Boukhalfa Yaïci

download Boukhalfa Yaïci

of 18

Transcript of Boukhalfa Yaïci

  • 8/22/2019 Boukhalfa Yaci

    1/18

    1

    Boukhalfa Yaci

    Keynote update Algeria:

    Transitioning from Fossil fuels to

    Renewable Energies

    Solar MaghrebRabat, 22 & 23 May 2013

  • 8/22/2019 Boukhalfa Yaci

    2/18

    2

    Introduction Our Company

    Brief description of the Algerian Renewable

    Energies Program Current situation

    Conclusions

    Agenda

  • 8/22/2019 Boukhalfa Yaci

    3/18

    3

    Introduction

    As an exporter of oil and gas with limited resources to cover local need

    and to support export contracts for years and years, Algeria has decided

    to develop renewable energies as a strategic approach,

    Electricity demand is increasing at a high rate mainly pushed by

    domestic air conditioners during summer and agricultural sector,Part of revenues provided by exported fossils resources will serve to

    develop and execute a program revealed in February 2011 with the aim

    to install 22 GW of electricity by 2030 (12 GW to cover local needs and

    10 GW as an export option)

    RE Industrial development is a key point of this program.

  • 8/22/2019 Boukhalfa Yaci

    4/18

    4

    Brief overview ofEnR Engineering Services:

    Services offered

    Compagnies

    Consulting

    Engineering

    TrainingMarket analysis

    B2B relationship

    Industrial projects

    Solar PV plants

    Off-grid systemsSpecific studies

    Engineers

    Installers

  • 8/22/2019 Boukhalfa Yaci

    5/18

    5

    Brief overview ofEnR Engineering Services

    RE Project expertise

    Feasiblystudies

    Siteassessment

    Administrativeprocess

    EngineeringEconomic &

    financialassessment

    We constructed a

    site ranking

    model

    considering

    multiple criteria

    (solar radiation,

    surfaces

    available,distance to the

    grid, etc.)

    We studied

    required

    documentation

    and duration

    process to fulfill

    local and centralregulations

    We develop a

    step by step

    process to study

    and execute a

    project

    We develop a

    business model

    based on a local

    financing process

    As a first step

    before to invest,

    we estimate

    performance and

    cost of a project

  • 8/22/2019 Boukhalfa Yaci

    6/18

    6

    The Algerian Renewable Energy and Energy Efficiency

    Program (2011 2030)

    12,000 MW by 2030

    CSP plants: 60% focusing on tower + storage.

    PV solar farm: 24 % using crystalline technology.

    Wind farm: 16 % of the total

  • 8/22/2019 Boukhalfa Yaci

    7/18

    7

    Financial and investment support

    A derogatory scheme:Exemption during 3 years (realization period) and 10 years (exploitation period)

    All the wilayates of the South, some wilayates of the highlands and some

    municipalities of some wilayates of the highlands.

    Project of national interests (convention regim):

    Extension of periods exemption: 5 years (realization period) and 10 years(exploitation period)

    An investment code to offer advantage through three mechanisms

    A general scheme:Exemption for 1 to 3 years during construction: customs duties, VAT, property

    transfer tax, registration fees, etc.

    Exemption of tax on profits, tax on turn-over during 3 years which can be extended

    to 5 years in case of job creation

  • 8/22/2019 Boukhalfa Yaci

    8/18

    8

    Financial and investment support

    A renewable energy fund (1% of oil & gas fiscality) which:

    Contribute to finance projects producing electricity using RE and cogeneration plants, Subsidize equipments,

    cover the feed-in-tariff (tarif de rachat garanti),

    Stimulate other renewable energies (not producing electricity)

    Participate to set up new structures like laboratories (control and certification)

    Other aspects like studies, training, maintenance, etc.

    Investment funds (one at a national level and 48 at wilayate level) which:

    Participate at a level not more than 49%

    Limit their contribution to 30% of its one fund for each project

    Can provide risk capital, developing capital or restructuration of the capital

    RE projects are eligible to these investment funds

    Bank loans:

    Limited to 65 70% of a project

    Credit loan at a rate of 5,5% with a high level of bonus

    Mid-term maturity

  • 8/22/2019 Boukhalfa Yaci

    9/18

    9

    Dispatching of RE development process

    RenewableEnergy

    Program

    SonelgazHolding

    12,000 MW

    by 2030

    Private and/orPublicOperators

    ?

