FIRE Vacuum Vessel and Remote Handling Overview B. Nelson, T. Burgess, T. Brown, D. Driemeyer, H-M...
-
date post
19-Dec-2015 -
Category
Documents
-
view
213 -
download
0
Transcript of FIRE Vacuum Vessel and Remote Handling Overview B. Nelson, T. Burgess, T. Brown, D. Driemeyer, H-M...
FIRE Vacuum Vessel
and Remote Handling
Overview
B. Nelson, T. Burgess, T. Brown, D. Driemeyer, H-M Fan, K. Freudenberg, G. Jones, C. Kessel, P. Ryan, M. Sawan, M. Ulrickson, D. Strickler,
D. Williamson
FIRE Physics Validation Review
March 31, 2004
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
2
Presentation Outline
Vacuum Vessel Design requirements Design concept and features Analysis to date Status and summary
Remote Handling Maintenance Approach & Component Classification In-Vessel Transporter Component Replacement Time Estimates Balance of RH Equipment
Design and analysis are consistent with pre-conceptual phase, but demonstrate basic feasibility of concepts
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
3
FIRE vacuum vessel
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
4
Vacuum vessel functions
Plasma vacuum environment
Primary tritium confinement boundary
Support for in-vessel components
Radiation shielding
Aid in plasma stabilization conducting shell internal control coils
Maximum access for heating/diagnostics
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
5
Vacuum vessel parameters
Configuration: Double wall torus Shielding water + steel with 60% packing factor Volume of torus interior 53 m^3 Surface Area of torus interior 112 m^2 Facesheet thickness 15 mm Rib thickness 15 - 30 mm Weight of structure, incl ports 65 tonnes Weight of torus shielding 100 tonnes
Coolant Normal Operation Water, < 100C, < 1 Mpa Bake-out Water ~150C, < 1 Mpa
Materials Torus, ports and structure 316LN ss Shielding 304L ss (tentative)
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
6
Vessel port configuration
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
7
Vessel ports and major components
Divertor pipingCryopump
Midplane port w/plugDivertor
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
8
Nuclear shielding concept Vessel shielding, port plugs and TF coils provide hands-on access to port
flanges Port plugs weigh ~7 tonnes each as shown, assuming 60% steel out to TF
boundary
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
9
Active control coils, segmented into octants IB and OB passive
stabilizing conductor
Active and passive stabilizing sys. passive plates ~25 mm thick copper with integral cooling
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
10
Passive conductor is also heat sink
Copper layer required to prevent large temperature gradients in VV due to nuclear heating, PFCs
Passive plates are required in most locations anyway
PFCs are conduction cooled to copper layer Reduces gradient in
stainless skin Extends pulse length
VV PFC Tile
Cu Passive stabilizer
Cu filler (can be removed to allow space for mag. diag.)
Gasket
VV splice plate
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
11
FIRE and ITER first wall concepts similar
Be Cu Tile SS Wall
Cu Cladding
0 10 20 30 40 50 60 70mm
80 90
Be Cu Tile
SS Back plate
ITER First Wall Panel
• BE, Cu, SSt
• Detachable FW panel
• Cooling integral with FW panel (requires coolant connections to FW)
ITER
FIRE
• BE, Cu, SSt
• Detachable FW tiles
• Cooling integral with Cu bonded to VV
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
12
VV octant subassy w/passive structure
Vessel octant prior to welding outer skin between ribs
Outboard passive conductor
Inboard passive cond.
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
13
Vessel octant subassembly fab. (2) Octant-to-octant splice joint requires double
wall weld All welding done from plasma side of vessel Splice plates used on plasma side only to
take up tolerance and provide clearance Plasma side splice plate wide enough to
accommodate welding the coil side joint
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
14
Vessel analysis
Vessel subjected to numerous loading conditions Normal operation (gravity, coolant pressure, thermal loads, etc.) Disruption (including induced and conductive (halo) loads Other loads (TF current ramp, seismic, etc.)
