IV. HARGA SATUAN DASAR BAHANDI LOKASI PEKERJAAN
![Page 26: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/26.jpg)
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : SirtuLokasi : QuarryTujuan : Lokasi Pekerjaan
HARGANo. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
II. URUTAN KERJA
III. PERHITUNGAN
![Page 27: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/27.jpg)
HARGANo. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
IV. HARGA SATUAN DASAR BAHANDI LOKASI PEKERJAAN
![Page 28: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/28.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
ASPHALT MIXING PLANT
U R A I A N
ANALISA BIAYA SEWA ALAT
![Page 29: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/29.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
U R A I A N
ASPHALT FINISHER
ANALISA BIAYA SEWA ALAT
![Page 30: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/30.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ASPHALT SPRAYER
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 31: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/31.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
BULLDOZER 100-150 HP
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 32: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/32.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
COMPRESSOR 4000-6500 L\M
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 33: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/33.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
CONCRETE MIXER 0.3-0.6 M3
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 34: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/34.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
CRANE 10-15 TON
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 35: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/35.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
DUMP TRUCK 3.5 TON
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 36: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/36.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
DUMP TRUCK 10 TON
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 37: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/37.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
EXCAVATOR 80-140 HP
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 38: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/38.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
FLAT BED TRUCK 3-4 M3
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 39: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/39.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
GENERATOR SET
![Page 40: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/40.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
MOTOR GRADER >100 HP
![Page 41: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/41.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
TRACK LOADER 75-100 HP
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 42: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/42.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
WHEEL LOADER 1.0-1.6 M3
![Page 43: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/43.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
THREE WHEEL ROLLER 6-8 T
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 44: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/44.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
TANDEM ROLLER 6-8 T.
![Page 45: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/45.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
TIRE ROLLER 8-10 T.
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 46: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/46.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
VIBRATORY ROLLER 5-8 T.
![Page 47: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/47.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
CONCRETE VIBRATOR
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 48: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/48.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
STONE CRUSHER
![Page 49: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/49.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
WATER PUMP 70-100 mm
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 50: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/50.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
WATER TANKER 3000-4500 L.
![Page 51: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/51.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
PEDESTRIAN ROLLER
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 52: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/52.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
TAMPER
![Page 53: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/53.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
JACK HAMMER
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 54: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/54.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
FULVI MIXER
![Page 55: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/55.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
CONCRETE PUMP
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 56: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/56.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
TRAILER 20 TON
![Page 57: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/57.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
PILE DRIVER + HAMMER (2,5 Ton)
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 58: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/58.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
PILE DRIVER + HAMMER (15 Ton)
![Page 59: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/59.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
CRANE ON TRACK 35 TON
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 60: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/60.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
WELDING SET
![Page 61: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/61.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
BORE PILE MACHINE
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 62: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/62.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
ASPHALT LIQUID MIXER
![Page 63: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/63.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ASPHALT LIQUID MIXER
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 64: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/64.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
TRONTON
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 65: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/65.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
COLD MILLING MACHINE
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 66: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/66.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ROCK DRILL BREAKER
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 67: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/67.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
COLD RECYCLER
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 68: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/68.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
HOT RECYCLER
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 69: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/69.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
AGGREGAT (CHIP) SPREADER
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 70: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/70.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ASPHALT DISTRIBUTOR
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 71: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/71.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
SLIP FORM PAVER
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 72: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/72.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
CONCRETE PAN MIXER
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 73: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/73.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
CONCRETE BREAKER
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 74: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/74.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ASPHALT TANKER
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 75: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/75.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
CEMENT TANKER
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 76: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/76.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
CONCRETE MIXER (350)
![Page 77: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/77.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
VIBRATING RAMMER
![Page 78: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/78.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
TRUK MIXER (AGITATOR)
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 79: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/79.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
BORE PILE MACHINE
![Page 80: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/80.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
CRANE ON TRACK 75-100 TON
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 81: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/81.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
BLENDING EQUIPMENT
![Page 82: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/82.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
TRUCK PICK UP
ANALISA BIAYA SEWA ALAT
U R A I A N
![Page 83: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/83.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
ANALISA BIAYA SEWA ALAT
U R A I A N
CONCRETE CUTTER
![Page 84: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/84.jpg)
No. KODE KOEF. SATUAN
A. URAIAN PERALATAN
B. BIAYA PASTI PER JAM KERJA
C. BIAYA OPERASI PER JAM KERJA
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P )
E. LAIN - LAIN
U R A I A N
MINI BORE PILE MACHINE
ANALISA BIAYA SEWA ALAT
![Page 85: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/85.jpg)
Analisa SNI-854
JENIS PEKERJAAN : Pasang Papan Nama ProyekSATUAN PEMBAYARAN : Bh
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01.a) Org/hari2. Tukang Kayu (L02) Org/hari3. Kepala Tukang (L10) Org/hari4. Mandor (L03) Org/hari
-
B. BAHAN
1. Kayu Kaso M40 M3
2. Triplek 5 mm M39.c lbr3. Cat kayu M85 Kg4. Minyak Cat M102 Kg5. Paku M30 Kg6. Kwas - bh
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
ANALISAHARGA SATUAN PEKERJAAN
![Page 86: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/86.jpg)
Analisa SNI-164
JENIS PEKERJAAN : Pasangan Batu Bata ad. 1 Pc : 4 PsrSATUAN PEMBAYARAN : M2
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Org/hari2. Tukang Kayu (L02) Org/hari3. Kepala Tukang (L10) Org/hari4. Mandor (L03) Org/hari
-
B. BAHAN
1. Batu Bata M03 M3
2. Semen PC M25 Zak3. Pasir Pasang M01a Kg
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
![Page 87: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/87.jpg)
Analisa SNI-165
JENIS PEKERJAAN : Plesteran Dan Acian Camp. 1 Pc : 4 PsrSATUAN PEMBAYARAN : M2
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Org/hari2. Tukang Kayu (L02) Org/hari3. Kepala Tukang (L10) Org/hari4. Mandor (L03) Org/hari
-
B. BAHAN
1. Semen PC M25 Zak2. Pasir Pasang M01a Kg
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
ANALISAHARGA SATUAN PEKERJAAN
![Page 88: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/88.jpg)
Analisa SNI-166
JENIS PEKERJAAN : Plesteran Siar Camp. 1 Pc : 2 PsrSATUAN PEMBAYARAN : M2
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Org/hari2. Tukang Kayu (L02) Org/hari3. Kepala Tukang (L10) Org/hari4. Mandor (L03) Org/hari
-
B. BAHAN
1. Semen PC M25 Zak2. Pasir Pasang M01a Kg
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 89: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/89.jpg)
Analisa SNI-856
JENIS PEKERJAAN : Pengecatan KansteenSATUAN PEMBAYARAN : M2
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Org/hari2. Tukang Cat (L02) Org/hari3. Kepala Tukang (L10) Org/hari4. Mandor (L03) Org/hari
-
B. BAHAN
1. Cat Dasar M85 Kg2. Cat Penutup M99 Kg
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 90: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/90.jpg)
Analisa SNI-857
JENIS PEKERJAAN : Pemasangan Keramik 30 x 30 BerwarnaSATUAN PEMBAYARAN : M2
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Org/hari2. Tukang Batu (L02) Org/hari3. Kepala Tukang (L10) Org/hari4. Mandor (L03) Org/hari
-
B. BAHAN
1. Keramik Berwarna M113 M2
uk. 30 x 30 KW. 12. Semen Portland M26 Kg3. Pasir Pasang M01a M3
4. Semen Warna M26a Kg
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 91: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/91.jpg)
Analisa SNI-858.a
JENIS PEKERJAAN : Pemasangan Rambu Lalu Lintas uk. 45 x 45 cmSATUAN PEMBAYARAN : Bh
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. UPAH
1. Pemotongan dan Pengeboran Unit2. Pengelasan Cm3. Perakitan dan Penyetelan Unit4. Pengecatan Belakang Daun Rambu M2
5. Ongkos Angkut ke Lokasi Bh
-
B. BAHAN
1. Daun Rambu Alumunium 1,8 mm M2
dgn Reflective Sheeting2. Pipa Galvanis 1,5" M60.c M'3. Plat Strip uk. 4 x 30 mm M'4. Angkur Besi Siku uk. 30 x 30 x 3 mm M'5. Mur Baut Bh6. Tutup Pipa dia. 1,5" Bh7. Cor Pondasi Beton EI-616 BS M3
8. Galian Tanah dan Urug Kembali EI-213 M3
9. Urugan Pasir Bawah Pondasi EI-162 M3
10. Bekisting Pondasi EI-671 M3
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA UPAH
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 92: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/92.jpg)
F. HARGA SATUAN PEKERJAAN ( D + E ) -
![Page 93: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/93.jpg)
Analisa SNI-858.b
JENIS PEKERJAAN : Pemasangan Rambu Lalu Lintas uk. 60 x 60 cmSATUAN PEMBAYARAN : Bh
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. UPAH
1. Pemotongan dan Pengeboran Unit2. Pengelasan Cm3. Perakitan dan Penyetelan Unit4. Pengecatan Belakang Daun Rambu M2
5. Ongkos Angkut ke Lokasi Bh
-
B. BAHAN
1. Daun Rambu Alumunium 1,8 mm M2
dgn Reflective Sheeting2. Pipa Galvanis 1,5" M60.c M'3. Plat Strip uk. 4 x 30 mm M'4. Angkur Besi Siku uk. 30 x 30 x 3 mm M'5. Mur Baut Bh6. Tutup Pipa dia. 1,5" Bh7. Cor Pondasi Beton EI-616 BS M3
8. Galian Tanah dan Urug Kembali EI-213 M3
9. Urugan Pasir Bawah Pondasi EI-162 M3
10. Bekisting Pondasi EI-671 M3
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA UPAH
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 94: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/94.jpg)
Analisa SNI-858.c
JENIS PEKERJAAN : Pemasangan Rambu Lalu Lintas uk. 75 x 75 cmSATUAN PEMBAYARAN : Bh
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. UPAH
1. Pemotongan dan Pengeboran Unit2. Pengelasan Cm3. Perakitan dan Penyetelan Unit4. Pengecatan Belakang Daun Rambu M2
5. Ongkos Angkut ke Lokasi Bh
-
B. BAHAN
1. Daun Rambu Alumunium 1,8 mm M2
dgn Reflective Sheeting2. Pipa Galvanis 2" M60.d M'3. Plat Strip uk. 4 x 30 mm M'4. Angkur Besi Siku uk. 30 x 30 x 3 mm M'5. Mur Baut Bh6. Tutup Pipa dia. 2" Bh7. Cor Pondasi Beton EI-616 BS M3
8. Galian Tanah dan Urug Kembali EI-213 M3
9. Urugan Pasir Bawah Pondasi EI-162 M3
10. Bekisting Pondasi EI-671 M3
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA UPAH
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 95: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/95.jpg)
Analisa SNI-858.d
JENIS PEKERJAAN : Pemasangan Rambu Lalu Lintas uk. 90 x 90 cmSATUAN PEMBAYARAN : Bh
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. UPAH
1. Pemotongan dan Pengeboran Unit2. Pengelasan Cm3. Perakitan dan Penyetelan Unit4. Pengecatan Belakang Daun Rambu M2
5. Ongkos Angkut ke Lokasi Bh
-
B. BAHAN
1. Daun Rambu Alumunium 2 mm M2
dgn Reflective Sheeting2. Pipa Galvanis 2" M60.d M'3. Plat Strip uk. 4 x 40 mm M'4. Angkur Besi Siku uk. 30 x 30 x 3 mm M'5. Mur Baut Bh6. Tutup Pipa dia. 2" Bh7. Cor Pondasi Beton EI-616 BS M3
8. Galian Tanah dan Urug Kembali EI-213 M3
9. Urugan Pasir Bawah Pondasi EI-162 M3
10. Bekisting Pondasi EI-671 M3
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA UPAH
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 96: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/96.jpg)
JENIS PEKERJAAN : GALIAN LUMPUR DAN PEMBUANGAN ( ALAT )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Mandor (L03) jam
JUMLAH HARGA TENAGA -
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
1. Excavator E10 jam2. Dump Truck E08 jam
JUMLAH HARGA PERALATAN -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHHARGA
(Rp.)
