Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow Control Device Based on SPE 180037. Martin Halvorsen et al. Bergen 2016

Transcript of Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow Control Device · PDF...

Page 1: Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow Control Device · PDF file · 2017-10-11Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow

Enhanced Oil Recovery On Troll Field By

Implementing Autonomous Inflow Control Device

Based on SPE 180037. Martin Halvorsen et al. Bergen 2016

Page 2: Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow Control Device · PDF file · 2017-10-11Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow

Slide 2

Troll oil field –

• Thin oil column

• Huge gas cap

• Subsea wells

• Long horizontal wells

• Multilateral wells

• Inflow control devices

• Downhole monitoring and

control

• Gas coning/contact movement

SPE 180037 • Enhanced Oil Recovery On Troll By Implementing AICD • Martin Halvorsen

Introduction

Page 3: Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow Control Device · PDF file · 2017-10-11Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow

SPE 180037 • Enhanced Oil Recovery On Troll By Implementing AICD • Martin HalvorsenSlide 3

Well placement

Page 4: Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow Control Device · PDF file · 2017-10-11Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow

Slide 4

Control:

• Inflow control devices

(AICD - Autonomous Inflow Control Device)

• Branch control

Monitoring

• P/T gauges

Zone isolation

• Swellable packers

SPE 180037 • Enhanced Oil Recovery On Troll By Implementing AICD • Martin Halvorsen

Completion design

Page 5: Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow Control Device · PDF file · 2017-10-11Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow

Slide 5

The ‘levitating disc’ AICD

Fmom Flift Fdrag

Fmom + Flift + Fdrag = 0

Oil

Gas

Oil

Water

Page 6: Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow Control Device · PDF file · 2017-10-11Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow

AICD function from experimental tests

Page 7: Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow Control Device · PDF file · 2017-10-11Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow

Slide 7

Nozzle

Disk

Body

SPE 180037 • Enhanced Oil Recovery On Troll By Implementing AICD • Martin Halvorsen

Technology advancements

Page 8: Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow Control Device · PDF file · 2017-10-11Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow

AICD Implementation on Troll

0

5

10

15

20

25

30

2008 2009 2010 2011 2012 2013 2014 2015 2016

Nu

mb

er o

f La

tera

lsAICD Implementation at Troll

Original Design Improved Design

Page 9: Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow Control Device · PDF file · 2017-10-11Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow

Slide 9 SPE 180037 • Enhanced Oil Recovery On Troll By Implementing AICD • Martin Halvorsen

Reservoir simulations

Page 10: Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow Control Device · PDF file · 2017-10-11Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow

Slide 10

10 mths (SPE159634)

SPE 180037 • Enhanced Oil Recovery On Troll By Implementing AICD • Martin Halvorsen

Strong results

2 years

Page 11: Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow Control Device · PDF file · 2017-10-11Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow

• The AICD technology has been implemented successfully at the Troll Oil Field

(75 laterals)

Success Criteria

− no associated problems during completion, startup or production,

− no negative effect on production

− a favourable GOR development and cumulative oil production.

• The AICD wells are producing better than expected and have contributed to

an increased oil production at Troll.

Slide 11 SPE 180037 • Enhanced Oil Recovery On Troll By Implementing AICD • Martin Halvorsen

Conclusion

Page 12: Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow Control Device · PDF file · 2017-10-11Enhanced Oil Recovery On Troll Field By Implementing Autonomous Inflow

Any Questions?

Tendeka combines field proven production technologies to measurably improve how today’s completions perform.