Preliminary FEA analysis performed Linear, static stress analysis Linear, transient and static thermal analyses
Main issues are disruption loads, thermal stresses
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
15
Vacuum vessel mechanical loads
Load
Gravity load
Vertical displacement event (VDE) load Vertical Lateral, net
Seismic load (assumed) Vertical accelerat ion Lateral acceleration
Maximum total vertical load Maximum total lateral load Maximum local EM load
Local pressure on vacuum vessel from internal co mponents
EM load from TF ramp Coolant pressure
Normal operation Bakeout
[1] Disrupti on loads per Wesley, based on 10T, 50% halo current
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
16
Disruption effects on VV
Disruptions will cause high loads on the VV due to induced currents and conducting (halo) currents flowing in structures Direct loads on vessel shell and ribs Direct loads on passive plates Reaction loads at supports for internal components Divertor assemblies and piping FW tiles Port plugs / in-port components (e.g. RF antennas)
Dynamic effects should be considered, including: Transient load application Shock loads due to gaps in load paths (gaps must be avoided)
All loads should be considered in appropriate combinations e.g. Gravity + coolant pressure + VDE + nuclear / PFC heating + Seismic + …
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
17
TSC runs confirm induced currents will concentrate in passive structures
Several TSC disruption simulations prepared by C. Kessel
VDE simulation used as basis for further analysis
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
18
VDE analysis based on TSC runs TSC output used to create drivers for Eddycuff model of VV Peak loads applied to ANSYS model of VV Halo loads from TSC mapped directly onto VV model
CopperPlates
InnerFaceSheet
OuterFace Sheet
EDDYCUFF EM Model ANSYS Structural Model
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
19
Plasma Evolution (TSC), from earlier data
I (A)
10-ms 300-ms 301-ms
301.6-ms 302.6-ms
ReducedFilamentModel (EDDYCUFF)
TSCFilaments
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
20
Constant Current VectorsProportional Current Vectors
Typical Induced Eddy Currents
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
21
Current vs Time, Slow VDE (1 MA/ms)
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
22
Typical EM loads due to Induced Current
• Max force = -1 MN radial, +0.7 MN vertical per 1/16 sector (~11 MN tot)
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
23
Total Force vs time, induced + halo currents
•
F(lbs)
t(s)
FZ
FR
1 MA/ms VDE
Case 2 Case 1
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
24
Typ. EM Force distr. due to Halo Current
• Mapped directly from TSC to ANSYS, Halo current = 12-25% Ip• Max force = +0.13 MN radial, +1.2 MN vert. per 1/16 sector
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
25
Y
X
Z
Pin 1 ReactionFx=12662Fz=10708
Pin 2 ReactionFx=-22147Fz=6614
Lug 1 ReactionFx=35121Fy=40107Fz=6987
Lug 2 ReactionFx=-32540Fy=-36384Fz=-6473 Forces are in pounds
Divertor loads from current loop
Loads based on PC-Opera analysis *ref Driemeyer, Ulrickson
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
26
Combined stress, with VDE Stresses due to gravity, coolant pressure, vacuum, VDE VDE load includes direct EM loads on vessel (induced current and
halo) and non-halo divertor loads
1.5Sm = 28 ksi (195 Mpa)
VV TorusPorts
Stress is in psi
Stress is in psi
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
27
Divertor attachment local stresses Global model not adequate for analysis Detailed model indicates adequate design
Stress is in psi1.5Sm = 28ksi (195 Mpa)
Reinforced pins near connection points
Increased hole Diameter to 0.7”
Modified rib thickness to
correct values
Extended pins through the ribs and attached them to the outer shell
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
28
Nuclear heating and thermal effects Vacuum vessel is subject to two basic heat loads:
Direct nuclear heating from neutrons and gammas Heating by conduction from first wall tiles (which in turn are heated by direct nuclear
heating and surface heat flux)
A range of operating scenarios is possible, but the baseline cases for analysis assume: 150 MW fusion power 100 W/cm^2 surface heat load assumed on first wall,
