“Erosion to Deposition” - JICA - 国際協力機構 Erosion to Deposition”...
Transcript of “Erosion to Deposition” - JICA - 国際協力機構 Erosion to Deposition”...
“Erosion to Deposition”Tractive force reduction
1) Bamboo dragons for depth reduction2) Single groyne and bamboo basket3) Multiple groynes for roughness installation
1Ibo River, Japan
Presentation 3 24 March 2014 Dr. Matsuki Hirotada: JICA Expert for Disaster Risk Reduction
How to make the riverbank stable against erosion?
Thalweg shifts downward and outward due to tractive force.
If the tractive force gets smaller, the thalweg shifts less.
Spiraling flow and thalweg shift
2
Theory 1
Tractive force reduction
Tractive force develops by the weight of water in the direction of the flow.
τ = ρ x g x H x S
τ : tractive forceg : gravity acceleration
H : water depthS : bed slope
v = 1/n x R2/3 x I1/2
v : flow velocityn : roughness coefficient
R : hydraulic radiusI : energy gradient
To reduce tractive force,increase roughness.
3
To reduce tractive force,decrease water depth.
Theory 2
River facilities must be safe and also
easy-to-maintain within the lowest cost.
River maintenance
= combination of flow control and dyke protection
= groyne+ foot protection + foundation + slope protection
4
Flow control and bank protection
Total planning
1) Bamboo dragons for depth reduction
Ta Trach River/ Kim Ngoc, Hue, Vietnamin JICA project for disaster resiliency (phase-I), 2009
1) Bamboo dragons for depth reduction
Ta Trach River/ Kim Ngoc, Hue, Vietnamin JICA project for disaster resiliency (phase-I), 2009
55
Bamboo dragons were set under the water.
The cost was 10,000,000JPN for 210m (520USD/m)
That keeps water depth shallower during floodso that tractive force doesn’t get larger.
Tributary
Stream
Eroded slope
Existing Bank Protection Works(stone placing)
Flow direction
Community RoadResidential area of Kim Ngoc Ward (120 households)
Ferry service
Flow direction
Kim Ngoc Ward in Hue (2009)
6
Tributary
Stream
Riverbak Protection Works
Existing Bank Protection Works(stone placing)
Flow direction
Community Road
Residential area of Kim Ngoc Ward (120 households)
Ferry service
Flow direction
(1)
(2)
(1) Slope Protection Works with Bamboo Stone Box (total length : 250m )
(2) Foot Protection Works by Bamboo Stone Gabion or Stone Riprap
Kim Ngoc Ward in Hue (design)
7
mainly by slope protection with bamboo stone box and gabion
Bamboo Stone Box
( 2m wide * 2m long * 1m deep stone size max 20cm)
Bamboo Stone Gabion (stone size max 20cm)
(Length ? : Depeding of cross section)
Bamboo Pile
(diameter 10- 12cm, 2- 2.5m long ?)
Weave (connected) bamboo piles with
bamboo outer skin
Lowest water level
Stone Placing
Sodding or other vegetations (willow, Malaysia grass, etc)
TS40 to 50 (matt)
Community Road
1:2
Bamboo Planting
Bamboo Gabion Net (diameter 0.6 m, mesh interval of
mbamboo outer skin 10cm)
Length ?
Diameter 0.6m ?
TS40 to 50 (matt)
Kim Ngoc Ward in Hue (design for shallow river)
8
9
Kim Ngoc Ward in Hue (2009)
9Eroding bank
10
Bamboo dragon for foot protection
Kim Ngoc Ward in Hue (2010)
10
11
Kim Ngoc Ward in Hue (2010)
11After completion
12
Kim Ngoc Ward in Hue (2012)
12After 2 years
Kim Ngoc Ward in Hue (2014)
13After 4 years
Kim Ngoc Ward in Hue (2014)
14Sedimentation for plants
Kim Ngoc Ward in Hue (2014)
15Nature-friendly riverbank
Recommendation! Generate BAMBOO DRAGON using pig container art
16
Bamboo dragon (in a museum)
Bamboo snake (in Kim Ngoc)
2) Single groyne and bamboo basket
Thu Bon River/ Thanh Xuyen, Quang Nam, Vietnamin JICA project for disaster resiliency (phase-I), 2009
2) Single groyne and bamboo basket
Thu Bon River/ Thanh Xuyen, Quang Nam, Vietnamin JICA project for disaster resiliency (phase-I), 2009
1717
A masonry groyne was installed to block direct flow attack.Bamboo baskets were sunk behind design thalweg line.