ANALISAHARGA SATUAN PEKERJAAN
Analisa EI-113
![Page 97: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/97.jpg)
JENIS PEKERJAAN : GALIAN LUMPUR BUANG DITEMPAT ( ALAT )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Mandor (L03) jam
JUMLAH HARGA TENAGA -
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
1. Excavator E10 jam
JUMLAH HARGA PERALATAN -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHHARGA
(Rp.)
Analisa EI-113.a
ANALISAHARGA SATUAN PEKERJAAN
![Page 98: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/98.jpg)
JENIS PEKERJAAN : GALIAN LUMPUR DAN PEMBUANGAN ( MANUAL )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01.a) jam2. Mandor (L03) jam
JUMLAH HARGA TENAGA -
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
1. Truck Pick Up E53 jam
JUMLAH HARGA PERALATAN -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
Analisa EI-114
ANALISA
![Page 99: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/99.jpg)
JENIS PEKERJAAN : GALIAN LUMPUR BUANG DITEMPAT ( MANUAL)SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01.a) jam2. Mandor (L03) jam
JUMLAH HARGA TENAGA -
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
Analisa EI-115
![Page 100: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/100.jpg)
JENIS PEKERJAAN : PASANGAN BATU KALI UNTUK SALURAN (ALAT)SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang Batu (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Batu Kali M02 M32. Semen (PC) M25 zak3. Pasir Pasang M01a M3
-
C. PERALATAN
1. Conc. Mixer E06 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-121
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 101: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/101.jpg)
JENIS PEKERJAAN : PASANGAN BATU KALI UNTUK SALURAN (BURUH)SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang Batu (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Batu Kali M02 M32. Semen (PC) M25 zak3. Pasir Pasang M01a M3
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-122
ANALISA
![Page 102: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/102.jpg)
JENIS PEKERJAAN : PASANGAN BATU KOSONGSATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang Batu (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Batu Kali M02 M3
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-122.a
ANALISAHARGA SATUAN PEKERJAAN
![Page 103: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/103.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton, Ø 30 cm ; P = 100 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Gorong-gorong Buis Beton M117 bhØ 30 cm panj. 100 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 jam2. Flat Bed Truck E11 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-1311
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 104: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/104.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton, Ø 40 cm ; P = 100 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Gorong-gorong Buis Beton M118 bhØ 40 cm panj. 100 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 jam2. Flat Bed Truck E11 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-1312
ANALISA
![Page 105: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/105.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton, Ø 50 cm ; P = 100 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Gorong-gorong Buis Beton M119 bhØ 50 cm panj. 100 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 jam2. Flat Bed Truck E11 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-1313
ANALISAHARGA SATUAN PEKERJAAN
![Page 106: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/106.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton, Ø 60 cm ; P = 100 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Gorong-gorong Buis Beton M120 bhØ 60 cm panj. 100 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 jam2. Flat Bed Truck E11 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-1314
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 107: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/107.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton (1/2), Ø U 30 cm ; P = 100 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Gorong-gorong Buis Beton (1/2) M117.a bhØ U 30 cm panj. 100 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 jam2. Flat Bed Truck E11 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-1321
ANALISA
![Page 108: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/108.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton (1/2), Ø U 40 cm ; P = 100 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Gorong-gorong Buis Beton (1/2) M118.a bhØ U 40 cm panj. 100 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 jam2. Flat Bed Truck E11 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-1322
ANALISAHARGA SATUAN PEKERJAAN
![Page 109: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/109.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton (1/2), Ø U 50 cm ; P = 100 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Gorong-gorong Buis Beton (1/2) M119.a bhØ U 50 cm panj. 100 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 jam2. Flat Bed Truck E11 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-1323
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 110: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/110.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton (1/2), Ø U 60 cm ; P = 100 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Gorong-gorong Buis Beton (1/2) M120.a bhØ U 60 cm panj. 100 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 jam2. Flat Bed Truck E11 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-1324
ANALISA
![Page 111: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/111.jpg)
JENIS PEKERJAAN : Gorong² Precast Pipa Beton Tak Bertulang, Ø 30 cm ; P = 125 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Gorong-gorong tidak bertulang M62 bhØ 30 cm panj. 125 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 jam2. Flat Bed Truck E11 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-130
ANALISAHARGA SATUAN PEKERJAAN
![Page 112: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/112.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 40 cm ; P = 125 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Gorong-gorong tidak bertulang M62.a bh
Ø 40 cm panj. 125 cm2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 jam
2. Flat Bed Truck E11 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-131
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 113: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/113.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 50 cm ; P = 125 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Gorong-gorong tidak bertulang Ø 50 cm M62.b bh
panj. 125 cm2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-132
ANALISA
![Page 114: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/114.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 60 cm, Panj. 250 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Gorong-gorong tidak bertulang Ø 60 cm M62.c bh
panj. 250 cm2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-133
ANALISAHARGA SATUAN PEKERJAAN
![Page 115: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/115.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 80 cm, Panj. 250 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Gorong-gorong tidak bertulang Ø 80 cm M62.d bh
panj. 250 cm2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-134
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 116: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/116.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 90 cm, P = 250 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Gorong-gorong tidak bertulang Ø 90 cm M62.e bh
panj. 250 cm2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-135
ANALISA
![Page 117: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/117.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 100 cm, P = 250 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Gorong-gorong tidak bertulang Ø 100 cm M62.f bh
panj. 250 cm2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) -
E. OVERHEAD & PROFIT 10 % x D -
F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-136
ANALISAHARGA SATUAN PEKERJAAN
![Page 118: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/118.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 30 cm, P = 250 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Gorong-gorong bertulang Ø 30 cm M63 bh
panj. 250 cm2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-140
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 119: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/119.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 40 cm, P = 250 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Gorong-gorong bertulang Ø 40 cm M63.a bh
panj. 250 cm2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-141
ANALISA
![Page 120: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/120.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 50 cm, P = 250 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Gorong-gorong bertulang Ø 50 cm M63.b bh
panj. 250 cm2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-142
ANALISAHARGA SATUAN PEKERJAAN
![Page 121: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/121.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 60 cm, P = 250 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Gorong-gorong bertulang Ø 60 cm M63.c bh
panj. 250 cm2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-143
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 122: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/122.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 70 cm, P = 250 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Gorong-gorong bertulang Ø 70 cm M63.d bh
panj. 250 cm2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-144
ANALISA
![Page 123: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/123.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 80 cm, P = 250 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Gorong-gorong bertulang Ø 80 cm M63.e bh
panj. 250 cm2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-145
ANALISAHARGA SATUAN PEKERJAAN
![Page 124: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/124.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 90 cm, P = 250 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Gorong-gorong bertulang Ø 90 cm M63.f bhpanj. 250 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-146
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 125: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/125.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 100 cm, P = 250 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Gorong-gorong bertulang Ø 100 cm M63.g bhpanj. 250 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-147
ANALISA
![Page 126: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/126.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 120 cm, P = 250 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Gorong-gorong bertulang Ø 120 cm M63.h bhpanj. 250 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-148
ANALISAHARGA SATUAN PEKERJAAN
![Page 127: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/127.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 150 cm, P = 250 cmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Gorong-gorong bertulang Ø 150 cm M63.j bhpanj. 250 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-149
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 128: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/128.jpg)
JENIS PEKERJAAN : GORONG-GORONG PIPA BAJA BERGELOMBANGSATUAN PEMBAYARAN : Ton
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Pipa Baja Glb. M35 Kg2. Urugan Porus (EI-161) M33. Mat. Pilihan M10 M3
-
C. PERALATAN
1. Tamper E25 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-150
ANALISA
![Page 129: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/129.jpg)
JENIS PEKERJAAN : Timbunan Porous atau Bahan Penyaring (Filter)SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Agregat Kasar M13 M32. Pasir M01b M3
-
C. PERALATAN
1. Tamper E25 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-161
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 130: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/130.jpg)
JENIS PEKERJAAN : Timbunan PasirSATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1 Pasir Urug M01e M3
-
C. PERALATAN
1. Tamper E25 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-162
ANALISA
![Page 131: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/131.jpg)
JENIS PEKERJAAN : KisdamSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Karung M114 buah2. Cerucuk Dolken Ø 8 - 10 cm M38.a M'
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-171
ANALISA
![Page 132: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/132.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 400 x 400 HDSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Box Culvert BC 400 x 400 HD M122.a bhpanjang 100 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-181
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 133: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/133.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 500 x 500 HDSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Box Culvert BC 500 x 500 HD M122.b bhpanjang 100 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-182
ANALISA
![Page 134: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/134.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 600 x 600 HDSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Box Culvert BC 600 x 600 HD M122.c bhpanjang 100 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-183
ANALISAHARGA SATUAN PEKERJAAN
![Page 135: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/135.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 800 x 800 HDSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Box Culvert BC 800 x 800 HD M122.d bhpanjang 100 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-184
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 136: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/136.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 1000 x 1000 HDSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Box Culvert BC 1000 x 1000 HD M122.e bhpanjang 100 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-185
ANALISA
![Page 137: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/137.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 1200 x 1200 HDSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Box Culvert BC 1200 x 1200 HD M122.f bhpanjang 100 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-186
ANALISAHARGA SATUAN PEKERJAAN
![Page 138: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/138.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 1400 x 1400 HDSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Box Culvert BC 1400 x 1400 HD M122.g bhpanjang 100 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-187
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 139: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/139.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 1500 x 1500 HDSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Box Culvert BC 1400 x 1400 HD M122.h bhpanjang 100 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-188
ANALISA