45 W/cm^2 is current baseline (H-mode) > 45 W/cm^2 for AT modes
pulse length of 20 seconds (H-mode - 10T, 7.7 MA) Pulse length of 40-ish seconds (AT mode - 6.5T, 5 MA)
Vessel is cooled by water Flowing in copper first wall cladding Flowing between walls of double wall structure
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
29
Heat loads on vessel and FEA model
Fusion power of 150 MW Surface heat flux is variable, 0, 50,100, and 150 W/cm2 analyzed
D C B
Tile, (36 mm)
Cu cladding
Double wall Vac Vessel
A
IB OBBe PFC 20.7 22.1Cu Tiles 29.1 28.7Gasket 25.2 25.2Cooled Cu Vessel Cladding
24.9 24.9
H2O FWCoolant 17.1 19.2SS Inner VV Wall 21.0 19.2
SS VV Filler 20.4 17.7H2O VV Coolant 9.2 9.6SS Outer VV Wall 18.8 0.0
Volumetric heating in FIRE components - new
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
30
2-D temp distr (100W/cm2 surface flux)
Inboard midplane Outboard midplane
20
s p
uls
e4
0 s
pu
lse
377 C
619 C622 C
383 C
Be limit ~ 600C
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
31
Peak Be temp vs heat flux, pulse length
Be limit
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
32
Nuclear heating distribution*
* Ref M. Sawan
Neutron wall loading
Volumetric heating:
plasma side, ss coil side, ss divertor
1.0
1.5
1.7
1.2
1.9
2.2 MW/m^2
4.1 W/cc (behind divertor)
1.1
0.9
21.0 W/cc 19.2 W/cc18.8 W/cc 0.04 W/cc
11.1 W/cc
10.9 W/cc
0.02 W/cc
12.4 W/cc
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
33
Typical 3-D temp distribution in VV
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
34
VV thermal deformation and stress
High stress region localizedStress < 3xSm ( 56 ksi)
Typical Deformation
Peak Stress is in psi
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
35
Combined stresses, 40 s pulse
Nuclear heating, gravity, coolant pressure, vacuum
Max Stress = 23 ksi, < 3Sm (56ksi) Max Deflection = 0.041 in.
Stress is in psi
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
36
Combined stress, 10T, 7.7MA, 20 s pulse, with VDE is worst loading condition Nuclear heating, gravity, coolant pressure, vacuum, slow VDE
Stress is in psi
Stress is in psi
3xSm
Max Stress = 58 ksi, > 3Sm (56ksi), but very localized
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
37
Combined stress, 6.5T, 5 MA, 40 s pulse, with VDE – not as severe as high field case
Nuclear heating, gravity, coolant pressure, vacuum, slow VDE
Stress is in psi
Max Stress = 46 ksi, < 3Sm (56ksi), also very localized
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
38
Preliminary VV stress summary (1)
Normal, High field (10T, 7.7 MA), 20 s pulse operation – O.K.
Case # Load ConditionGeneral Stress (Mpa) [allowable
stress = 195 Mpa]
Local Peak Stress (Mpa) [allowable stress = 390 Mpa]
General Stress (Mpa) [allowable
stress = 195 Mpa]
Local Peak Stress (Mpa) [allowable stress = 390 Mpa]
1 Gravity (with internals) 16 25 28 50
2 Vacuum Load 7 12 10 19
3 Coolant Pressure (10 Mpa) 83 145 110 242
4 TF Ramp Loads, 10 T in 20 s 19 29 14 26
5 Thermal stress from nuclear heating
76 133 83 241
10 Combine 1,2,3 103 141 134 242
11 Combine 1,2,3,4 97 145 138 215
12 Combine 1,2,3,5 142 253 179 311
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
39
Preliminary VV stress summary (2)
High field (10T, 7.7 MA), 20 s pulse with VDE – a little high
Case # Load ConditionGeneral Stress (Mpa) [allowable
stress = 195 Mpa]
Local Peak Stress (Mpa) [allowable stress = 390 Mpa]
General Stress (Mpa) [allowable
stress = 195 Mpa]
Local Peak Stress (Mpa) [allowable stress = 390 Mpa]
6
Disruption Loads (10 T, 7.7 MA) due to Eddy Currents
Fast disruption forces (.622 sec)
138 260 145 379
7
Disruption Loads (10 T, 7.7 MA) due to Eddy Currents
Slow disruption forces (.622 sec)
46 82 62 122
8Halo Loads in Vessel(Fast disruption load)
12 24 6 19
9Halo Loads in Vessel (Slow disruption load)
138 268 179 344
13Combine 1,2,3,6,8 [FAST, No Heating]
177 264 124 372
14 Combine 1,2,3,7,9 [SLOW, No Heating]
152 272 228 383
15Combine 1,2,3,5,6,8 [FAST, with heating]
160 239 222 434
16 Combine 1,2,3,5,7,9 [SLOW, with heating]
159 259 193 403
Torus Port regions
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
40
Preliminary VV stress summary (3)
Normal, Low field (6.5T, 5 MA), 40 s pulse operation – O.K.
