PLAN DE L’EXPOSE
1. GENERALITES ET DEFINITIONS
2. PREPARATION DU CHANTIER
3. PLANIFICATION DES TRAVAUX
4. INSTALLATION DU CHANTIER
5. SUIVI ET CONTRÔLE DES TRAVAUX
![Page 3: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/3.jpg)
GENERALITES ET DEFINITIONS
![Page 4: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/4.jpg)
PREPARATION DU CHANTIER
![Page 5: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/5.jpg)
PREPARER, C’EST
1- Effectuer les démarches
administratives
2- Mettre au point le projet
d’exécution
3- Elaborer les plans
d’exécution
4- Définir les modes
opératoires
5- Constituer l’équipe
de tâcherons
6- Commander les matériaux
7- Prévoir la sécurité
![Page 6: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/6.jpg)
DEFINITIONS
Préparer un chantier
faire coïncider la commande du client et les moyens de l’entreprise (Poste main
d’œuvre, Poste matériaux et Poste matériels)
C’est donc évaluer les besoins et les coûts des matériels, des matériaux et de la
main d’oeuvre
![Page 7: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/7.jpg)
OBJECTIFS
Bon déroulement économique et social du chantier;
Meilleure exécution des travaux
70 % des dysfonctionnements sont dus à sa non préparation
![Page 8: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/8.jpg)
NECESSITES
1- Plan d’exécution de l’ouvrage
Devis descriptif (plans et documents techniques)
Devis quantitatif
Devis estimatif
2- Planning
3- Coût général
![Page 9: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/9.jpg)
NORMES PROFESSIONNELLES
Délai de préparation, à défaut, = 3 mois
Décomposition du délai d’exécution
Période d’organisation du chantier;
Période d’exécution;
![Page 10: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/10.jpg)
PLANIFICATION DU CHANTIER
![Page 11: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/11.jpg)
PLANIFIER, C’EST
1- Etablir le calendrier prévisionnel
Et les budgets nécessaires
2- Main d’oeuvre
3- Matériaux
4- Matériel
![Page 12: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/12.jpg)
PHASES D’ELABORATION DU PLANNING
1- Consultation
des documents
2- Décomposition
des zones
3- Liste
Les tâches
4- Elaboration
des graphes
5- Saisie des données
6- Dessin du Planning
7- Mise à jour
![Page 13: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/13.jpg)
ETABLISSEMENT DU PLANNINGN° tâch Mois 1 Mois 2
1
2
…
Semaine 1 2 3 4 1 2 3 4
M. Œuvre
M.S
M.O
Matériel
Poclain
Pelle
Camion
…..
Matériaux
Gravette
Maçonn
Ciment
Courbe de la Main d’Oeuvre
![Page 14: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/14.jpg)
INSTALLATION DU CHANTIER
![Page 15: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/15.jpg)
INSTALLER, C’EST
1- Réaliser les réseaux
Tél, Eléctricité, …
2- Réaliser les zones
De travail
3- Réaliser les aires
de stockage
4- Bureaux, parquements
Clôture, vestiaire
5- Installer le matériel
6- Tracer l’ouvrage
À réaliser
7- Terrasser
![Page 16: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/16.jpg)
OBJECTIFS
Assurer aux personnes de bonnes conditions d’hygiène et de travail;
Accueillir sur le chantier les différents fournisseurs;
Réserver différentes zones pour stocker les matériaux, du matériel, ….
![Page 17: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/17.jpg)
