Transcript of Avances De Obra Camino Real
159
16151408 09 10 11 12
Edificio 8 Edificio 9 Edificio 10 Edificio 11 Edificio 12 Edificio 13 Edificio 14 Edificio 15 Edificio 16
URBANISMO 30% 30% 30% 30% 30% 30% 90% 90% 90%INFRAESTRUCTURA 100% 100% 100% 100% 100% 100% 100% 100% 100%
SUPERESTRUCTURA 80% 90% 100% 100% 100% 100% 100% 100% 100%
INSTALACIONES ELECTRICAS 65% 65% 70% 95% 100% 100% 100% 100% 100%
INSTALACIONES SANITARIAS 65% 65% 70% 95% 100% 100% 100% 100% 100%
INSTALACIONES DE GAS 65% 65% 70% 95% 100% 100% 100% 100% 100%
ALBAÑILERIA 0% 0% 0% 10% 40% 90% 100% 100% 100%
ACABADOS 0% 0% 0% 0% 0% 0% 20% 20% 15%
VIDRIOS Y ALUMINIOS 0% 0% 0% 0% 0% 0% 0% 0% 0%
HERRERIA 0% 0% 0% 5% 30% 50% 100% 100% 66%
41% 42% 44% 53% 60% 67% 81% 81% 77%
Descripción
Avance de obra al 08-04-2010
Torre 8 - 16
Torre 8 - 16