ESTIM ASI RINCIAN BIAYA TUKANG NO KEBUTUHAN Ukuran (Lx T ) LUAS (m ) BIAYA /(m ) TOTALBIAYA KETERANGAN 1 Pondasi 27 m 27 75,000 2,025,000 2 Susun Batu Lt. Baw ah 25,6 x3,5 90 15,000 1,344,000 3 CorTiang 7 x3,5 25 15,000 367,500 4 Kam arM andi 1 500,000 500,000 5 CorLantai atas 6 jam x10 org 60 6,500 390,000 6 Cakarayam 7 Susun Batu Lt. atas 17 x1 17 15,000 255,000 8 Tehel 28 20,000 560,000 Plaster 15,000 - Tem busLuardalam 9,6 x3,5 34 15,000 504,000 Kam arbag. Dlm , dinding tengah, W C bag. Dlm , Pembataspintu Tdktem bus 11,5 x3,5 40 7,500 301,875 Kam arbag. Kiri Luar/belakang, W C bag. Luar, sisi kanan rum ah 10 Cat+ Plam er 2 Hari 1 150,000 150,000 6,397,375 9 ptila si Jendel a BADAN RUMAH Cuci

description

home

Transcript of Gambar rumah

Page 1: Gambar rumah

ESTIMASI RINCIAN BIAYA TUKANG

NO KEBUTUHAN Ukuran ( L x T ) LUAS (m) BIAYA / (m) TOTAL BIAYA KETERANGAN1 Pondasi 27 m 27 75,000 2,025,000 2 Susun Batu Lt. Bawah 25,6 x 3,5 90 15,000 1,344,000 3 Cor Tiang 7 x 3,5 25 15,000 367,500 4 Kamar Mandi 1 500,000 500,000 5 Cor Lantai atas 6 jam x 10 org 60 6,500 390,000 6 Cakar ayam7 Susun Batu Lt. atas 17 x 1 17 15,000 255,000 8 Tehel 28 20,000 560,000

Plaster 15,000 -

Tembus Luar dalam 9,6 x 3,5 34 15,000 504,000 Kamar bag. Dlm, dinding tengah, WC bag. Dlm,

Pembatas pintu

Tdk tembus 11,5 x 3,5 40 7,500 301,875 Kamar bag. Kiri Luar / belakang, WC bag. Luar,

sisi kanan rumah10 Cat + Plamer 2 Hari 1 150,000 150,000

6,397,375

9

ptilasi Jendela

BADAN RUMAH

Cuci

Page 2: Gambar rumah

ESTIMASI RINCIAN BIAYA TUKANG

NO KEBUTUHAN Ukuran ( L x T ) LUAS (m) BIAYA / (m) TOTAL BIAYA KETERANGAN1 Pondasi 22,5 m 23 75,000 1,687,500 2 Susun Batu Lt. Bawah 22,5 x 3,5 79 15,000 1,181,250 3 Susun Batu Lt. atas 17 x 1 17 15,000 255,000 4 Tehel 28 20,000 560,000

Plaster 15,000 -

Tembus Luar dalam 9,6 x 3,5 34 15,000 504,000 Kamar bag. Dlm, dinding tengah, WC bag. Dlm,

Pembatas pintu

Tdk tembus 11,5 x 3,5 40 7,500 301,875 Kamar bag. Kiri Luar / belakang, WC bag. Luar,

sisi kanan rumah6 Cor Tiang 12 X 3,5 42 15,000 630,000 7 Kamar Mandi 1 500,000 500,000 8 Cor Lantai atas 6 jam x 10 org 60 6,500 390,000 9 Cat + Plamer 2 Hari 1 150,000 150,000

6,159,625

5

ESTIMASI BIAYA BAHAN BANGUNAN

NO KEBUTUHAN JUMLAH (Truk/Bh/kg) BIAYA TOTAL BIAYATimbunan 2 175,000 350,000

Pasir Pondasi 3 275,000 825,000 Batu Pondasi 1 450,000 450,000

Pasir 5 175,000 875,000 Kerikil - Semen 100 57,000 5,700,000 Besi 10 138 58,000 8,004,000 Batako 2000 1,300 2,600,000 Kawat 5 18,000 90,000

Behel 6 SNI 15 25,000 375,000 Paku 3 1 - Paku 2 0.5 -

Papan mal 6 25,000 150,000 Konsen 5 250,000 1,250,000

Pintu 2 - Tehel 28 60,000 1,680,000

- 22,349,000