Timber fences were set to reduce flow velocity.
The cost was 10,000,000JPN for 270m (400USD/m)
These facilities keeps riverbed shallow and reduces water velocityto get sediment which covered the eroded bank.
Thanh Xuyen Ward in Quang Nam (2009)
18Eroding bank
Thanh Xuyen Ward in Quang Nam (2009)
19Bamboo fence (working as an attracting groyne)
Thanh Xuyen Ward in Quang Nam (2009)
20Rock outcrop (can be a guide groyne)
Sand bar
Sand bar Flow direction
Natural stone groin (existing)
Bamboo groin (existing)(sand bar length by spur dyke : 50 m in long Eroded slope
Flow direction
Community road
Residential area of Thanh Xuen Ward (250 households)
Rock (existing)Rock(existing)
Stream (existing)
(rebound water flow direction)
Thanh Xuyen Ward in Quang Nam (2009)
21
……. ………. ………. …..………. …. ………
……….
………. …
....
Sand bar
Sand bar
Flow direction
Natural ? stone groin(existing)
Bamboo groin (existing)(sand bar length by spur dyke : 50 m in long Eroded slope
Flow direction
Community roadResidential area of Thanh Xuen Ward (250 households)
Rock(existing)
Rock(existing)
(1) Stone Groin (total length : 20m )
(2) Bamboo Stone Box(1m wide*1m long* 1m deep)
(3) Bamboo Groin (18m long* 5 sets with 50m internal)
(4) Bamboo Stone Gabion (1.5 m diameter* 1m high)
(5) Slope Protection (leveling and sodding, site works mainly by community people)
(1)
(2)
(3)
(4)
(5)
(rebound water flow direction)
Thanh Xuyen Ward in Quang Nam (design)
22
Top Width3m
Height4 or 5 m ?
Slope Gradient1:1.0 or 1:1.5
Bottom Width13 m or 18 m ?
Slope Gradient 1:20
Slope Gradient 1:1.0 or 1.5
Stone groin
Stone size: 20 - 40 cm ?
Community people: access to the top of groin(for monitoring of dyke condition after construction of stone groin)
Upstream and downstream of dyke: Planting of bamboo
(1) Stone Groin (Total Length : 20m): Image Plan
Direct angle(90 degree)
Lowest water level
Depth 2.0- 2.5 m ?
Height 2.0- 2.5 m ?
1. Surface above low water level is filled up by concrete?
Downstream View
Groin length 20m
Foundation of groin ?see below points
Points to be reconsidered Foundation of groin: can be replaced by gravel bag (not only sand, material of bag ?)
23
(4) Bamboo Stone Gabion : Image Plan
Bamboo Stone Gabion
Diameter: 1.5m
Height 1.0m
Prefablication of bamboo gabion net : It is simple net. Can be purchased at market.However, this gabion net can be prefablicated by community people.(strongly desired in view of livelihood improvement)
Lowest water level
Beacon sign
Stone size 10- 20 cm
Downstream View
Points to be reconsidered
Bamboo gabion in the first layer in the above Figure :
Gabion net : can be replaced by wire netStone to be filled in the net: can be replaced by gravel (not only sand) Material of bag ???
24
Thanh Xuyen Ward in Quang Nam (2010)
25After completion
Thanh Xuyen Ward in Quang Nam (2010)
26After completion
Thanh Xuyen Ward in Quang Nam (2014)
27After 4 years
Thanh Xuyen Ward in Quang Nam (2014)
28After 4 years (over 1m of sedimentation)
3) Multiple groynes for roughness installation
Mekong River/ Ban Tonpheung, Bokeo, Laos since 1998
3) Multiple groynes for roughness installation
Mekong River/ Ban Tonpheung, Bokeo, Laos since 1998
2929
A series of groynes were installed in 7 years.These had impermeable masonry and permeable vegetation.
The cost was 4,178,000,000Kip for 2km (237USD/m)
Groynes on the riverbank works as roughnessto turn off the thalweg and to get sediment.
Sediment comes in flood seasons and protects riverbank in dray seasons.
Mekong groynes at Ban Tonpheung
Mekong groyne project started in1998 at Ban Tonpheung, Laos.