    Through a feed-in Tariff

    (to be implemented)

  • 8/22/2019 Boukhalfa Yaci

    10/18

    10

    F-i-T: Mechanism elected by CREG

    Source: CREG. Mcanismes dencouragement des EnR en algrie. ERA-EnviroAlgrie, Oran, 17 Oct. 2012

  • 8/22/2019 Boukhalfa Yaci

    11/18

    11

    An important change is necessary in local regulation

    2 decrees are in preparation (by CREG):

    1. Conditions to access to advantages related to diversification costs by:

    Removing the auction process (updating diversification costs decree)

    RE electricity producer will be submitted to standard regime and not special regime

    concerning grid-connexion to transport grid (>60 kV) or distribution grid (

  • 8/22/2019 Boukhalfa Yaci

    12/18

    12

    An important change is necessary in local regulation

    Technology

    Power (MW)

    RE Resources

    Solar PV, Solar CSP

    Wind

    Biomass

    Geothermal

    Cogeneration Plants

    Solar insolation (Hours)

    Wind (m/s)

    Due to the non availability of long-term resource data records, the feed-in-tariff could

    be subject to revision after a 5-year period.

  • 8/22/2019 Boukhalfa Yaci

    13/18

    13

    Existing or announcement of investments

    Player Value Chain Capacity Current situationRouiba Eclairage PV: from Si to Panel 140 MW/y Starting of production: mid 2014

    Extend of capacity is projected

    Condor PV: assembling solar panels 50 MW/y Starting of production: June 2013

    Aures Solar PV: assembling solar panels 20 MW/y A J/V company with foreign

    partner (49% /51%)Starting of production: by the end

    of 2013

    ALPV (Algerian

    PV Company)

    PV: assembling solar panels 12 MW/y Line in place since many months

    Private companies anticipate a development of a local market in solar PV technology.

  • 8/22/2019 Boukhalfa Yaci

    14/18

    14

    Actual status of the program

    Technology Capacity

    (MW)

    Type Remarks

    PV 1,1 Grid-connected Under construction

    Commissioning: Sept. 2013

    PV 3 Off-grid Disseminated over 13 wilayate

    Starting on Q4 2013 till Q2 2014

    Wind 10 Grid-connected Under construction

    Commissioning: Sept. 2013

    Technology Capacity

    (MW)

    Type of equipment Remarks

    PV modules 22 270 Wp Under tender bid process

    Inverters 22 500 kW To be relauched

    Transformers 71,5 650 kVA Awarded

    DC

    combiners

    Under tender bid process

    Period

    2011/201

    2

    SinceJ

    an

    .2013

  • 8/22/2019 Boukhalfa Yaci

    15/18

    15

    Development process of a PV project followed by Sonelgaz

    A modular Concept of a solar PV plant

    PV: 1 MWp Inverter: 2x 500 kW

    Transformer: 2x650 kW

    Separating Engineering, Procurement and Construction phases

    Engineering: CEEG awarded a contract to a Spanish engineering company(end 2012)

    Procurement of components: local tender process before to launchinternational tender process (in case of a failed first process)

    Construction: Local companies will be privileged

    Industrial Approach privileged

    Seek a partnership through important contract awarded

    Certification of products through a laboratory control

  • 8/22/2019 Boukhalfa Yaci

    16/18

    16

    Next steps

    Availability of FIT before this autumn as Sonelgaz will commission twoplants,

    Level of FIT will be probably the same as observed in other countries

    We expect a solar PV private market mainly oriented to farmers and

    industrials

    Probably , first projects will be available in 2014.

  • 8/22/2019 Boukhalfa Yaci

    17/18

    17

    Conclusions

    Algeria is facing a major dilemma: how to leave a fossil economy to a

    green economy fueled by revenue representing more than 96% ofexporting goods?

    An increase of energy consumption at a present rate is unsustainable,

    RE but also Energy Efficiency is considered as a necessary change in

    order to satisfy a requirement of environment and a better way toengage the country in a new era with the aim to satisfy local needs in

    electricity, exporting solar electricity instead of fossil fuels and

    developing local industry,

    A program with 22 GW of RE power is under development and a new

    local industry is emerging in solar photovoltaic

    An aggressive tariff could push heavily this tendency.

  • 8/22/2019 Boukhalfa Yaci

    18/18

    18

    Thank you for your attention!

    www.enrengineeringservices.com

    http://www.enrengineeringservices.com/http://www.enrengineeringservices.com/