Chap 4 Sch&Plmin

download Chap 4 Sch&Plmin

of 18

Transcript of Chap 4 Sch&Plmin

  • 7/29/2019 Chap 4 Sch&Plmin

    1/18

    Chapter - IV Scheduling and Planning

  • 7/29/2019 Chap 4 Sch&Plmin

    2/18

    Introduction

    The Construction time management is the backbone of construction industry as it governs

    directly or indirectly the elements involved in the project. As discussed in the earlier chapter, the construction

    cost, quality and other related elements gets affected with the delay in construction project. This shows the

    vulnerability of construction project due to improper construction time management.

    Construction Time management is basically scheduling and planning the constructionprocesses, activities in a logical sequence in accordance to the available resources and project objectives. The

    terms Planning and Scheduling do appear as synonyms in general, but they are different in the context of

    construction time management. These terms and the scheduling methods will be dealt in this and the further

    chapters.

    Scheduling and Project Planning

    Scheduling and planning are two terms that are often thought to be synonymous. But theyare not. Scheduling is actually a part of planning in construction Project. The term Planning is used in different

    fields under different contexts. In case of construction industry and construction projects Planning a project

    means

    " the process of choosing the one method and order of work to be adopted for a

    construction project from all the various ways and sequences in which it could be done "

    The PMI (Project management institute) defines the project Planning process in the

    PMBOK as " those processes performed to establish the total scope of the effort, define and refine the

    objectives, and develop the course of action required to attain Project objectives ". Project planning serves as afoundation for several related functions, such as cost estimating, scheduling, project control, safety management

    and others that enhances the construction project.

    There are various key terms and various elements that are to be understood before

    understanding project scheduling and planning. The descriptions of a few key terms and elements of a schedule

    are given below in order.

    Deadline : a specific point in time, such as the day on which part of a project must be completed. For example,

    the deadline of excavation activity of the construction project means that the excavation part should

    be completed at any cost by the end of the specified day in the schedule.

    Period : it is the time span taken for ant certain activity or process for its completion. For example, the time

    period of 14 days for centering means that the centering activity takes 14 days to be completed.

    Tasks : these are the very foundation of the schedule and refer to self - contained work units. For example,

    tiling the ground floor is a task. And when several tasks are combined then the result is a Summary

    task. Example, tiling and plastering)

  • 7/29/2019 Chap 4 Sch&Plmin

    3/18

    Task Duration & Duration planning : it is the time needed to complete a task. The calculation of duration is

    referred to as Duration Planning.

    Sequence Planning : the construction project consists of various activities which are formed under the WBS of

    Project. These activities are to be linked logically in certain order so as to create a proper

    and efficient schedule for the project. This process of establishing the dependencies

    between activities is referred to as Sequence Planning.

    Fig.4.2 : Duration Planning and Sequence Planning

    Construction Scheduling

    The duration of the activities and the sequence planning of them when taken together

    form the basis of Construction Scheduling. Scheduling is the determination of the Timing and sequence of

    operations in a project and their assembly to give the overall completion time of the project. As mentioned

    earlier Scheduling focuses on one part of Planning effort.

    The difference between project planning and scheduling can be understood from the

    figure below. Project planning actually deals with the overall activities relating to the project. The selection of

    contractors, where, when, how, by whom, at what cost etc. these all will be answered by the project planning

    process. The Scheduling part deals with the "when" part in detailed level.

    Fig. 4.3 : Construction project Scheduling

  • 7/29/2019 Chap 4 Sch&Plmin

    4/18

    Fig. 4.4 : The relation between Construction Project Planning and Scheduling

    Milestone

    A milestone is a task without any duration. It is a special event entered separately into the

    schedule. Typical scheduling milestones include the start of construction, completion of the building structure,

    sealing the building envelope, final inspection and putting the building into operation.

    Sequential dependencies

    In most cases, tasks are not isolated items on the schedule but are integrated into a web of

    dependencies with other tasks. There can be several reasons for this. The normal case is a Sequential

    dependency. Task B can begin only when task A is finished i.e. for e.g. ground floor walls ground floor

    ceiling upper floor walls.

    Some tasks can only be performed jointly in a parallel process e.g. setting up scaffolding

    floor by floor as the structure of a multistory building goes up. Often these process dependencies can be broken

    into sequential dependencies by using a higher level of detail. It is often impossible for contractors to work in

    parallel during a number of construction phases where one activity (task) interferes with another. This is why it

    is essential for planners to examine mutual dependencies between specialized tasks and, if necessary, to divide

    the project into optimal construction phases.

    Various types of relationships play an important role in the graphic representation of

    dependencies between two tasks. Construction scheduling distinguishes between four types :

    Finis-to-start : Task B can only start after task A is finished. This is the most common type of relationship and

    may apply to activities such as the construction of interior walls (A) and interior plastering (B).

  • 7/29/2019 Chap 4 Sch&Plmin

    5/18

    Finish-to-finish : Task A an task B must be completed by the same time. This type of relationship exists when

    tasks A and B provide the foundation for an additional task. Examples are installing windows (A) and sealing

    the roof (B), which create the airtight building envelope necessary for interior work.

    Start-to-Finish : Task B must end when task A begins. In this type of relationship, one task can be scheduled at

    the least possible point in time before it interferes with another task.

    Start -to-start : Task A and task B must start at the same time. This makes sense if the work can be performedin parallel - if, for instance, workers from one trade can use a crane that is operated by another contractor to

    deliver large building elements.

    Fig. 4.5 : Different types of Relationships between activities.

    Forms of Representation

    There are different ways to represent a schedule graphically. The following forms of

    representation are used to communicate schedule contents in a clear and useful manner, depending on the goal

    and purpose of the Schedule.

  • 7/29/2019 Chap 4 Sch&Plmin

    6/18

  • 7/29/2019 Chap 4 Sch&Plmin

    7/18

    Scheduling is the determination of the timing and sequence of operations in the

    project and their assembly to give the overall completion time. As mentioned

    previously, scheduling focuses on one part of the planning effort.

    Project planning answers the questions What is going to be done? How? Where?

    By

    whom? and When (in general terms, the projects start and end)? Scheduling deals

    with

    when on a detailed level.

    In fact, scholars have generally separated planning from scheduling CPM

    separates

    planning and scheduling, and once project information is collected and expressed

    as a network plan and activity time estimates assigned, CPM calculations can be

    made.

    Planning ceases and scheduling starts when the first computation is performed that

    shows a project duration. The project duration is then compared with the desired

    schedule and scheduling begins. (OBrien and Plotnick, 2009, p. 417)

    To get an idea about the relationship between project planning and scheduling,

  • 7/29/2019 Chap 4 Sch&Plmin

    8/18

    assume that you are planning a family vacation project for next summer. Your

    plan

    may include considerations such as these:

  • 7/29/2019 Chap 4 Sch&Plmin

    9/18

  • 7/29/2019 Chap 4 Sch&Plmin

    10/18

  • 7/29/2019 Chap 4 Sch&Plmin

    11/18

  • 7/29/2019 Chap 4 Sch&Plmin

    12/18

  • 7/29/2019 Chap 4 Sch&Plmin

    13/18

  • 7/29/2019 Chap 4 Sch&Plmin

    14/18

  • 7/29/2019 Chap 4 Sch&Plmin

    15/18

  • 7/29/2019 Chap 4 Sch&Plmin

    16/18

  • 7/29/2019 Chap 4 Sch&Plmin

    17/18

  • 7/29/2019 Chap 4 Sch&Plmin

    18/18