Case # Load ConditionGeneral Stress (Mpa) [allowable
stress = 195 Mpa]
Local Peak Stress (Mpa) [allowable stress = 390 Mpa]
General Stress (Mpa) [allowable
stress = 195 Mpa]
Local Peak Stress (Mpa) [allowable stress = 390 Mpa]
1 Gravity (with internals) 16 25 28 50
2 Vacuum Load 7 12 10 19
3 Coolant Pressure (10 Mpa) 83 145 110 242
10 Combine 1,2,3 103 141 134 242
17 TF ramp loads, 6.5T, 20s 7 12 4 11
18 Thermal Stress from nuclear heating
117 194 159 273
23 Combine 1,2,3,17 97 144 131 188
24 Combine 1,2,3,18 119 212 138 242
Torus Ports
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
41
Preliminary VV stress summary (4)
Low field (6.5T, 5 MA), 40 s pulse with VDE – O.K.
Case # Load ConditionGeneral Stress (Mpa) [allowable
stress = 195 Mpa]
Local Peak Stress (Mpa) [allowable stress = 390 Mpa]
General Stress (Mpa) [allowable
stress = 195 Mpa]
Local Peak Stress (Mpa) [allowable stress = 390 Mpa]
19
Disruption Loads (6.5 T, 5 MA) due to Eddy Currents
Fast disruption forces (.633 sec) quench at .622 sec
52 109 41 188
20
Disruption Loads (6.5 T, 5 MA) due to Eddy Currents
Slow disruption forces (.622 sec)
19 34 23 51
21Halo Loads in Vessel (Fast disruption load)
9 27 6 19
22Halo Loads in Vessel (Slow disruption load)
69 104 77 144
25Combine 1,2,3,19,21
[FAST VDE, No Heating]110 146 159 234
26Combine 1,2,3,20,22
[SLOW VDE , No Heating]100 145 159 238
27Combine 1,2,3,18,19,21
[FAST VDE, With Heating]124 185 145 330
28 Combine 1,2,3,18,20,22 [SLOW VDE, with Heating]
141 200 172 320
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
42
Conclusions of vessel analysis
Can vessel achieve normal operation? YES
Can vessel achieve pulse length? YES 20 second pulse appears achievable 40 second pulse should be achievable but depends on surface heat
flux distribution and Be temperature
Can vessel take disruption loads? ITS CLOSE Some local stresses over limit, but local reinforcement is possible Additional load cases must be run
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
43
What analysis tasks are next?
Optimized geometry and refined FEA models Dynamic analysis with temporal distribution of VDE loads Fatigue analysis, including plastic effects Seismic analysis Plastic analysis Limit analysis
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
44
Longer term issues for FIRE
Refine design Develop design of generic port plug Optimize divertor attachments for stress, remote handling Design internal plumbing and shielding Re-design / optimize gravity supports
Perform needed R&D Select/verify method for bonding of copper cladding to vessel skin Select/verify method for routing of cooling passages into and out of
cladding Develop fabrication technique for in-wall active control coils Perform thermal and structural tests of prototype vessel wall, with
cladding, tubes, tiles, etc. (need test facility) Verify assembly welding of octants and tooling for remote
disassembly/reassembly (need test facility)
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
45
Remote Handling Overview
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
46
Remote Handling*
Maintenance Approach & Component Classification
In-Vessel Transporter
Component Replacement Time Estimates
Balance of RH Equipment
*ref T. Burgess
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
47
Remote Maintenance Approach
Hands-on maintenance employed to the fullest extent possible. Activation levels outside vacuum vessel are low enough to permit hands-on maintenance.
In-vessel components removed as integral assemblies and transferred to the hot cell for repair or processing as waste.
In-vessel contamination contained by sealed transfer casks that dock to the VV ports.
Midplane ports provide access to divertor, FW and limiter modules. Port mounted systems (heating and diagnostics) are housed in a shielded assembly that is removed at the port interface.
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
48
Remote Maintenance Approach (2)
Upper and lower auxiliary ports house diagnostic and cryopump assemblies that are also removable at the port interface.
Remote operations begin with disassembly of port assembly closure plate.
During extended in-vessel operations (e.g., divertor changeout), a shielded enclosure is installed at the open midplane port to allow human access to the ex-vessel region.
Remote maintenance drives in-vessel component design and interfaces. Components are given a classification and preliminary requirements are being accommodated in the layout of facilities and the site.
