FPI review process & AIV&T plan of FPIA

17
FPI review process & AIV&T plan of FPIA Based on spica_AIVT_revC, FPI_review_by_SDR_F Apr. 6 th , 2010 by H. Matsuhara, N. Takahashi, T. Nakagawa

description

FPI review process & AIV&T plan of FPIA. Based on spica_AIVT_revC , FPI_review_by_SDR_F Apr. 6 th , 2010 by H. Matsuhara , N. Takahashi, T. Nakagawa. Review process in Japan as well as International Level. FPI Review by SDR. Review process of Japanese-lead instruments. - PowerPoint PPT Presentation

Transcript of FPI review process & AIV&T plan of FPIA

Page 1: FPI  review process & AIV&T plan of FPIA

FPI review process &AIV&T plan of FPIA

Based on spica_AIVT_revC, FPI_review_by_SDR_F

Apr. 6th, 2010 byH. Matsuhara, N. Takahashi, T. Nakagawa

Page 2: FPI  review process & AIV&T plan of FPIA

FPI REVIEW BY SDRReview process in Japan as well as International Level

Page 3: FPI  review process & AIV&T plan of FPIA

Review process of Japanese-lead instruments

• Japanese-lead instruments:– MIRACLE, MIRMES, MIRHES, SCI

• Instrument Proposals (including conceptual design report ) shall be submitted by the end of April, 2010.

• Review by a Japanese Board (Selection committee) – prioritize each proposal by July 2010. – prioritize the instrument specifications (not instrument

as a whole) in each FPI, judging by their scientific values and the technical readiness, etc.

– The Details of Review & Decision process was discussed in the Task Force Meeting on 29th March, 2010

Page 4: FPI  review process & AIV&T plan of FPIA

Issues to be addressed in the review

Consistency with the scientific targets described in the Mission Requirement Document

Technical FeasibilityMaturity of results from the concept studyConsistency with the ICS-FPI (ICS-SAFARI,

etc.) Identification of technical development risks,

clear description of prescription against risksPropriety in the development plan, cost, & team

organization

Page 5: FPI  review process & AIV&T plan of FPIA

International Review of FPI

• Review in Japan• 30th Apr. 2010 : due of Japanese-led instrument• May-July: Review by a Japanese board• Korean-based instrument (FPC) will be also reviewed

• ESA-JAXA Review• Q2-Q3 FY2010: review for the focal plane instrument under an

international Board organized by ``Joint-Project Office” - details need to be discussed / agreed

• “SAFARI Phase-A final study report” need to be reviewed also by ESA & JAXA, well before SDR

• US-lead Instruments• US-lead instrument: review & selection process need to be

discussed with NASA – ex. NASA representative will be a member of the Joint-Project Office?

Page 6: FPI  review process & AIV&T plan of FPIA

“FPI Review process”Issues to be agreed

Definition of ‘Joint-Project Office’ & review board for the final FPI decision Authority, place in the project structure Policy of membership

Review Policy – need to be agreed Judgment should be based on the achievement in

the “Issues to be addressed” (see page 5) For Japanese-lead instrument, JAXA proposes to

make selection based on the function/coverage of the instrument within SPICA and not on the individual instrument.

Page 7: FPI  review process & AIV&T plan of FPIA

FPIA MODEL PHILOSOPHY & TEST SCHEDULE

Necessary Models for the System Level Tests of the FPI Assembly

Page 8: FPI  review process & AIV&T plan of FPIA

Key issues for FPI AIV&T

FPI’s system-level test plan should take account of the critical issues as below: (a) FPI is cooled to <5K with J-T coolers under

extremely careful Spacecraft thermal design. (b) disturbance and interference from J-T coolers and

AOCS (such as RW, gyro) To assure high-sensitivity (low-noise) in orbit

(c) Co-operation with FPC-G to establish the pointing stability

Interferences? Alignment? (d) Co-focus among FPIs (especially MIR’s)

Since STA 2ry cannot be adjusted so frequently in orbit

Page 9: FPI  review process & AIV&T plan of FPIA

FPI Model philosophy

Cold FPIs Minimum number of Models required for the system level test (in the

previous page) is: FM (Flight Model) (& its spare) STM : structure thermal model CQM : cold qualification model