TACHES D’INSTALLATION
1. Définir le type de chantier pour implanter les locaux et l’équipement à mettre en place;
2. Tracer le réseau électrique, le réseau d’AEP, les accès, le téléphone, le réseau des eaux usées;
3. Installer la clôture du chantier;
4. Placer les engins de levage, les surfaces de production du béton, …;
5. Définir un plan particulier de sécurité et de production de la santé.
![Page 18: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/18.jpg)
TYPES DE CHANTIER
Installations nécessaires
Type
d’installation
Type « a »
Durée < 15 J
Type « b »
15 J- 4 mois
Type « c »
> 4 mois
Abri
Vestiaire
Repas
Eau
Sanitaire
Latrines
Bureau
Aires stocka
Zone travail
Trousses de
secours
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
![Page 19: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/19.jpg)
SUIVI ECONOMIQUE ET
TECHNIQUE DU CHANTIER
![Page 20: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/20.jpg)
SUIVRE LE CHANTIER, C’EST
1- Contrôler techniquement
2- Gérer le personnel
3- Suivre les consommations
(MO, Matériaux, Matériel)
4- Contrôler l’avancement
Des travaux
5- Gérer les relations avec
Les fournisseurs
6- Facturer
7- Analyser les résultats
(MO, Matériaux, Matériel)
8- Les utiliser dans un
autre chantier
![Page 21: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/21.jpg)
OBJECTIFS
Pointer l’avancement des travaux au fur et à mesure;
Mettre à jour le planning d’exécution;
Prévoir les approvisionnements des matériaux et matériels;
Comparer les réalisation aux prévisions et les recettes aux dépenses
Dégager un résultat positif
![Page 22: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/22.jpg)
MERCI
![Page 23: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/23.jpg)
RECONNAISSANCE ET IMPLANTATION
![Page 24: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/24.jpg)
Reconnaissance et implantation
Implantation avec AUEA
PV d’implantation
Levé topographique (Profils en long et en travers)
Calage (soumis à l’avis de l’AT)
Piquetage
Tableau de cote soumis au chef de chantier
Contrôle topo
![Page 25: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/25.jpg)
TERRASSEMENTS
![Page 26: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/26.jpg)
TERRASSEMENTS
![Page 27: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/27.jpg)
TOLEARANCE
![Page 28: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/28.jpg)
BLOCAGES
![Page 29: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/29.jpg)
BLOCAGES
![Page 30: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/30.jpg)
BLOCAGEBONNES PRATIQUES
![Page 31: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/31.jpg)
PREPARATION AGREGATS
![Page 32: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/32.jpg)
UNITE DE PRODUCTION
![Page 33: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/33.jpg)
AGREGATS
![Page 34: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/34.jpg)
FERRAILLAGE
![Page 35: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/35.jpg)
POSE FERRAILLAGE
![Page 36: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/36.jpg)
POSE FERRAILLAGE
![Page 37: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/37.jpg)
COFFRAGES
![Page 38: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/38.jpg)
COFFRAGES
![Page 39: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/39.jpg)
COFFRAGES
![Page 40: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/40.jpg)
BETONS
![Page 41: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/41.jpg)
CARACTERISTIQUES DES BETONS ET DES MORTIERS
EQUIVALNT DE SABLE
2- 70 <= ES <= 85 EAU DE GACHAGE
Matières en suspension :
<= 2 g/l pour un béton de qualité<= 5 g/l pour un béton courant
DOSAGE :
Ciment / Eau = 2 SEL
<= 15 g/l pour un béton de qualité<= 30 g/l pour un béton courant
7- MALAXAGE
Durée : 2 – 3 mn Ordre d’approvisionnement : G2 ; Ciment ; G1 et eau
![Page 42: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/42.jpg)
COMPOSITION BETON
COMPOSITION Sable : 35 % G1 : 25 % G2 : 40 %
G / S = 1,85
COMPOSITION SABLE
Sable fin (0,08 – 0,315) : 25 % Sable moyen (0,315 – 1,25) : 10 % Sable gros (1,25 – 5,00) : 65 %
RESISTANCE DES BETONS
Type de béton Compression à 7 jours à 28 jours
Béton armé 17 27Béton ordinaire 15 23Béton de propreté 11 18
![Page 43: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/43.jpg)
Bétons
![Page 44: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/44.jpg)
FISSURATIONS DU RADIER
![Page 45: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/45.jpg)
BETON RADIER
![Page 46: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/46.jpg)
MISE EN OUEVRE BETON
![Page 47: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/47.jpg)
MISE EN ŒUVRE BETONDEFAUTS
![Page 48: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/48.jpg)
SEGREGATIONS DU BETON
![Page 49: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/49.jpg)
PEAU DE CRAPAUD
![Page 50: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/50.jpg)
MACONNERIE
![Page 51: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/51.jpg)
MACONNERIE
![Page 52: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/52.jpg)
MACONNERIE – MUR DE PROTECTION
![Page 53: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/53.jpg)
MISE EN ŒUVRE MACONNERIE
![Page 54: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/54.jpg)
ARROSAGE ET CURE
![Page 55: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/55.jpg)
ARROSAGE
![Page 56: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/56.jpg)
JOINTS
![Page 57: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/57.jpg)
JOINTS
1. Joints de construction:
Se placent au lieu d’interruption du chantier; c’est à dire entre deux bétons d’âge différent (par exemple entre le radier et le bajoyer dans le cas où ils sont coulés séparément). En général, ils jouent ultérieurement le rôle de joints de retrait transversaux ou longitudinaux, ou joints de dilatation.