![Page 140: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/140.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 300/300SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. U-Ditch uk. 300/300 M130 bhpanjang 120 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-191
ANALISAHARGA SATUAN PEKERJAAN
![Page 141: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/141.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 400/400SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. U-Ditch uk. 400/400 M131 bhpanjang 120 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-192
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 142: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/142.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 500/500SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. U-Ditch uk. 500/500 M132 bhpanjang 120 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-193
ANALISA
![Page 143: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/143.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 600/600SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. U-Ditch uk. 600/600 M133 bhpanjang 120 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-194
ANALISAHARGA SATUAN PEKERJAAN
![Page 144: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/144.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 800/800SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. U-Ditch uk. 800/800 M134 bhpanjang 120 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-195
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 145: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/145.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 800/1000SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. U-Ditch uk. 800/1000 M134.a bhpanjang 120 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-195.a
ANALISA
![Page 146: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/146.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 800/1200SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. U-Ditch uk. 800/1200 M134.b bhpanjang 120 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-195.b
ANALISAHARGA SATUAN PEKERJAAN
![Page 147: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/147.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 1000/1000SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. U-Ditch uk. 1000/1000 M135 bhpanjang 120 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-196
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 148: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/148.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 1200/1200SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. U-Ditch uk. 1200/1200 M136 bhpanjang 120 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-197
ANALISA
![Page 149: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/149.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 1400/1400SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. U-Ditch uk. 1400/1400 M137 bhpanjang 120 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-198
ANALISAHARGA SATUAN PEKERJAAN
![Page 150: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/150.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 1600/1600SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. U-Ditch uk. 1600/1600 M139 bhpanjang 120 cm
2. Urugan Porus (EI-161) M3
-
C. PERALATAN
1. Tamper E25 Jam
2. Flat Bed Truck E11 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-199
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
![Page 151: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/151.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa dan Pembuangan (Alat), Kedalaman Max. 1 MSATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
C. PERALATAN
1. Excavator E10 Jam2. Dump Truck E08 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-211
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
![Page 152: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/152.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa Pembuangan (Manual) / PU, Kedalaman Max. 1 MSATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01.a) Jam2. Mandor (L03) Jam
-
B. BAHAN
C. PERALATAN
1. Pick Up E53 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-212
ANALISAHARGA SATUAN PEKERJAAN
![Page 153: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/153.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa Buang Ditempat (Manual), Kedalaman Max. 1 MSATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01.a) Jam2. Mandor (L03) Jam
-
B. BAHAN
C. PERALATAN
1. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
Analisa EI-213
ANALISAHARGA SATUAN PEKERJAAN
![Page 154: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/154.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa dan Pembuangan (Alat), Kedalaman Max. 2 MSATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
C. PERALATAN
1. Excavator E10 Jam2. Dump Truck E08 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
Analisa EI-214
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
![Page 155: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/155.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa Pembuangan (Manual) / PU, Kedalaman Max. 2 MSATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01.a) Jam2. Mandor (L03) Jam
-
B. BAHAN
C. PERALATAN
1. Pick Up E53 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
ANALISA
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
Analisa EI-215
![Page 156: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/156.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa Buang Ditempat (Manual), Kedalaman Max. 2 MSATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01.a) Jam2. Mandor (L03) Jam
-
B. BAHAN
-
C. PERALATAN
1. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-216
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
![Page 157: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/157.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa dan Pembuangan (Alat), Kedalaman Max. 3 MSATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
C. PERALATAN
1. Excavator E10 Jam2. Dump Truck E08 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
Analisa EI-217
ANALISAHARGA SATUAN PEKERJAAN
![Page 158: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/158.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa Pembuangan (Manual) / PU, Kedalaman Max. 3 MSATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01.a) Jam2. Mandor (L03) Jam
-
B. BAHAN
C. PERALATAN
1. Pick Up E53 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-218
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 159: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/159.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa Buang Ditempat (Manual), Kedalaman Max. 3 MSATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01.a) Jam2. Mandor (L03) Jam
-
B. BAHAN
C. PERALATAN
1. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-219
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
![Page 160: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/160.jpg)
JENIS PEKERJAAN : GALIAN BATU / TANAH KERAS ( ALAT )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
-
C. PERALATAN1. Compressor E05 Jam2. Jack Hammer E26 Jam3. Dump Truck E08 Jam4. Alat bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-221
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 161: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/161.jpg)
Analisa EI-222
JENIS PEKERJAAN : GALIAN BATU / TANAH KERAS ( MANUAL )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01.a) Jam2. Mandor (L03) Jam
-
B. BAHAN
C. PERALATAN
1. Pick Up E53 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
ANALISAHARGA SATUAN PEKERJAAN
![Page 162: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/162.jpg)
JENIS PEKERJAAN : GALIAN PERKERASAN BERASPAL ( MANUAL )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01.a) Jam2. Mandor (L03) Jam
-
B. BAHAN
C. PERALATAN
1. Truck Pick Up E53 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
Analisa EI-242
![Page 163: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/163.jpg)
JENIS PEKERJAAN : TIMBUNAN TANAH SETEMPATSATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01.a) Jam2. Mandor (L03) Jam
-
B. BAHAN
C. PERALATAN
1. Tamper E25 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-263
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 164: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/164.jpg)
JENIS PEKERJAAN : TIMBUNAN TANAH PILIHANSATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01.a) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Bahan pilihan M10 M3
-
C. PERALATAN
1. Tamper E25 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-264
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
![Page 165: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/165.jpg)
JENIS PEKERJAAN : TIMBUNAN BADAN JALAN TANAH PILIHAN ( ALAT )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Tanah pilihan M10 M3
-
C. PERALATAN1. Motor Grader E13 Jam2. Tandem Roller 6 - 8 T E17 Jam3. Water Tanker E23 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
Analisa EI-271
ANALISA
![Page 166: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/166.jpg)
JENIS PEKERJAAN : TIMBUNAN BADAN JALAN TANAH PILIHAN ( MANUAL)SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01.a) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Tanah pilihan M10 M3
-
C. PERALATAN
1. Tandem Roller 6 - 8 T E17 Jam2. Water Tanker E23 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-272
ANALISAHARGA SATUAN PEKERJAAN
![Page 167: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/167.jpg)
JENIS PEKERJAAN : PENYIAPAN BADAN JALAN ( MENGGUNAKAN ALAT )SATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Mandor (L03) jam
-
B. BAHAN
C. PERALATAN
1. Motor Grader E13 jam2. Three Wheel Roller 6 - 8 Ton E16 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
Analisa EI-281
ANALISAHARGA SATUAN PEKERJAAN
![Page 168: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/168.jpg)
JENIS PEKERJAAN : PENYIAPAN BADAN JALAN ( MANUAL )SATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01.a) jam2. Mandor (L03) jam
-
B. BAHAN
C. PERALATAN
1. Three Wheel Roller 6 - 8 Ton E16 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-282
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 169: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/169.jpg)
JENIS PEKERJAAN : LAPIS PONDASI AGREGAT Kls. A ( ALAT )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Agregat A M19 M3
-
C. PERALATAN
1 Motor Grader E13 Jam2 Tandem Roller 6 - 8 T E17 Jam3 Water Tanker E23 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
Analisa EI-311
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
![Page 170: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/170.jpg)
JENIS PEKERJAAN : LAPIS PONDASI AGREGAT Kls. A ( MANUAL )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) jam2. Mandor (L03) jam
-
B. BAHAN
1. Agregat A M19 M3
-
C. PERALATAN
1. Tandem Roller 6 - 8 T E17 jam2. Water Tanker E23 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISA
Analisa EI-312
![Page 171: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/171.jpg)
JENIS PEKERJAAN : LAPIS PONDASI AGREGAT Kls. B, CBR MIN 60 % ( ALAT )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Agregat B M20 M3
-
C. PERALATAN
1 Motor Grader E13 Jam2 Tandem Roller 6 - 8 T E17 Jam3 Water Tanker E23 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
Analisa EI-321
ANALISA
![Page 172: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/172.jpg)
JENIS PEKERJAAN : LAPIS PONDASI AGREGAT Kls. B, CBR MIN 60 % ( MANUAL )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) jam2. Mandor (L03) jam
-
B. BAHAN
1. Agregat Klass B M20 M3
-
C. PERALATAN
1. Tandem Roller 6 - 8 T E17 jam2. Water Tanker E23 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
Analisa EI-322
ANALISAHARGA SATUAN PEKERJAAN
![Page 173: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/173.jpg)
JENIS PEKERJAAN : LPS. POND. AGG. KLS. A ( ALAT )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Mandor (L03) jam
-
B. BAHAN
1. Aggrgat A M19 M3
-
C. PERALATAN1. Motor Grader E13 jam2. Tandem Roller E17 jam3. Water Tanker E23 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-411
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
![Page 174: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/174.jpg)
JENIS PEKERJAAN : LPS. POND. AGG. KLS. A ( MANUAL )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Mandor (L03) jam
-
B. BAHAN
1. Aggrgat A M19 M3
-
C. PERALATAN
1. Tandem Roller E17 jam2. Water Tanker E23 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
Analisa EI-412
ANALISA
![Page 175: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/175.jpg)
JENIS PEKERJAAN : LPS. POND. AGREGAT. KLS. B ( ALAT )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Mandor (L03) jam
-
B. BAHAN
1. Aggregat B M20 M3
-
C. PERALATAN1. Motor Grader E13 jam2. Tandem Roller E17 jam3. Water Tanker E23 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-421
ANALISAHARGA SATUAN PEKERJAAN
![Page 176: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/176.jpg)
JENIS PEKERJAAN : LPS. POND. AGREGAT. KLS. B ( MANUAL )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Mandor (L03) jam
-
B. BAHAN
1. Aggregat B M20 M3
-
C. PERALATAN
1. Tandem Roller E17 jam2. Water Tanker E23 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
Analisa EI-422
ANALISAHARGA SATUAN PEKERJAAN
![Page 177: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/177.jpg)
JENIS PEKERJAAN : LAPIS PONDASI BAWAH KONSTRUKSI TELFORD ( MANUAL )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN1. 0 M02 M3
0 M06 M3
0 M01d M3
-
C. PERALATAN1. Tandem Roller 6 - 8 Ton E17 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-44
ANALISAHARGA SATUAN PEKERJAAN
![Page 178: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/178.jpg)
JENIS PEKERJAAN : LAPIS PONDASI BAWAH KONSTRUKSI BATU KAPUR ( MANUAL )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN1. Batu kapur M11 M3
-
C. PERALATAN1. Tandem Roller 6 - 8 Ton E17 Jam2. Water Tanker E23 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
Analisa EI-45
ANALISAHARGA SATUAN PEKERJAAN
![Page 179: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/179.jpg)
JENIS PEKERJAAN : Lapis Pondasi Agregat Dengan Cement Treated Base (CTB) ManualSATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN1. Agregat Pecah Tersaring M19 M3
(Base Coarse A)2. Semen M26 Kg3 Alat Bantu Ls
-
C. PERALATAN1. Tandem Roller E17 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
Analisa EI-491
ANALISA
![Page 180: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/180.jpg)
JENIS PEKERJAAN : LAPIS RESAP PENGIKAT (PRIME COAT)SATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Aspal M49 Kg2. Kerosene M55 liter
-
C. PERALATAN
1. Asphalt Distributor E41 Jam2. Compressor E05 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
Analisa EI-511A
ANALISA
![Page 181: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/181.jpg)
JENIS PEKERJAAN : LAPIS PEREKAT (TACK COAT)SATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Aspal M49 Kg2. Kerosene M55 liter
-
C. PERALATAN
1. Asphalt Distributor E41 Jam2. Compressor E05 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
Analisa EI-512A
ANALISAHARGA SATUAN PEKERJAAN
![Page 182: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/182.jpg)
JENIS PEKERJAAN : SAND SHEETSATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Sand Sheet M54 Ton
-
C. PERALATAN1. Asphalt Finisher E02 Jam2. Tandem Roller E17 Jam3. P. Tyre Roller E18 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-531