30
Mekong groynes at Ban Tonpheung
Eroded (left) riverbank was anaked cliff of 10-meters heightwith no vegetation before 1998.On the opposite (right) side, finesand was deposited thickly.
31
Riverbank erosion before 1998
Chiang Saen
Ban Tonpheung
1km
THAI LAO
Mekong groynes at Ban Tonpheung
32
b) Dried-up cliff slides down after heavy rain fall.
High water level
a) Strong shear force leaves a sheer cliff under the water.
Fluctuation
5m
10m
Low water level
c) Collapsed soil are moved away by flow year by year.
Mekong groynes at Ban Tonpheung
Cyclic erosion in monsoon fluctuation
a) Cliff formation under the waterAt a concave bank of a river bend,
spiraling flow washes both riverbank andriverbed. Especially in high-waterseasons, strong shear force removes smallparticles away. After repeating high-water, Mekong finally leaves a sheer 10-meterm cliff of undisturbed diluvial layersunder the water.
b) Cliff emergence and circular slipIn the next low-water season, arid air
dries up the cliff to keep its stability. Inthe end of the season, however, heavyrain seeps into the cliff top and suddenlyupsets the gravity balance to causecircular slips. The bank shoulder lineretreats and collapsed soil clump supportsstability of the bank.
c) Collapsed soil to be swept awayThe collapsed soil under water is easy
to be swept away. Spiraling flow incoming high-water seasons sweeps it littleby little. In several years at 5-meter set-back position, a 10-meter cliff will standagain.
33
Mekong groynes at Ban Tonpheung
Design parameters (masonry)
Rock size: over 20 cm diameterReferring an empirically-derived formula6)
to keep still in 3.0 m/s flow. Same withexisting concrete blocks and 4 times largerthan riverbed gravels.
Length: 40 mFor dry-work workability in the low waterseason. Equivalent to one-tenth of the riverwidth.
Height: 6mHalf of the cliff heights to be submergedduring the high water season.
Crest width: 3mTo plant willows on clogged masonries.
Slope: 1:3 and 1:1.5Imitation of stable natural riverbank of 1:3for the tip/downstream side. Half of it for theupper.
Spacing: 100 m2.5 times longer than the masonry length tocover the 3km early. Predetermining anadditional short groyne for another collapsebetween groynes.
Work sequence: downstream firstTo prevent scouring due to diffraction flow.
Inspection and rehabilitation: every yearTo repair quickly for smaller damage.
34
Groyne to welcome sand sedimentation form fluctuating Mekong river
(impermeable masonry with permeable vegetation)
Mekong groynes at Ban Tonpheung
1st groyne (May 1998) 4 groynes (February 1999)
352.5 groynes (October 1998) 4 groynes (April 2000)
No.12
No.10
No.7
No.11
No.8
No.20
No.3
No.9
No.6
No.4
No.5
No.18
No.17
No.16
No.14
No.13
No.19No.1
No.15
No.2
Gro
yne
fiel
d (2
km)
(ALOS satellite image by JAXA on 26 February 2010)
Mekong groynes at Ban Tonpheung
36
Mekong groynes at Ban Tonpheung
The 1st groyne has beennaturally covered by Kok Khaiand tall trees, which make flowslower and slower.
37
Mekong groynes at Ban Tonpheung
Groynes are trapping sedimentbetween them and also workingas a jetty.
38
Mekong groynes at Ban Tonpheung
Riverbank keeps stability due tosedimentation and growingplants are making themsustainable.
39
Total cost was 474,522 USD for 20 groynes and the groynes had 100-meters interval, which means initial cost was 237 USD per meter.And it is almost free for maintenance and rehabilitation.
Year Number Cost in Lao Kip Equivalent in USD
1998-1999 3 540,000,000 75,949
1999-2000 1 338,000,000 47,539
2000-2001 2 600,000,000 63,830
2001-2002 4 800,000,000 85,106
2002-2003 4 700,000,000 74,468
2003-2004 4 800,000,000 85,106
2004-2005 2 400,000,000 42,253
total 20 4,178,000,000 474,552
Mekong groynes at Ban Tonpheung
40
(Data source: Muraoka, former JICA Expert for Lao)
Mekong groynes at Ban Tonpheung
41Eroding bank in February 1998
Mekong groynes at Ban Tonpheung
42Eroding bank in February 1998
Mekong groynes at Ban Tonpheung
43The first groyne in February 2014
Mekong groynes at Ban Tonpheung
44Stable bank in February 2014