2. Joints de retrait transversaux
Destinés à empêcher les crevasses transversales qui résulteraient des changements de volume causés par les baisses de températures ou des pertes d’humidité, y compris celles qui se produisent lors de la prise (curing).
Pour les revêtement en béton ordinaire, les espacements entre ces joints sont de 50 fois l’épaisseur de la dalle
3. Joints longitudinaux:
Utilisés pour empêcher les crevasses irrégulières de se former dans le sens de la longueur.
Au cas d’une dalle non armée et si le périmètre de revêtement est supérieur à 9 m², on espace ces joints de 2,5 à 4,5 m. Ils ne sont prévus, en dalle armée, qu’au cas des canaux à grande largeur supérieure à 4 m.
![Page 58: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/58.jpg)
4. Joints de dilatation:
Ne sont pas nécessaires en général dans les canaux à revêtement en béton sauf lorsque ceux-ci viennent s’appuyer contre un ouvrage fixe, dans l’intrados des courbes de faible rayon, ou dans conditions sortant de la normale (climat très chaud).
Ces joints sont appliqués lors de la construction en maçonnerie et en béton armé sous forme de joint water stop respectivement tous les 12 ml.
Ces joints ont pour effet d’augmenter l’ouverture des joints de retrait voisins, ce qu’il faut éviter dans le revêtement des canaux en béton ordinaire du fait de la difficulté de maintien de l’étanchéité.
Ces joints doivent être exécutés sur toute l’épaisseur de la dalle, avec une largeur de 2 cm.
![Page 59: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/59.jpg)
JOINTS DE DILATATION
![Page 60: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/60.jpg)
JOINTS DE RETRAIT
![Page 61: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/61.jpg)
JOINTS DE RETRAIT
![Page 62: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/62.jpg)
JOINTS DE CONSTRUCTION
![Page 63: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/63.jpg)
JOINTS WATER STOP
![Page 64: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/64.jpg)
REMBLAIS ET REMISE EN ETAT
![Page 65: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/65.jpg)
REMBLAIS
![Page 66: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/66.jpg)
REMBLAIS
![Page 67: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/67.jpg)
ENVIRONNEMENT
![Page 68: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/68.jpg)
ASPECTS ENVIRONEMENTAUX
![Page 69: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/69.jpg)
ASPECTS ENVIRONEMENTAUX
![Page 70: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/70.jpg)
SECURITE ET SANTE
![Page 71: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/71.jpg)
OUVRAGES PARTICULIERS
![Page 72: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/72.jpg)
OUVRAGE D’ANGLE
![Page 73: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/73.jpg)
OUVRAGES DE PASSGE
![Page 74: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/74.jpg)
OUVRAGE DE PASSAGE
![Page 75: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/75.jpg)
VANNETTES
![Page 76: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/76.jpg)
VANNETTE
![Page 77: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/77.jpg)
OUVRAGE DE CHUTE
![Page 78: Gestion chantier MCA-](https://reader034.fdocument.pub/reader034/viewer/2022052304/558317d1d8b42a3c658b48c6/html5/thumbnails/78.jpg)
OUVRAGE KHETTARA