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 183: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/183.jpg)
JENIS PEKERJAAN : LAPIS TIPIS ASPAL BETON ( LATASTON/HRS ) - ( ALAT )SATUAN PEMBAYARAN : Ton
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Lataston ( HRS ) M53 Ton
-
C. PERALATAN1. Asphalt Finisher E02 Jam2. Tandem Roller E17 Jam3. P. Tyre Roller E18 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-532
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
![Page 184: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/184.jpg)
JENIS PEKERJAAN : LAPIS ASPAL BETON ( LASTON /AC ) - ( ALAT )SATUAN PEMBAYARAN : Ton
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Laston ( AC ) M52 Ton
-
C. PERALATAN1. Asp. Finisher E02 Jam2. Tandem Roller E17 Jam3. P. Tyre Roller E18 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
Analisa EI-533
ANALISA
![Page 185: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/185.jpg)
JENIS PEKERJAAN : ASPHALT TREADE BASE ( ATB ) - ( ALAT )SATUAN PEMBAYARAN : Ton
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. ATB M51 Ton
-
C. PERALATAN1. Asphalt Finisher E02 Jam2. Tandem Roller E17 Jam3. P. Tyre Roller E18 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-534
ANALISAHARGA SATUAN PEKERJAAN
![Page 186: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/186.jpg)
JENIS PEKERJAAN : LAPIS PERMUKAAN PENETRASI MACADAM ( t = 7 cm )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. 0 M13 M32. Agregat Halus M14 M33. 0 M49 Kg
-
C. PERALATAN
1. 3-Wheel Roller E16 Jam2. Asp. Sprayer E03 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
Analisa EI-551
ANALISAHARGA SATUAN PEKERJAAN
![Page 187: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/187.jpg)
JENIS PEKERJAAN : LAPIS PONDASI PERATA PENETRASI MACADAMSATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. 0 M13 M32. 0 M23 M33. 0 M49 Kg
-
C. PERALATAN
1. 3-Wheel Roller E16 Jam2. Asp. Sprayer E03 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-552
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 188: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/188.jpg)
JENIS PEKERJAAN : SAND SHEET (UNTUK JALAN LINGKUNGAN)SATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Sand Sheet M54 Ton
-
C. PERALATAN
1. Tandem Roller E17 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
Analisa EI-541
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
![Page 189: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/189.jpg)
JENIS PEKERJAAN : LAPIS TIPIS ASPAL BETON ( LATASTON/HRS ) - ( ALAT )SATUAN PEMBAYARAN : Ton
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Lataston ( HRS ) M53 Ton
-
C. PERALATAN
1. Tandem Roller E17 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISA
Analisa EI-542
![Page 190: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/190.jpg)
JENIS PEKERJAAN : LAPIS ASPAL BETON ( LASTON /AC ) - ( MANUAL )SATUAN PEMBAYARAN : Ton
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Laston ( AC ) M52 Ton
-
C. PERALATAN
1. Tandem Roller E17 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
Analisa EI-543
ANALISA
![Page 191: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/191.jpg)
JENIS PEKERJAAN : ASPHALT TREADE BASE ( ATB ) - ( MANUAL )SATUAN PEMBAYARAN : Ton
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Asphalt Trade Base ( ATB ) M51 Ton
-
C. PERALATAN
1. Tandem Roller E17 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
Analisa EI-544
ANALISAHARGA SATUAN PEKERJAAN
![Page 192: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/192.jpg)
JENIS PEKERJAAN : BETON STRUKTUR READY MIX K-500SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Beton Ready Mix K-500 M47 M3
-
C. PERALATAN
1. Concrete Vibrator E20 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-611
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
![Page 193: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/193.jpg)
JENIS PEKERJAAN : BETON STRUKTUR READY MIX K-400SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Beton Ready Mix K-400 M46 M3
-
C. PERALATAN
1. Concrete Vibrator E20 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
Analisa EI-612
ANALISAHARGA SATUAN PEKERJAAN
![Page 194: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/194.jpg)
JENIS PEKERJAAN : BETON STRUKTUR READY MIX K-350SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Beton Ready Mix K-350 M45 M3
-
C. PERALATAN
1. Concrete Vibrator E20 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-613
ANALISAHARGA SATUAN PEKERJAAN
![Page 195: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/195.jpg)
JENIS PEKERJAAN : BETON STRUKTUR READY MIX K-300SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Beton Ready Mix K-300 M44 M3
-
C. PERALATAN
1. Concrete Vibrator E20 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
Analisa EI-614
ANALISAHARGA SATUAN PEKERJAAN
![Page 196: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/196.jpg)
JENIS PEKERJAAN : BETON STRUKTUR READY MIX K-225SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Beton Ready Mix K-225 M43 M3
-
C. PERALATAN
1. Concrete Vibrator E20 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-615
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 197: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/197.jpg)
JENIS PEKERJAAN : BETON STRUKTUR K-225 ( SITE MIX )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Semen M25 Zak2. Pasir beton M01b M3
3. Agregat Kasar M13 M3
-
C. PERALATAN
1. Conc. Mixer E06 jam2. Water Tanker E23 jam3. Concrete Vibrator E20 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-616 BS
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
![Page 198: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/198.jpg)
JENIS PEKERJAAN : BETON STRUKTUR SITE MIX K-175SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Semen M25 Zak2. Pasir beton M01b M33. Agregat Kasar M13 M3
-
C. PERALATAN
1. Conc. Mixer E06 jam2. Water Tanker E23 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
Analisa EI-617
ANALISA
![Page 199: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/199.jpg)
JENIS PEKERJAAN : BETON SIKLOP STRUKTUR SITE MIX K-175SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Semen M25 Zak2. Pasir beton M01b M33. Agregat Kasar M13 M34. Batu Belah M06 M3
-
C. PERALATAN
1. Conc. Mixer E47 jam2. Water Tanker E23 jam3. Con. Vibrator E20 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-618
ANALISAHARGA SATUAN PEKERJAAN
![Page 200: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/200.jpg)
JENIS PEKERJAAN : BETON STRUKTUR SITE MIX K-125SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Semen M25 Zak2. Pasir beton M01b M33. Agregat Kasar M13 M3
-
C. PERALATAN
1. Conc. Mixer E06 jam2. Water Tanker E23 jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
Analisa EI-619
ANALISAHARGA SATUAN PEKERJAAN
![Page 201: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/201.jpg)
JENIS PEKERJAAN : PEMBESIAN BAJA TULANGANSATUAN PEMBAYARAN : Kg
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. 0 M31a Kg2. Kawat Beton M28 Kg
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-621
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 202: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/202.jpg)
JENIS PEKERJAAN : BEKISTING UNTUK BETON STRUKTUR (JEMBATAN)SATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Kayu Acuan M40 M3
2. Multipleks 120 x 240 x 0.90 cm M39.b Lbr3 Paku Jembatan M30 Kg
-
C. PERALATAN
1. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
Analisa EI-67
ANALISA
![Page 203: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/203.jpg)
JENIS PEKERJAAN : BEKISTING UNTUK BETON STRUKTUR SALURANSATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Kayu Acuan M40 M3
2. Tripleks M39.c Lbr3 Paku M30 Kg
-
C. PERALATAN
1. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-671
ANALISAHARGA SATUAN PEKERJAAN
![Page 204: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/204.jpg)
JENIS PEKERJAAN : PONDASI CERUCUK, PENYEDIAAN DAN PEMANCANGANSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Dolken Ø 8-10 cm ; P = 4 m M38.a btg
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-661
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
![Page 205: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/205.jpg)
JENIS PEKERJAAN : DINDING TURAP BAJASATUAN PEMBAYARAN : Kg
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Baja Struktur M34 Kg2. Kawat Las M32 Dos
-
C. PERALATAN
1. Crane E07 jam2. Welding Set E32 jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
Analisa EI-665
ANALISA
![Page 206: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/206.jpg)
JENIS PEKERJAAN : BRONJONGSATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Kawat Bronjong Pabrikasi M121 Kg2. Batu M02 M3
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
Analisa EI-6102
ANALISA
![Page 207: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/207.jpg)
JENIS PEKERJAAN : BRONJONG (DENGAN ANGKUTAN)SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Kawat Bronjong Pabrikasi M121 Kg2. Batu M02 M3
-
C. PERALATAN
1. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-6103
ANALISAHARGA SATUAN PEKERJAAN
![Page 208: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/208.jpg)
JENIS PEKERJAAN : PEMBONGKARAN BETON ( MANUAL )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
C. PERALATAN
1. Dump Truck E08 Jam2. Alat bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-616 PB
ANALISAHARGA SATUAN PEKERJAAN
![Page 209: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/209.jpg)
JENIS PEKERJAAN : BORE PILE BETON, Dia. 300 mmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Beton K-225 M43 M3
2. Baja Tulangan M31a Kg3. Casing M113 M2
-
C. PERALATAN
1. Mini Bore Pile Machine E55 jam2. Concr. Pump E28 jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-6618
ANALISAHARGA SATUAN PEKERJAAN
![Page 210: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/210.jpg)
JENIS PEKERJAAN : BORE PILE BETON, Dia. 400 mmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Beton K-225 M43 M3
2. Baja Tulangan M31a Kg3. Casing M113 M2
-
C. PERALATAN
1. Mini Bore Pile Machine E55 jam2. Concr. Pump E28 jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
Analisa EI-6619
ANALISAHARGA SATUAN PEKERJAAN
![Page 211: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/211.jpg)
JENIS PEKERJAAN : BORE PILE BETON, Dia. 500 mmSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Beton K-225 M43 M3
2. Baja Tulangan M31a Kg3. Casing M113 M2
-
C. PERALATAN
1. Mini Bore Pile Machine E55 jam2. Concr. Pump E28 jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-6620
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 212: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/212.jpg)
JENIS PEKERJAAN : PEMANCANGAN SHEET PILESATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam4. Operator (L04) Jam5. Pembantu Operator (L05) Jam
-
B. BAHAN
C. PERALATAN
1. Crane 10-15 ton E07 Jam2. Pile Driver + Hammer E30.a Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-63
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
![Page 213: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/213.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-325-A-1000 P : 8-13, K-700SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Sheet Pile W-325-A-1000, M140.a m'P : 8-13, K-700
-
C. PERALATAN
1. Flat Bed Truck E11 Jam2. Crane 10-15 ton E07 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
Analisa EI-641.a
ANALISA
![Page 214: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/214.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-325-B-1000 P : 8-14, K-700SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Sheet Pile W-325-B-1000, M140.b m'P : 8-14, K-700
-
C. PERALATAN
1. Flat Bed Truck E11 Jam2. Crane 10-15 ton E07 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-641.b
ANALISAHARGA SATUAN PEKERJAAN
![Page 215: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/215.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-350-A-1000 P : 9-15, K-700SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Sheet Pile W-350-A-1000, M141.a m'P : 9-15, K-700
-
C. PERALATAN
1. Flat Bed Truck E11 Jam2. Crane 10-15 ton E07 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
Analisa EI-641.c
ANALISAHARGA SATUAN PEKERJAAN
![Page 216: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/216.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-350-B-1000 P : 10-15, K-700SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Sheet Pile W-350-B-1000, M141.b m'P : 10-15, K-700
-
C. PERALATAN
1. Flat Bed Truck E11 Jam2. Crane 10-15 ton E07 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-641.d
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 217: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/217.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-400-A-1000 P : 10-16, K-700SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Sheet Pile W-400-A-1000, M142.a m'P : 10-16, K-700
-
C. PERALATAN
1. Flat Bed Truck E11 Jam2. Crane 10-15 ton E07 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-641.e
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
![Page 218: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/218.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-400-B-1000 P : 11-16, K-700SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Sheet Pile W-400-B-1000, M142.b m'P : 11-16, K-700
-
C. PERALATAN
1. Flat Bed Truck E11 Jam2. Crane 10-15 ton E07 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
Analisa EI-641.f
ANALISA
![Page 219: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/219.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-450-A-1000 P : 11-17, K-700SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Sheet Pile W-450-A-1000 M143.a m'P : 11-17, K-700
-
C. PERALATAN
1. Flat Bed Truck E11 Jam2. Crane 10-15 ton E07 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-641.g
ANALISAHARGA SATUAN PEKERJAAN
![Page 220: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/220.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-450-B-1000 P : 12-17, K-700SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Sheet Pile W-450-B-1000 M143.b m'P : 12-17, K-700
-
C. PERALATAN
1. Flat Bed Truck E11 Jam2. Crane 10-15 ton E07 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
Analisa EI-641.h
ANALISAHARGA SATUAN PEKERJAAN
![Page 221: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/221.jpg)
JENIS PEKERJAAN : PENYEDIAAN FLAT SHEET PILE, K-700SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Flat Sheet Pile, K-700 M143.c m'
-
C. PERALATAN
1. Flat Bed Truck E11 Jam2. Crane 10-15 ton E07 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-642
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 222: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/222.jpg)
JENIS PEKERJAAN : PEMANCANGAN TIANG PANCANGSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam4. Operator (L04) Jam5. Pembantu Operator (L05) Jam
-
B. BAHAN
C. PERALATAN
1. Crane 10-15 ton E07 Jam2. Pile Driver + Hammer E30.a Jam3. Welding Set E32 Jam4. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
KOMPONEN HARGA
Analisa EI-65
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 223: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/223.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-300 - 6 s/d 8, Segmen BottomSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Tiang Pancang Type A2 - 300 - M144.a m'6 s/d 8, Segmen Bottom
-
C. PERALATAN
1. Flat Bed Truck E11 Jam2. Crane 10-15 ton E07 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
(Rp.)