Warm Electronics Similar as above, except for the terminology (CQM PM (proto-

model) A concern about SAFARI Warm Electronics STM : can the

requested heat dissipation be simulated by a heater? Spacecraft DHS simulator(SpaceWire I/F) will be developed, and

distributed hopefully before 2014 ( under discussion)

Page 10: FPI  review process & AIV&T plan of FPIA

STM (Structure Thermal Model) for FPIs

Purposes Evaluate their mechanical (at ambient temp.) & thermal compliances at

cold, in the system level (PLM or Spacecraft) Evaluate transfer function of mechanical disturbances originated from

FPIs Required Function

Same mechanical I/F specifications to FM Same thermal I/F specifications to FM Equipped with thermometers, acceleration sensors for measurement of

I/F environmental condition Simulate mechanical disturbance according to the system operation

modes Proposed Delivery

Oct. 2012 : before starting of assembly of PLM(STM) for the system Mechanical & Thermal Test

Page 11: FPI  review process & AIV&T plan of FPIA

CQM (Cold Qualification Model) for FPIs

Purposes Evaluate thermal compliance at cold with J-T(PM) cooler Evaluate susceptibility to mechanical disturbances from J-T (disturbance

simulator) and AOCS simulator Evaluate electrical interferences among FPIs, J-T, AOCS

Required Function Same thermal, mechanical, electrical I/F specifications to FM Equipped with detectors operable at low-temperature, with the same

noise performance as that of FM Simulate heat-dissipation (load to J-Ts), mechanical disturbance according

to the system operation modes Equipped with a optical image, to check the co-focus among FPIs

Proposed Delivery Apr. 2015 : when the PLM(FM) is available for us to test the items in page

2. Earlier delivery enables us to feedback for the design of FM

Page 12: FPI  review process & AIV&T plan of FPIA

FM (Flight Model) for FPIs

Purposes For on-orbit observations; for our scientific objectives, of course! After delivery and assembly to FPIA, FM will go to the “evaluation at

cold” in the dedicated chamber for evaluation of interferences, co focus among FPIs

Required Function Science Grade optical, noise, and sensitivity performances! Note that after the test called “FPI evaluation at cold”, long-wavelength

channel detectors cannot be operated (even may not be switched on??) - so how to verify its health during the long waiting time before launch/cooling in orbit?

Delivery date of FM:

June 2016 (August 2016 at worst) in the proposed scenario.

Page 13: FPI  review process & AIV&T plan of FPIA

SPICA AIV&T timeline (tentative)

13Consistency need to be checked with Industries’ estimates !!

Page 14: FPI  review process & AIV&T plan of FPIA

FPI: SPICA system test plan

With STM: Mechanical Environmental test & thermal test at cold at the PLM level Mechanical Environmental test & Thermal balance test at Spacecraft level Measure disturbance at FPI from J-T cooler/AOCS

With CQM: Cooling compliance test with J-T (PM) most important Evaluate susceptibility to mechanical disturbances from J-T (disturbance

simulator) and AOCS simulator, Co-focus is also checked to some level at cold (tbd) Evaluate electrical interferences among FPIs, J-T, AOCS in the 1st whole

FM V&T in 2016 if FM is not available yet With FM

FPI evaluation at cold (optical & electrical) STA optical performance test at cold Thermal test at cold at PLM level

14

Page 15: FPI  review process & AIV&T plan of FPIA

PLM Thermal Test at cold(STM and FM)

Purpose Evaluation of PLM cooling

system performances Alignment measurement

between STA and FPIA with FPC?

Date & Duration STM: April 2013 FM: Dec. 2017, ~2months

Method Additional shields in the

existing 13m space chamber in Tsukuba

Shields are externally lifted by mechanical coolers

15

Page 16: FPI  review process & AIV&T plan of FPIA

IOB FPI FPI

LHe

Mech. Cooler (commercial)

FPI(CQM or FM) test config. in the 1st Whole FM V&T

1Q-2Q FY2016, checkout with FM Bus Module Electronics before assembly/integration of FM Bus System

16

Page 17: FPI  review process & AIV&T plan of FPIA

Summary

Short-term schedule, esp. review process by SDR concept of ‘Joint-Project Office’, international review process

should be discussed / agreed “The Review policy” need to be agreed

FPI Model Philosophy Two models (STM, CQM) besides FM are proposed Proposed Delivery :

Oct. 2012 for STM Apr. 2015 for CQM June 2016 for FM

Earlier Delivery of CQM benefits to the mature design of FM