Experiences from de Stroomversnelling
nZEB renovation of row housing
Mieke Oostra
professor Spatial Transformations Hanze University of Applied Sciences
• Introduc*on of de stroomversnelling • Why was de Stroomversnelling
developed • Before de Stroomversnelling • How it evolved • What is new • What is currently happening in rela*on
to housing associa*ons & private house owners
• What is s*ll needed to accelerate upscaling
CONTENTS
www.westonpain*ngcontractors.co.uk
The introduc*on to A Dutch retrofiCng programme
for row housing stroomversnelling huur
Dutch row housing
picture: de stroomversnelling
• a Dutch deal to accelerate deep
retrofiCng by 4 contractors and 6 housing associa*ons
• part of Energiesprong, an innova*on programme commissioned by the Dutch Ministry of the Interior
• signed on the 20th of June 2013 • to convert 11.000 houses to Net Zero
Energy Buildings
GOALS • 10 year warranty on energy performance • retrofit within a week • costs of living remain the same for occupant • aUrac*ve for occupants
picture: de stroomversnelling
ROOF
FACADE
NEW KITCHEN, BATHROOM & TOILET
INSTALATIONS
INSULATION (GROUND FLOOR)
picture: de stroomversnelling
How are these realised?
picture: de stroomversnelling
pilot Schrijverswijk Heerhugowaard
picture: de stroomversnelling
pilot Schrijverswijk Heerhugowaard
hUps://www.youtube.com/watch?v=5Do2IMB8xQs
Melick
hUps://www.youtube.com/watch?v=BvXVVQZ_hso
Nieuw Buinen
hUp://www.roCnghuis.nl/nl/projecten/detail/testwoning-‐stroomversnelling-‐nieuw-‐buinen
pilot 2.1 Nieuw Buinen
source: hUps://m.youtube.com/watch?v=I3WBT2eAArI
Challenge 1 -‐ a 20% reduc*on of CO2 emissions and 14% renewable energy genera*on in 2020. An enormous challenge Challenge 2 -‐ more commercial ini*a*ves, a reduc*on of government and reduc*on of governmental spending. How to combine these two challenges? The ingredients are: leave more to the market, coopera*on between companies & knowledge ins*tutes and a green deal with partners.
WHY
www.unitedisaan.com
Pilot projects as: • To proof new technology concepts • To test and present a renova*on concept • For dissemina*on purposes
BEFORE - one off pilot dwellings
Onshuisverdienthet.nl
• Step from building to area • Focus on retrofiCng, new
build and replacement of buildings
• Real change within 2 years. • For this GEN (Gebieden
Energie Neutraal) was ini*ated.
e.g. Valkenburg & Kerschoten
BEFORE – area’s
• Knowledge development vs realisa*on • Development of different themes (micro,
macro, finance, business models & area management) vs integral approach
• Lowest housing costs vs client oriented approach
• Proven technology vs technology of the future
• Top-‐down vs boUom-‐up ini*a*ves
BEFORE – area’s – some dilemma’s
• Short term results needed • Ten leading companies: Alliander, BAM,
Cofely GDF Suez, Eneco, Eversheds Faasen, KPMG, Rabobank, Royal Haskoning DHV, TNO, United Energy Works.
• Companies wan*ng change within 2 years. • Forma*on of GEN (Gebieden Energie
Neutraal). e.g. Valkenburg & Kerschoten
BEFORE – pilot projects for row housing
• Short term results needed • Ten leading companies: Alliander, BAM,
Cofely GDF Suez, Eneco, Eversheds Faasen, KPMG, Rabobank, Royal Haskoning DHV, TNO, United Energy Works.
• Companies wan*ng change within 2 years. • Forma*on of GEN (Gebieden Energie
Neutraal). e.g. Valkenburg & Kerschoten
BEFORE – LALOG
stroomversnelling huur
ONS HUIS VERDIENT HET
ONS HUIS VERDIENT HET
stroomversnelling koop
Foto: Riesjard Schropp
stroomversnelling koop
WHAT IS NEW?
• Directed at upscaling • Involving all stakeholders • Flexible • Step change innova*on • Not only technical innova*on
but also system innova*on e.g. energy performance fee
• New roles & responsibili*es for stakeholders
New about the programme
Blog.gemalto.com
Outcome: cost reduction
... time reduction & increased integration
picture: de stroomversnelling
…process innovation,
picture: de stroomversnelling
& supply chain management
picture: de stroomversnelling
One off pilot projects
www.stroomversnelling.nl/publica*e
Energy performance fee
WHAT’S NEXT?
deals in different regions: • Utrecht • Brabant • Overijssel & Gelderland • Groningen
Construction period
Row houses
Percentage of total
number (%) 1946 - 1964 480,000 7 1965 – 1974 606,000 9 1975 - 1991 879,000 12.9
Total 1,965,000 29
TO CREATE IMPACT
• The average energy consump*on per dwelling in the Netherlands in 1440 m3 natural gas and 3440 kWh of electricity (Nibud, 2015). 53 GJ per dwelling.
• RetrofiCng 10 % of housing stock to nZEB in 10 years (19,650 a year) will represent a saving of 1.04 PJ of fossil energy a year.
hUps://www.youtube.com/watch?v=pAAQBmsGmDE&list=PLxqrMoxgE53ndDAFqpEb9h9tbLuB3MD7c&index=2
One off pilot projects
www.unitedisaan.com
www.unitedisaan.com
Thank you for your kind aUen*on [email protected]