Analisa EI-651.a
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
![Page 224: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/224.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-300 - 6 s/d 8, Segmen Bottom PencilSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Tiang Pancang Type A2 - 300 - M144.b m'6 s/d 8, Segmen Bottom Pencil
-
C. PERALATAN
1. Flat Bed Truck E11 Jam2. Crane 10-15 ton E07 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAH HARGA TENAGA
Analisa EI-651.b
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
![Page 225: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/225.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-300 - 6 s/d 8, Segmen MiddleSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Tiang Pancang Type A2 - 300 - M144.c m'6 s/d 8, Segmen Middle
-
C. PERALATAN
1. Flat Bed Truck E11 Jam2. Crane 10-15 ton E07 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAH HARGA BAHAN
Analisa EI-651.c
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
![Page 226: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/226.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-400 - 6 s/d 8, Segmen BottomSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Tiang Pancang Type A2 - 400 - M145.a m'6 s/d 8, Segmen Bottom
-
C. PERALATAN
1. Flat Bed Truck E11 Jam2. Crane 10-15 ton E07 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
Analisa EI-651.d
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
![Page 227: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/227.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-400 - 6 s/d 8, Segmen Bottom PencilSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Tiang Pancang Type A2 - 400 - M145.b m'6 s/d 8, Segmen Bottom Pencil
-
C. PERALATAN
1. Flat Bed Truck E11 Jam2. Crane 10-15 ton E07 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
Analisa EI-651.e
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
![Page 228: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/228.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-400 - 6 s/d 8, Segmen MiddleSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Tiang Pancang Type A2 - 400 - M145.c m'6 s/d 8, Segmen Middle
-
C. PERALATAN
1. Flat Bed Truck E11 Jam2. Crane 10-15 ton E07 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
ANALISA
Analisa EI-651.f
![Page 229: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/229.jpg)
JENIS PEKERJAAN : PASANG ELASTOMERIK; BEARING PAD 35 X 40 X 3,9SATUAN PEMBAYARAN : BUAH
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Bearing Pad Elastomer M162 BuahUk. 350 x 400 x 39
2. Non Shrinkage Mortar M159 Kg2. Baja Anyaman M156 Kg2. Epoxy Adhesive M161 Liter
-
C. PERALATAN
1. Alat Bantu E07 Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
KOMPONEN HARGA
Analisa EI-681
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 230: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/230.jpg)
JENIS PEKERJAAN : PASANG PIPA AIR 3" (DECK DRAIN)SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Pipa PVC D. 3" M60.a m'2. Mur Baut M154 Kg3. Besi Plat Strip M155 Kg4. Section Steel M157 Kg5. Fitting & Support / Reducer M158 Buah
-
C. PERALATAN
1. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
(Rp.)
Analisa EI-682
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
![Page 231: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/231.jpg)
JENIS PEKERJAAN : EXPANSION JOINTSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Expansion Joint Type Asphaltic Plug M163 m'
-
C. PERALATAN
1. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAH HARGA TENAGA
Analisa EI-683
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
![Page 232: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/232.jpg)
JENIS PEKERJAAN : MARKA TERMOPLASTIK (ALAT)SATUAN PEMBAYARAN : M2
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Cat Thermoplastic Marka Jalan M99 Kg2. Cat Marka, Glass Beads (Drop On) M103 Kg3. Epoxy Premarking M160 Liter
-
C. PERALATAN
1. Compressor 4000-6500 L/M E05 Jam2. Line Marker Truck E57 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAH HARGA BAHAN
Analisa EI-684
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
![Page 233: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/233.jpg)
JENIS PEKERJAAN : LAUNCHING PCI GIRDERSATUAN PEMBAYARAN : BUAH
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam4. Operator (L04) Jam
-
B. BAHAN
-
C. PERALATAN
1. Crane 10-15 ton E07 Jam2. Crane 120 Ton E56 Jam3. Alat Bantu E58 Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
Analisa EI-6851
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
![Page 234: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/234.jpg)
JENIS PEKERJAAN : LAUNCHING PCI GIRDERSATUAN PEMBAYARAN : BUAH
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam4. Tukang Besi / Las (L02) Jam
-
B. BAHAN
1. Kawat Las M32 Kg
-
C. PERALATAN
1. Launching Girder E62 Jam2. Crane 10-15 ton E07 Jam3. Flat Bed Truck w/ Crane 4 Ton E58 Jam4. Single Cage Elevator (Hoist) E61 Jam5. Traveller Beam Set E59 Jam6. Generator Set E12 Jam7. Crane 120 Ton E56 Jam8. Welding Set E32 Jam9. Hydraulic Jack 150 Ton E60 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
Analisa EI-6852
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
![Page 235: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/235.jpg)
JENIS PEKERJAAN : BALOK I GIRDER K-600; L = 20,6 MSATUAN PEMBAYARAN : BUAH
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
B. BAHAN
1. Girder Type I, 20,6 m M164 BuahH = 70 cm
-
C. PERALATAN
1. Launching PCI Girder EI-6851 Buah
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISA
Analisa EI-6861.a
![Page 236: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/236.jpg)
JENIS PEKERJAAN : BALOK I GIRDER K-800; L = 45,7 MSATUAN PEMBAYARAN : BUAH
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
B. BAHAN
1. Girder Type I, 45,7 m M165 BuahH = 240 cm
-
C. PERALATAN
1. Launching PCI Girder EI-6852 Buah
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
HARGA SATUAN PEKERJAAN
Analisa EI-6862.a
ANALISA
![Page 237: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/237.jpg)
JENIS PEKERJAAN : PERKERASAN JALAN BETON K-350 SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Beton Ready Mix K-350 M45 M3
2. 0 M114 Bh3. 0 Ltr
-
C. PERALATAN
1 Con. Vibrator E20 jam2 Con. Cutter E54 jam3 Alat Bantu Ls
- D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) - G. HARGA SATUAN PEKERJAAN / M3 -
Analisa EI-711
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
![Page 238: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/238.jpg)
JENIS PEKERJAAN : PERKERASAN JALAN BETON K-350 ( DENGAN ANGKUTAN )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Beton Ready Mix K-350 M45 M3
2. Karung Bh3. Curing Ltr
-
C. PERALATAN
1. Con. Vibrator E20 jam2. Con. Cutter E54 jam3. Truck Pick Up E53 jam4. Alat Bantu Ls
- D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) - G. HARGA SATUAN PEKERJAAN / M3 -
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
ANALISA
Analisa EI-712
![Page 239: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/239.jpg)
JENIS PEKERJAAN : PERKERASAN JALAN BETON READY MIX K-225 SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Beton Ready Mix K-225 M43 M3
2. Karung Bh3. Curing Ltr
-
C. PERALATAN
1 Con. Vibrator E20 jam2 Con. Cutter E54 jam3 Alat Bantu Ls
- D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) - G. HARGA SATUAN PEKERJAAN / M3 -
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
Analisa EI-713
ANALISA
![Page 240: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/240.jpg)
JENIS PEKERJAAN : PERKERASAN JALAN BETON READY MIX K-225 ( DENGAN ANGKUTAN )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Beton Ready Mix K-225 M43 M3
2. Karung Bh3. Curing Ltr
-
C. PERALATAN
1 Con. Vibrator E20 jam2 Con. Cutter E54 jam3. Truck Pick Up E53 jam4. Alat Bantu Ls
- D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) - G. HARGA SATUAN PEKERJAAN / M3 -
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-714
ANALISAHARGA SATUAN PEKERJAAN
![Page 241: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/241.jpg)
JENIS PEKERJAAN : PERKERASAN JALAN BETON K-225 ( SITE MIX )SATUAN PEMBAYARAN : M³
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA1. Pekerja (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Semen M25 Zak2. Pasir beton M01b M3
3. Agregat Kasar M13 M3
4. Karung Bh5. Curing Ltr
-
C. PERALATAN
1. Conc. Mixer E47 jam2. Water Tanker E23 jam3. Con. Vibrator E20 jam4. Con. Cutter E54 jam5 Alat Bantu Ls
- D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) - G. HARGA SATUAN PEKERJAAN / M3 -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAH
Analisa EI-715
ANALISAHARGA SATUAN PEKERJAAN
![Page 242: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/242.jpg)
JENIS PEKERJAAN : ACUAN PERKERASAN BETONSATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Kayu Acuan M40 M3
2. Multipleks 9 mm M39.b Lbr3. Paku M30 Kg
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA
Analisa EI-72
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 243: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/243.jpg)
JENIS PEKERJAAN : PASANGAN PLASTIC SHEETSATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Plastik Sheet M115 M2
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAH HARGA TENAGA
Analisa EI-73
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
![Page 244: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/244.jpg)
JENIS PEKERJAAN : JOINT SEALENTSATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
1. Sealent M91 Kg
-
C. PERALATAN
1. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
Analisa EI-74
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHHARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
![Page 245: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/245.jpg)
JENIS PEKERJAAN : PEMOTONGAN POHON KERASSATUAN PEMBAYARAN : Buah
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01.a) Jam2. Mandor (L03) Jam
-
B. BAHAN
C. PERALATAN
1. Truck Pick Up E53 Jam2. Chainsaw Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
Analisa EI-823.a
ANALISAHARGA SATUAN PEKERJAAN
![Page 246: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/246.jpg)
JENIS PEKERJAAN : PEMOTONGAN POHON LUNAKSATUAN PEMBAYARAN : Buah
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
C. PERALATAN
1. Parang Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-823.b
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 247: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/247.jpg)
JENIS PEKERJAAN : PENGUPASAN DAN PEMBERSIHAN SEMAKSATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
C. PERALATAN
1 Mesin Potong Rumput Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-824
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
![Page 248: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/248.jpg)
JENIS PEKERJAAN : PENGUPASAN DAN PEMBERSIHAN GULMANSATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Mandor (L03) Jam
-
B. BAHAN
C. PERALATAN
1 Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
Analisa EI-824.b
ANALISA
![Page 249: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/249.jpg)
JENIS PEKERJAAN : STABILISASI DENGAN TANAMANSATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) jam2. Tukang (L02) jam3. Mandor (L03) jam
-
B. BAHAN
1. Gebalan Rumput M107 M2
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-831
ANALISAHARGA SATUAN PEKERJAAN
![Page 250: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/250.jpg)
JENIS PEKERJAAN : MARKA JALAN TERMOPLASTIK (MANUAL)SATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Cat Marka M99 Kg2. Thinner M102 Liter3. Glass Beads M103 Kg
-
C. PERALATAN
1. Compressor E05 Jam2. Dump Truck E08 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-841
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
![Page 251: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/251.jpg)
JENIS PEKERJAAN : MARKA JALAN BUKAN TERMOPLASTIK (MANUAL)SATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Cat Marka M98 Kg2. Thinner M102 Liter3. Glass Beads M103 Kg
-
C. PERALATAN
1. Compressor E05 Jam2. Dump Truck E08 Jam3. Alat Bantu Ls
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
Analisa EI-842
ANALISAHARGA SATUAN PEKERJAAN
![Page 252: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/252.jpg)
JENIS PEKERJAAN : PASANGAN KANSTEEN 15.25.40SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Kansteen uk. 15 x 25 x 40 M109.a Bh2. Semen M25 Zak3. Pasir Urug M01a M3
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-8410.a
ANALISAHARGA SATUAN PEKERJAAN
![Page 253: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/253.jpg)
JENIS PEKERJAAN : PASANGAN KANSTEEN 13.20.40SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Kansteen uk. 13 x 20 x 40 M109.b Bh2. Semen M25 Zak3. Pasir Urug M01a M3
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
Analisa EI-8410.b
ANALISAHARGA SATUAN PEKERJAAN
![Page 254: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/254.jpg)
JENIS PEKERJAAN : PASANGAN KANSTEEN 15.28.40SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Kansteen uk. 15 x 28 x 40 M109.c Bh2. Semen M25 Zak3. Pasir Urug M01a M3
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-8410.c
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 255: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/255.jpg)
JENIS PEKERJAAN : PASANGAN KANSTEEN 20.25.60SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Kansteen uk. 20 x 25 x 60 M109.d Bh2. Semen M25 Zak3. Pasir Urug M01a M3
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-8410.d
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
![Page 256: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/256.jpg)
JENIS PEKERJAAN : PASANGAN KANSTEEN 30.25.60SATUAN PEMBAYARAN : M'
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Kansteen uk. 30 x 25 x 60 M109.e Bh2. Semen M25 Zak3. Pasir Urug M01a M3
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
HARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
(Rp.)