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
49
Remote Handling,Classification of Components
* Activation levels acceptable for hands-on maintenance
Class 1 Class 2 Class 3 Class 4*
Divertor Modules Limiter Modules Midplane Port Assemblies - RF heating- diagnostics
First Wall Modules Upper and Lower Horiz. Auxiliary Port Assemblies - cryopumps- diagnostics
Vacuum Vessel Sector with TF Coil Passive Plates In-Vessel Cooling Pipes - divertor pipes- limiter pipes
Toroidal Field Coil Poloidal Field Coil Central Solenoid Magnet Structure
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
50
Mi
Transfer Cask
Articulated Boom
Boom End -Effector Midplane Port Assembly
In-Vessel Remote Handling Transporter
Cantilevered Articulated Boom (± 45° coverage)
Complete in-vessel coverage from 4 midplane ports.
Local repair from any midplane port.
Handles divertor, FW modules, limiter (with component specific end-effector).
Transfer cask docks and seals to VV port and hot cell interfaces to prevent spread of contamination.
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
51
VV to Cryostat seal
VV port flange
Midplane port plug
Connecting plate
Cryostat panel
Port plug designed for RH Plug uses ITER-style connection to vessel, accommodates transfer cask
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
52
In-Vessel Remote Handling (2)
Divertor and baffle handled as one unit
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
53
Six (6) positioning degrees of freedom provided by boom (2 DOF) and end-effector (4 DOF)
Module weight = 800 kg
Divertor Handling End-Effector
Transport position Installation position
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
54
Component Maintenance Frequency and Time Estimates
* Includes active remote maintenance time only. Actual machine shutdown period will be longer by ~ > 1 month.** Based on single divertor module replacement time estimate.† Based on midplane port replacement time estimate.
Component or Operation RH Class Expected Frequency Maintenance Time Estimate*
Divertor Modules
1
TBD replacements
> 2
One module: 3.3 weeks
Limiter Modules All (32) modules: 5.9 months
Midplane Port Assemblies One module: 3.3 weeks
In-vessel InspectionFrequent deployment
Bank (5?) modules: 3.5 weeks
FW Modules
2TBD replacements
≤ 2
One module: 3.3 weeks**
Combined FW and Divertor Modules All (#TBD) modules: TBD
Auxiliary Port Assemblies † 12 month time target
Vacuum Vessel Sector with TF Coil
3Replacement not
expectedTBD, replacement must be possible and would require extended shutdown
Passive Plates
In-Vessel Cooling Pipes
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
55
Remote Handling Equipment Summary In-Vessel Component Handling System
In-vessel transporter (boom), viewing system and end-effectors (3) for: divertor module, first wall / limiter module and general purpose manipulator
In-Vessel Inspection System Vacuum compatible metrology and viewing system probes for inspecting
PFC alignment, and erosion or general viewing of condition One of each probe type (metrology and viewing) initially procured
Port-Mounted Component Handling Systems Port assembly transporters (2) with viewing system and dexterous
manipulator for handling port attachment and vacuum lip-seal tools Includes midplane and auxiliary port handling systems
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
56
Remote Handling Equipment Summary (2)
Component & Equipment Containment and Transfer Devices Cask containment enclosures (3) for IVT, midplane and auxiliary port Double seal doors in casks with docking interfaces at ports and hot cell interfaces Cask transport (overhead crane or air cushion vehicles TBD) and support systems Portable shielded enclosure (1) for midplane port extended opening
Remote Tooling Laser based cutting, welding and inspection (leak detection) tools for:
vacuum lip-seal at vessel port assemblies (2 sets) divertor and limiter coolant pipes (2 sets)
Fastener torquing and runner tools (2 sets)
Fire Site Mock-Up Prototype remote handling systems used for developing designs are ultimately used at
FIRE site to test equipment modifications, procedures and train operators Consists of prototypes of all major remote handling systems and component mock-ups
(provided by component design WBS)
31 March 2004 FIRE Physics Validation Review: Vacuum Vessel and Remote Handling
57
Some generic issues for ITER/FIRE
Develop ASME code for Fusion (Section III, Division 4) to avoid force fitting designs to Section III
Develop remote, in-vessel inspection systems leak detection metrology Detection of incipient failure modes, like cracks
Create a qualification / test facility for in-vessel and in-port components to quantify and improve RAM Thermal environment Vacuum environment Mechanical loading, shock, fatigue Remote handling capability