Analisa EI-8410.e
ANALISA
![Page 257: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/257.jpg)
JENIS PEKERJAAN : PERKERASAN PAVING BLOK (PEDESTRIAN)SATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Paving Blok M110 M2
2. Pasir Beton M01b M3
-
C. PERALATAN
1. Tamper E25 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
Analisa EI-8412.1
ANALISAHARGA SATUAN PEKERJAAN
![Page 258: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/258.jpg)
JENIS PEKERJAAN : PERKERASAN PAVING BLOK, t = 8 cm (JALAN)SATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Paving Blok M110.b M2
2. Pasir Beton M01b M3
-
C. PERALATAN
1. Tamper E25 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
JUMLAH HARGA PERALATAN
JUMLAHKOMPONEN HARGA
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
Analisa EI-8412.2a
ANALISAHARGA SATUAN PEKERJAAN
![Page 259: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/259.jpg)
JENIS PEKERJAAN : PERKERASAN PAVING BLOK, t = 6 cm (JALAN)SATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Paving Blok M110.c M2
2. Pasir Beton M01b M3
-
C. PERALATAN
1. Tamper E25 Jam
-
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
KOMPONEN HARGA(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-8412.2b
ANALISAHARGA SATUAN PEKERJAAN
JUMLAH
![Page 260: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/260.jpg)
JENIS PEKERJAAN : BONGKAR DAN PEMASANGAN KEMBALI PAVING BLOKSATUAN PEMBAYARAN : M²
PERKIRAAN HARGANO. SATUAN KUANTITAS SATUAN
(Rp.)
A. TENAGA
1. Pekerja Biasa (L01) Jam2. Tukang (L02) Jam3. Mandor (L03) Jam
-
B. BAHAN
1. Pasir Beton M01b M3
-
C. PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) - E. OVERHEAD & PROFIT 10 % x D - F. HARGA SATUAN PEKERJAAN ( D + E ) -
(Rp.)
JUMLAH HARGA TENAGA
JUMLAH HARGA BAHAN
JUMLAH HARGA PERALATAN
Analisa EI-8413
ANALISAHARGA SATUAN PEKERJAAN
JUMLAHKOMPONEN HARGA
![Page 261: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/261.jpg)
JENIS PEKERJAAN : GALIAN LUMPUR DAN PEMBUANGAN ( ALAT )SATUAN PEMBAYARAN : M³ METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 262: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/262.jpg)
JENIS PEKERJAAN : GALIAN LUMPUR DAN PEMBUANGAN ( ALAT )SATUAN PEMBAYARAN : M³ METODE KERJA
Lanjutan
No. KODE KOEF. SATUAN
Lihat lampiran.
5. ANALISA HARGA SATUAN PEKERJAANLihat perhitungan dalam ANALISAHARGA SATUAN PEKERJAAN
Didapat Harga Satuan Pekerjaan :
Rp. 0 / M3
6. WAKTU PELAKSANAAN YANG DIPERLUKANMasa Pelaksanaan : . . . . . . . . . . . . bulan
7. VOLUME PEKERJAAN YANG DIPERLUKANVolume pekerjaan : M3
U R A I A N
![Page 263: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/263.jpg)
JENIS PEKERJAAN : GALIAN LUMPUR BUANG DITEMPAT ( ALAT )SATUAN PEMBAYARAN : M³ METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
U R A I A N
![Page 264: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/264.jpg)
JENIS PEKERJAAN : GALIAN LUMPUR DAN PEMBUANGAN ( MANUAL )SATUAN PEMBAYARAN : M³ METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
U R A I A N
![Page 265: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/265.jpg)
JENIS PEKERJAAN : GALIAN LUMPUR BUANG DITEMPAT ( MANUAL)SATUAN PEMBAYARAN : M³ METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
U R A I A N
![Page 266: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/266.jpg)
JENIS PEKERJAAN : PASANGAN BATU KALI UNTUK SALURAN (ALAT)SATUAN PEMBAYARAN : M³ METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 267: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/267.jpg)
JENIS PEKERJAAN : PASANGAN BATU KALI UNTUK SALURAN (ALAT)SATUAN PEMBAYARAN : M³ METODE KERJA
Lanjutan
No. KODE KOEF. SATUAN
Lihat lampiran.
5. ANALISA HARGA SATUAN PEKERJAANLihat perhitungan dalam ANALISAHARGA SATUAN PEKERJAAN
Didapat Harga Satuan Pekerjaan :
Rp. 0 / M3
6. WAKTU PELAKSANAAN YANG DIPERLUKANMasa Pelaksanaan : . . . . . . . . . . . . bulan
7. VOLUME PEKERJAAN YANG DIPERLUKANVolume pekerjaan : M3
U R A I A N
![Page 268: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/268.jpg)
JENIS PEKERJAAN : PASANGAN BATU KALI UNTUK SALURAN (BURUH)SATUAN PEMBAYARAN : M³ METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 269: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/269.jpg)
JENIS PEKERJAAN : PASANGAN BATU KALI UNTUK SALURAN (BURUH)SATUAN PEMBAYARAN : M³ METODE KERJA
Lanjutan
No. KODE KOEF. SATUAN
5. ANALISA HARGA SATUAN PEKERJAANLihat perhitungan dalam ANALISAHARGA SATUAN PEKERJAAN
Didapat Harga Satuan Pekerjaan :
Rp. 0 / M3
6. WAKTU PELAKSANAAN YANG DIPERLUKANMasa Pelaksanaan : . . . . . . . . . . . . bulan
7. VOLUME PEKERJAAN YANG DIPERLUKANVolume pekerjaan : M3
U R A I A N
![Page 270: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/270.jpg)
JENIS PEKERJAAN : PASANGAN BATU KOSONGSATUAN PEMBAYARAN : M³ METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Rp. 0 / M3
U R A I A N
![Page 271: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/271.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton, Ø 30 cm ; P = 100 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 272: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/272.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton, Ø 30 cm ; P = 100 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 273: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/273.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton, Ø 40 cm ; P = 100 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 274: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/274.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton, Ø 40 cm ; P = 100 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 275: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/275.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton, Ø 50 cm ; P = 100 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 276: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/276.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton, Ø 50 cm ; P = 100 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 277: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/277.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton, Ø 60 cm ; P = 100 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 278: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/278.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton, Ø 60 cm ; P = 100 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 279: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/279.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton (1/2), Ø U 30 cm ; P = 100 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 280: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/280.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton (1/2), Ø U 30 cm ; P = 100 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 281: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/281.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton (1/2), Ø U 40 cm ; P = 100 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 282: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/282.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton (1/2), Ø U 40 cm ; P = 100 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 283: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/283.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton (1/2), Ø U 50 cm ; P = 100 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 284: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/284.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton (1/2), Ø U 50 cm ; P = 100 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 285: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/285.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton (1/2), Ø U 60 cm ; P = 100 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 286: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/286.jpg)
JENIS PEKERJAAN : Gorong² Buis Beton (1/2), Ø U 60 cm ; P = 100 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 287: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/287.jpg)
JENIS PEKERJAAN : Gorong² Precast Pipa Beton Tak Bertulang, Ø 30 cm ; P = 125 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 288: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/288.jpg)
JENIS PEKERJAAN : Gorong² Precast Pipa Beton Tak Bertulang, Ø 30 cm ; P = 125 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 289: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/289.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 40 cm ; P = 125 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 290: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/290.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 40 cm ; P = 125 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 291: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/291.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 50 cm ; P = 125 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 292: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/292.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 50 cm ; P = 125 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 293: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/293.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 60 cm, Panj. 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 294: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/294.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 60 cm, Panj. 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 295: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/295.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 80 cm, Panj. 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 296: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/296.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 80 cm, Panj. 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 297: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/297.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 90 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 298: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/298.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 90 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 299: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/299.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 100 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 300: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/300.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON TAK BERTULANG Ø 100 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 301: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/301.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 30 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 302: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/302.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 30 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 303: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/303.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 40 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 304: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/304.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 40 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 305: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/305.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 50 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 306: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/306.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 50 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 307: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/307.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 60 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 308: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/308.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 60 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 309: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/309.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 70 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 310: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/310.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 70 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 311: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/311.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 80 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 312: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/312.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 80 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 313: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/313.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 90 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 314: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/314.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 90 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 315: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/315.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 100 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 316: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/316.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 100 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 317: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/317.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 120 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 318: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/318.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 120 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 319: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/319.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 150 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 320: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/320.jpg)
JENIS PEKERJAAN : GORONG2 PRECAST PIPA BETON BERTULANG Ø 150 cm, P = 250 cmSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 321: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/321.jpg)
JENIS PEKERJAAN : GORONG-GORONG PIPA BAJA BERGELOMBANGSATUAN PEMBAYARAN : Ton METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 322: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/322.jpg)
JENIS PEKERJAAN GORONG-GORONG PIPA BAJA BERGELOMBANGSATUAN PEMBAYARAN Ton METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 323: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/323.jpg)
JENIS PEKERJAAN : Timbunan Porous atau Bahan Penyaring (Filter)SATUAN PEMBAYARAN : M³ METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
U R A I A N
![Page 324: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/324.jpg)
JENIS PEKERJAAN : Timbunan PasirSATUAN PEMBAYARAN : M³ METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
U R A I A N
![Page 325: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/325.jpg)
JENIS PEKERJAAN : KisdamSATUAN PEMBAYARAN : M' METODE KERJA
No. U R A I A N KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
![Page 326: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/326.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 400 x 400 HDSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 327: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/327.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 400 x 400 HDSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 328: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/328.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 500 x 500 HDSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 329: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/329.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 500 x 500 HDSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 330: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/330.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 600 x 600 HDSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
M
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 331: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/331.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 600 x 600 HDSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 332: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/332.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 800 x 800 HDSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 333: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/333.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 800 x 800 HDSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 334: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/334.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 1000 x 1000 HDSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 335: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/335.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 1000 x 1000 HDSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 336: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/336.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 1200 x 1200 HDSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 337: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/337.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 1200 x 1200 HDSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 338: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/338.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 1400 x 1400 HDSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 339: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/339.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 1400 x 1400 HDSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 340: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/340.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 1500 x 1500 HDSATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 341: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/341.jpg)
JENIS PEKERJAAN : BOX CULVERT BC 1500 x 1500 HDSATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 342: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/342.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 300/300SATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 343: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/343.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 300/300SATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 344: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/344.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 400/400SATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 345: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/345.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 400/400SATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 346: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/346.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 500/500SATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 347: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/347.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 500/500SATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 348: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/348.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 600/600SATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 349: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/349.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 600/600SATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 350: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/350.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 800/800SATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 351: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/351.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 800/800SATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 352: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/352.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 800/1000SATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 353: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/353.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 800/1000SATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 354: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/354.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 800/1200SATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 355: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/355.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 800/1200SATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 356: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/356.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 1000/1000SATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 357: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/357.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 1000/1000SATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 358: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/358.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 1200/1200SATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 359: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/359.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 1200/1200SATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 360: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/360.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 1400/1400SATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 361: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/361.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 1400/1400SATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 362: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/362.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 1600/1600SATUAN PEMBAYARAN : M' METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
![Page 363: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/363.jpg)
JENIS PEKERJAAN : U-DITCH TIPE U 1600/1600SATUAN PEMBAYARAN : M' METODE KERJA
Lanjutan
No. KODE KOEF. SATUANU R A I A N
![Page 364: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/364.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa dan Pembuangan (Alat), Kedalaman Max. 1 MSATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 365: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/365.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa dan Pembuangan (Alat), Kedalaman Max. 1 MSATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 366: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/366.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa Pembuangan (Manual) / PU, Kedalaman Max. 1 MSATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 367: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/367.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa Pembuangan (Manual) / PU, Kedalaman Max. 1 MSATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 368: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/368.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa Buang Ditempat (Manual), Kedalaman Max. 1 MSATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
U R A I A N
METODE KERJA
![Page 369: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/369.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa dan Pembuangan (Alat), Kedalaman Max. 2 MSATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 370: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/370.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa dan Pembuangan (Alat), Kedalaman Max. 2 MSATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 371: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/371.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa Pembuangan (Manual) / PU, Kedalaman Max. 2 MSATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
U R A I A N
METODE KERJA
![Page 372: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/372.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa Pembuangan (Manual) / PU, Kedalaman Max. 2 MSATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 373: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/373.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa Buang Ditempat (Manual), Kedalaman Max. 2 MSATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 374: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/374.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa dan Pembuangan (Alat), Kedalaman Max. 3 MSATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 375: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/375.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa dan Pembuangan (Alat), Kedalaman Max. 3 MSATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 376: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/376.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa Pembuangan (Manual) / PU, Kedalaman Max. 3 MSATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 377: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/377.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa Pembuangan (Manual) / PU, Kedalaman Max. 3 MSATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 378: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/378.jpg)
JENIS PEKERJAAN : Galian Tanah Biasa Buang Ditempat (Manual), Kedalaman Max. 3 MSATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 379: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/379.jpg)
JENIS PEKERJAAN : GALIAN BATU / TANAH KERAS ( ALAT )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
U R A I A N
METODE KERJA
![Page 380: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/380.jpg)
![Page 381: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/381.jpg)
JENIS PEKERJAAN : GALIAN BATU / TANAH KERAS ( MANUAL )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 382: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/382.jpg)
JENIS PEKERJAAN : GALIAN PERKERASAN BERASPAL ( MANUAL )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 383: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/383.jpg)
JENIS PEKERJAAN : TIMBUNAN TANAH SETEMPATSATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 384: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/384.jpg)
JENIS PEKERJAAN : TIMBUNAN TANAH PILIHANSATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 385: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/385.jpg)
JENIS PEKERJAAN : TIMBUNAN BADAN JALAN TANAH PILIHAN ( ALAT )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 386: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/386.jpg)
JENIS PEKERJAAN : TIMBUNAN BADAN JALAN TANAH PILIHAN ( ALAT )SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 387: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/387.jpg)
JENIS PEKERJAAN : TIMBUNAN BADAN JALAN TANAH PILIHAN ( MANUAL)SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 388: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/388.jpg)
JENIS PEKERJAAN : PENYIAPAN BADAN JALAN ( MENGGUNAKAN ALAT )SATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 389: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/389.jpg)
JENIS PEKERJAAN : PENYIAPAN BADAN JALAN ( MENGGUNAKAN ALAT )SATUAN PEMBAYARAN : M²
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 390: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/390.jpg)
JENIS PEKERJAAN : PENYIAPAN BADAN JALAN ( MANUAL )SATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 391: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/391.jpg)
JENIS PEKERJAAN : LAPIS PONDASI AGREGAT Kls. A ( ALAT )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 392: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/392.jpg)
JENIS PEKERJAAN : LAPIS PONDASI AGREGAT Kls. A ( ALAT )SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUANU R A I A N
METODE KERJA
![Page 393: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/393.jpg)
JENIS PEKERJAAN : LAPIS PONDASI AGREGAT Kls. A ( MANUAL )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 394: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/394.jpg)
JENIS PEKERJAAN : LAPIS PONDASI AGREGAT Kls. A ( MANUAL )SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 395: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/395.jpg)
JENIS PEKERJAAN : LAPIS PONDASI AGREGAT Kls. B, CBR MIN 60 % ( ALAT )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 396: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/396.jpg)
JENIS PEKERJAAN : LAPIS PONDASI AGREGAT Kls. B, CBR MIN 60 % ( ALAT )SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 397: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/397.jpg)
JENIS PEKERJAAN : LAPIS PONDASI AGREGAT Kls. B, CBR MIN 60 % ( MANUAL )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 398: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/398.jpg)
JENIS PEKERJAAN : LAPIS PONDASI AGREGAT Kls. B, CBR MIN 60 % ( MANUAL )SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 399: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/399.jpg)
JENIS PEKERJAAN : LPS. POND. AGG. KLS. A ( ALAT )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 400: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/400.jpg)
JENIS PEKERJAAN : LPS. POND. AGG. KLS. A ( ALAT )SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 401: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/401.jpg)
JENIS PEKERJAAN : LPS. POND. AGG. KLS. A ( MANUAL )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 402: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/402.jpg)
JENIS PEKERJAAN : LPS. POND. AGG. KLS. A ( MANUAL )SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 403: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/403.jpg)
JENIS PEKERJAAN : LPS. POND. AGREGAT. KLS. B ( ALAT )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 404: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/404.jpg)
JENIS PEKERJAAN : LPS. POND. AGREGAT. KLS. B ( ALAT )SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 405: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/405.jpg)
JENIS PEKERJAAN : LPS. POND. AGREGAT. KLS. B ( MANUAL )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 406: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/406.jpg)
JENIS PEKERJAAN : LPS. POND. AGREGAT. KLS. B ( MANUAL )SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 407: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/407.jpg)
JENIS PEKERJAAN : LAPIS PONDASI BAWAH KONSTRUKSI TELFORD ( MANUAL )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
U R A I A N
METODE KERJA
![Page 408: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/408.jpg)
JENIS PEKERJAAN : LAPIS PONDASI BAWAH KONSTRUKSI TELFORD ( MANUAL )SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 409: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/409.jpg)
JENIS PEKERJAAN : LAPIS PONDASI BAWAH KONSTRUKSI BATU KAPUR ( MANUAL )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 410: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/410.jpg)
JENIS PEKERJAAN : LAPIS PONDASI BAWAH KONSTRUKSI BATU KAPUR ( MANUAL )SATUAN PEMBAYARAN : M3
Lanjutan
No. KODE KOEF. SATUANU R A I A N
METODE KERJA
![Page 411: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/411.jpg)
JENIS PEKERJAAN : Lapis Pondasi Agregat Dengan Cement Treated Base (CTB) ManualSATUAN PEMBAYARAN : M³ METODE KERJA
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
U R A I A N
![Page 412: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/412.jpg)
JENIS PEKERJAAN : Lapis Pondasi Agregat Dengan Cement Treated Base (CTB) ManualSATUAN PEMBAYARAN : M³ METODE KERJA
Lanjutan
No. KODE KOEF. SATUAN
Lihat lampiran.
U R A I A N
![Page 413: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/413.jpg)
JENIS PEKERJAAN : LAPIS RESAP PENGIKAT (PRIME COAT)SATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
U R A I A N
METODE KERJA
![Page 414: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/414.jpg)
JENIS PEKERJAAN : LAPIS RESAP PENGIKAT (PRIME COAT)SATUAN PEMBAYARAN : M²
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 415: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/415.jpg)
JENIS PEKERJAAN : LAPIS PEREKAT (TACK COAT)SATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 416: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/416.jpg)
JENIS PEKERJAAN : LAPIS PEREKAT (TACK COAT)SATUAN PEMBAYARAN : M²
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 417: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/417.jpg)
JENIS PEKERJAAN : SAND SHEETSATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 418: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/418.jpg)
JENIS PEKERJAAN : SAND SHEETSATUAN PEMBAYARAN : M²
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 419: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/419.jpg)
JENIS PEKERJAAN : LAPIS TIPIS ASPAL BETON ( LATASTON/HRS ) - ( ALAT )SATUAN PEMBAYARAN : Ton
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 420: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/420.jpg)
JENIS PEKERJAAN : LAPIS TIPIS ASPAL BETON ( LATASTON/HRS ) - ( ALAT )SATUAN PEMBAYARAN : Ton
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 421: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/421.jpg)
JENIS PEKERJAAN : LAPIS ASPAL BETON ( LASTON /AC ) - ( ALAT )SATUAN PEMBAYARAN : Ton
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 422: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/422.jpg)
JENIS PEKERJAAN : LAPIS ASPAL BETON ( LASTON /AC ) - ( ALAT )SATUAN PEMBAYARAN : Ton
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 423: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/423.jpg)
JENIS PEKERJAAN : ASPHALT TREADE BASE ( ATB ) - ( ALAT )SATUAN PEMBAYARAN : Ton
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA / METODE PELAKSANAAN
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
U R A I A N
METODE KERJA
![Page 424: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/424.jpg)
JENIS PEKERJAAN : ASPHALT TREADE BASE ( ATB ) - ( ALAT )SATUAN PEMBAYARAN : Ton
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 425: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/425.jpg)
5.5 (1)JENIS PEKERJAAN : LAPIS PERMUKAAN PENETRASI MACADAM ( t = 7 cm )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 426: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/426.jpg)
JENIS PEKERJAAN : LAPIS PERMUKAAN PENETRASI MACADAM ( t = 7 cm )SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUANU R A I A N
METODE KERJA
![Page 427: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/427.jpg)
JENIS PEKERJAAN : LAPIS PONDASI PERATA PENETRASI MACADAMSATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 428: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/428.jpg)
JENIS PEKERJAAN : LAPIS PONDASI PERATA PENETRASI MACADAMSATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 429: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/429.jpg)
JENIS PEKERJAAN : SAND SHEET (UNTUK JALAN LINGKUNGAN)SATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 430: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/430.jpg)
JENIS PEKERJAAN : SAND SHEET (UNTUK JALAN LINGKUNGAN)SATUAN PEMBAYARAN : M²
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 431: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/431.jpg)
JENIS PEKERJAAN : LAPIS TIPIS ASPAL BETON ( LATASTON/HRS ) - ( MANUAL )SATUAN PEMBAYARAN : Ton
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 432: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/432.jpg)
JENIS PEKERJAAN : LAPIS TIPIS ASPAL BETON ( LATASTON/HRS ) - ( MANUAL )SATUAN PEMBAYARAN : Ton
Lanjutan
No. KODE KOEF. SATUAN
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 433: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/433.jpg)
JENIS PEKERJAAN : LAPIS ASPAL BETON ( LASTON /AC ) - ( MANUAL )SATUAN PEMBAYARAN : Ton
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA / METODE PELAKSANAAN
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 434: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/434.jpg)
JENIS PEKERJAAN : LAPIS ASPAL BETON ( LASTON /AC ) - ( MANUAL )SATUAN PEMBAYARAN : Ton
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 435: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/435.jpg)
JENIS PEKERJAAN : ASPHALT TREADE BASE ( ATB ) - ( MANUAL )SATUAN PEMBAYARAN : Ton
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA / METODE PELAKSANAAN
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke hal. berikut.
METODE KERJA
U R A I A N
![Page 436: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/436.jpg)
JENIS PEKERJAAN : ASPHALT TREADE BASE ( ATB ) - ( MANUAL )SATUAN PEMBAYARAN : Ton
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 437: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/437.jpg)
JENIS PEKERJAAN : BETON STRUKTUR READY MIX K-500SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 438: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/438.jpg)
JENIS PEKERJAAN : BETON STRUKTUR READY MIX K-500SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 439: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/439.jpg)
JENIS PEKERJAAN : BETON STRUKTUR READY MIX K-400SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 440: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/440.jpg)
JENIS PEKERJAAN : BETON STRUKTUR READY MIX K-400SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
U R A I A N
METODE KERJA
![Page 441: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/441.jpg)
JENIS PEKERJAAN : BETON STRUKTUR READY MIX K-350SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 442: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/442.jpg)
JENIS PEKERJAAN : BETON STRUKTUR READY MIX K-350SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 443: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/443.jpg)
JENIS PEKERJAAN : BETON STRUKTUR READY MIX K-300SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 444: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/444.jpg)
JENIS PEKERJAAN : BETON STRUKTUR READY MIX K-300SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
U R A I A N
METODE KERJA
![Page 445: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/445.jpg)
JENIS PEKERJAAN : BETON STRUKTUR READY MIX K-225SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 446: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/446.jpg)
JENIS PEKERJAAN : BETON STRUKTUR READY MIX K-225SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 447: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/447.jpg)
JENIS PEKERJAAN : BETON STRUKTUR K-225 ( SITE MIX )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 448: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/448.jpg)
JENIS PEKERJAAN : BETON STRUKTUR K-225 ( SITE MIX )SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUANU R A I A N
METODE KERJA
![Page 449: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/449.jpg)
JENIS PEKERJAAN : BETON STRUKTUR SITE MIX K-175SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 450: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/450.jpg)
JENIS PEKERJAAN : BETON STRUKTUR SITE MIX K-175SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 451: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/451.jpg)
JENIS PEKERJAAN : BETON SIKLOP STRUKTUR SITE MIX K-175SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
U R A I A N
METODE KERJA
![Page 452: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/452.jpg)
JENIS PEKERJAAN : BETON SIKLOP STRUKTUR SITE MIX K-175SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 453: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/453.jpg)
JENIS PEKERJAAN : BETON STRUKTUR SITE MIX K-125SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 454: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/454.jpg)
JENIS PEKERJAAN : BETON STRUKTUR SITE MIX K-125SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUANU R A I A N
METODE KERJA
![Page 455: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/455.jpg)
JENIS PEKERJAAN : PEMBESIAN BAJA TULANGANSATUAN PEMBAYARAN : Kg
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 456: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/456.jpg)
JENIS PEKERJAAN : BEKISTING UNTUK BETON STRUKTUR (JEMBATAN)SATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
U R A I A N
METODE KERJA
![Page 457: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/457.jpg)
JENIS PEKERJAAN : BEKISTING UNTUK BETON STRUKTUR SALURANSATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 458: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/458.jpg)
JENIS PEKERJAAN : PONDASI CERUCUK, PENYEDIAAN DAN PEMANCANGANSATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 459: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/459.jpg)
JENIS PEKERJAAN : DINDING TURAP BAJASATUAN PEMBAYARAN : Kg
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 460: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/460.jpg)
JENIS PEKERJAAN : DINDING TURAP BAJASATUAN PEMBAYARAN : Kg
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 461: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/461.jpg)
JENIS PEKERJAAN : BRONJONGSATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 462: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/462.jpg)
JENIS PEKERJAAN : BRONJONG (DENGAN ANGKUTAN)SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 463: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/463.jpg)
JENIS PEKERJAAN : PEMBONGKARAN BETON ( MANUAL ) SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 464: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/464.jpg)
JENIS PEKERJAAN : PEMBONGKARAN BETON ( MANUAL ) SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 465: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/465.jpg)
JENIS PEKERJAAN : BORE PILE BETON, Dia. 300 mmSATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 466: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/466.jpg)
JENIS PEKERJAAN : BORE PILE BETON, Dia. 300 mmSATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 467: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/467.jpg)
JENIS PEKERJAAN : BORE PILE BETON, Dia. 400 mmSATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 468: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/468.jpg)
JENIS PEKERJAAN : BORE PILE BETON, Dia. 400 mmSATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUANU R A I A N
METODE KERJA
![Page 469: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/469.jpg)
JENIS PEKERJAAN : BORE PILE BETON, Dia. 500 mmSATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 470: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/470.jpg)
JENIS PEKERJAAN : BORE PILE BETON, Dia. 500 mmSATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 471: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/471.jpg)
JENIS PEKERJAAN : PEMANCANGAN SHEET PILESATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 472: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/472.jpg)
JENIS PEKERJAAN : PEMANCANGAN SHEET PILESATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 473: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/473.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-325-A-1000 P : 8-13, K-700SATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 474: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/474.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-325-A-1000 P : 8-13, K-700SATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 475: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/475.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-325-B-1000 P : 8-14, K-700SATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 476: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/476.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-325-B-1000 P : 8-14, K-700SATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 477: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/477.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-350-A-1000 P : 9-15, K-700SATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 478: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/478.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-350-A-1000 P : 9-15, K-700SATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 479: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/479.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-350-B-1000 P : 10-15, K-700SATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 480: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/480.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-350-B-1000 P : 10-15, K-700SATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 481: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/481.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-400-A-1000 P : 10-16, K-700SATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 482: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/482.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-400-A-1000 P : 10-16, K-700SATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 483: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/483.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-400-B-1000 P : 11-16, K-700SATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 484: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/484.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-400-B-1000 P : 11-16, K-700SATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 485: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/485.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-450-A-1000 P : 11-17, K-700SATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 486: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/486.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-450-A-1000 P : 11-17, K-700SATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 487: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/487.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-450-B-1000 P : 12-17, K-700SATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 488: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/488.jpg)
JENIS PEKERJAAN : PENYEDIAAN SHEET PILE TYPE W-450-B-1000 P : 12-17, K-700SATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 489: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/489.jpg)
JENIS PEKERJAAN : PENYEDIAAN FLAT SHEET PILE, K-700SATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 490: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/490.jpg)
JENIS PEKERJAAN : PENYEDIAAN FLAT SHEET PILE, K-700SATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 491: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/491.jpg)
JENIS PEKERJAAN : PEMANCANGAN TIANG PANCANGSATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 492: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/492.jpg)
JENIS PEKERJAAN : PEMANCANGAN TIANG PANCANGSATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 493: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/493.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-300 - 6 s/d 8, Segmen BottomSATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 494: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/494.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-300 - 6 s/d 8, Segmen BottomSATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 495: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/495.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-300 - 6 s/d 8, Segmen Bottom PencilSATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 496: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/496.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-300 - 6 s/d 8, Segmen Bottom PencilSATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 497: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/497.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-300 - 6 s/d 8, Segmen MiddleSATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 498: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/498.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-300 - 6 s/d 8, Segmen MiddleSATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 499: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/499.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-400 - 6 s/d 8, Segmen BottomSATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 500: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/500.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-400 - 6 s/d 8, Segmen BottomSATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 501: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/501.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-400 - 6 s/d 8, Segmen Bottom PencilSATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 502: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/502.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-400 - 6 s/d 8, Segmen Bottom PencilSATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 503: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/503.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-400 - 6 s/d 8, Segmen MiddleSATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 504: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/504.jpg)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Type A2-400 - 6 s/d 8, Segmen MiddleSATUAN PEMBAYARAN : M'
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 505: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/505.jpg)
JENIS PEKERJAAN : PERKERASAN JALAN BETON K-350 SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 506: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/506.jpg)
JENIS PEKERJAAN : PERKERASAN JALAN BETON K-350 SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 507: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/507.jpg)
JENIS PEKERJAAN : PERKERASAN JALAN BETON K-350 ( DENGAN ANGKUTAN )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 508: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/508.jpg)
JENIS PEKERJAAN : PERKERASAN JALAN BETON K-350 ( DENGAN ANGKUTAN )SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 509: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/509.jpg)
JENIS PEKERJAAN : PERKERASAN JALAN BETON READY MIX K-225 SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 510: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/510.jpg)
JENIS PEKERJAAN : PERKERASAN JALAN BETON READY MIX K-225 SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 511: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/511.jpg)
JENIS PEKERJAAN : PERKERASAN JALAN BETON READY MIX K-225 ( DENGAN ANGKUTAN SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 512: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/512.jpg)
JENIS PEKERJAAN : PERKERASAN JALAN BETON READY MIX K-225 ( DENGAN ANGKUTAN )SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUAN
METODE KERJA
U R A I A N
![Page 513: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/513.jpg)
JENIS PEKERJAAN : PERKERASAN JALAN BETON K-225 ( SITE MIX )SATUAN PEMBAYARAN : M³
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 514: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/514.jpg)
JENIS PEKERJAAN : PERKERASAN JALAN BETON K-225 ( SITE MIX )SATUAN PEMBAYARAN : M³
Lanjutan
No. KODE KOEF. SATUANU R A I A N
METODE KERJA
![Page 515: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/515.jpg)
JENIS PEKERJAAN : ACUAN PERKERASAN BETONSATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 516: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/516.jpg)
JENIS PEKERJAAN : PASANGAN PLASTIC SHEETSATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
U R A I A N
![Page 517: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/517.jpg)
JENIS PEKERJAAN : JOINT SEALENTSATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
U R A I A N
![Page 518: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/518.jpg)
JENIS PEKERJAAN : PEMOTONGAN POHON KERASSATUAN PEMBAYARAN : Buah
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
Berlanjut ke halaman berikut
METODE KERJA
U R A I A N
![Page 519: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/519.jpg)
JENIS PEKERJAAN : PEMOTONGAN POHON KERASSATUAN PEMBAYARAN : Buah
Lanjutan
No. KODE KOEF. SATUAN
Rp. 0 / Buah
6. MASA PELAKSANAAN YANG DIPERLUKANMasa Pelaksanaan : . . . . . . . . . . . bulan
7. VOLUME PEKERJAAN YANG DIPERLUKANVolume pekerjaan : Buah
METODE KERJA
U R A I A N
![Page 520: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/520.jpg)
JENIS PEKERJAAN : PEMOTONGAN POHON LUNAKSATUAN PEMBAYARAN : Buah
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 521: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/521.jpg)
JENIS PEKERJAAN : PENGUPASAN DAN PEMBERSIHAN SEMAKSATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 522: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/522.jpg)
JENIS PEKERJAAN : PENGUPASAN DAN PEMBERSIHAN GULMANSATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 523: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/523.jpg)
JENIS PEKERJAAN : STABILISASI DENGAN TANAMANSATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
U R A I A N
METODE KERJA
![Page 524: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/524.jpg)
JENIS PEKERJAAN : MARKA JALAN TERMOPLASTIK (MANUAL)SATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 525: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/525.jpg)
![Page 526: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/526.jpg)
JENIS PEKERJAAN : MARKA JALAN BUKAN TERMOPLASTIK (MANUAL)SATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 527: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/527.jpg)
![Page 528: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/528.jpg)
JENIS PEKERJAAN : PASANGAN KANSTEEN 15.25.40SATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 529: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/529.jpg)
JENIS PEKERJAAN : PASANGAN KANSTEEN 13.20.40SATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 530: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/530.jpg)
JENIS PEKERJAAN : PASANGAN KANSTEEN 15.28.40SATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 531: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/531.jpg)
JENIS PEKERJAAN : PASANGAN KANSTEEN 20.25.60SATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 532: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/532.jpg)
JENIS PEKERJAAN : PASANGAN KANSTEEN 30.25.60SATUAN PEMBAYARAN : M'
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 533: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/533.jpg)
JENIS PEKERJAAN : PERKERASAN PAVING BLOK (PEDESTRIAN)SATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N
![Page 534: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/534.jpg)
JENIS PEKERJAAN : PERKERASAN PAVING BLOK, t = 8 cm (JALAN)SATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
III. TENAGA
METODE KERJA
U R A I A N
![Page 535: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/535.jpg)
JENIS PEKERJAAN : PERKERASAN PAVING BLOK, t = 6 cm (JALAN)SATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
III. TENAGA
METODE KERJA
U R A I A N
![Page 536: HARGA DASAR SATUAN UPAH - docshare04.docshare.tips](https://reader030.fdocument.pub/reader030/viewer/2022012019/616881dbd394e9041f700bcb/html5/thumbnails/536.jpg)
JENIS PEKERJAAN : BONGKAR DAN PEMASANGAN KEMBALI PAVING BLOKSATUAN PEMBAYARAN : M²
No. KODE KOEF. SATUAN
I. ASUMSI
II. URUTAN KERJA
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
METODE KERJA
U R A I A N