Analisa Standard Material

17
ANALISA MATERIAL SITE LANTAI KERJA TOWER PASANGAN BATU BATA VOLUME 1.00 VOLUME 1.00 SEMEN 0.25 ZAAK SEMEN 0.32 ZAAK PASIR BETON 0.04 PASIR PASANG 0.03 SPLIT 0.07 BATU BATA 70.00 BUAH PONDASI TOWER ( READY MIX) SLOOF, KOLOM DAN RING BALOK VOLUME 1.00 VOLUME 1.00 READY MIX 1.00 SEMEN 4.00 ZAAK PASIR BETON 0.52 SPLIT 0.86 PONDASI TOWER ( SITE MIX) PLESTERAN DAN ACIAN PAGAR BATA VOLUME 1.00 VOLUME 1.00 SEMEN 6.80 ZAAK SEMEN 0.21 ZAAK PASIR BETON 0.54 PASIR PASANG 0.02 SPLIT 0.90 LANTAI KERJA PONDASI SHELTER ( SITE MIX) BETON RABAT ACCESS ROAD VOLUME 1.00 VOLUME 1.00 SEMEN 0.25 ZAAK SEMEN 6.80 ZAAK PASIR BETON 0.04 PASIR BETON 0.52 SPLIT 0.07 SPLIT Analisa Ma PONDASI SHELTER ( SITE MIX) SIRTU ACCESS ROAD VOLUME 1.00 VOLUME 1.00 SEMEN 6.40 ZAAK SIRTU 1.20 PASIR BETON 0.54 SPLIT 0.90 PONDASI BATU KALI PAGAR BETON JEMBATAN VOLUME 1.00 VOLUME 1.00 SEMEN 2.72 ZAAK SEMEN 6.40 ZAAK PASIR PASANG 0.54 PASIR BETON 0.52 BATU KALI 1.20 SPLIT 0.90 TANAH URUGAN BATU KALI JEMBATAN VOLUME 1.00 VOLUME 1.00 TANAH URUGAN 1.20 SEMEN 2.72 ZAAK M 2 M 2 M 3 M 3 M 3 M 3 M 2 M 3 M 3 M 3 M 3 M 2 M 3 M 3 M 3 M 2 M 3 M 3 M 3 M 3 M 3 M 3 M 3 M 3 M 3 M 2 M 3 M 3 M 3 M 3 M 3 M 3 M 3 M 3

Transcript of Analisa Standard Material

Page 1: Analisa Standard Material

ANALISA MATERIAL

SITE

LANTAI KERJA TOWER PASANGAN BATU BATA

VOLUME 1.00 VOLUME 1.00

SEMEN 0.25 ZAAK SEMEN 0.32 ZAAK

PASIR BETON 0.04 PASIR PASANG 0.03

SPLIT 0.07 BATU BATA 70.00 BUAH

PONDASI TOWER ( READY MIX) SLOOF, KOLOM DAN RING BALOK

VOLUME 1.00 VOLUME 1.00

READY MIX 1.00 SEMEN 4.00 ZAAK

PASIR BETON 0.52

SPLIT 0.86

PONDASI TOWER ( SITE MIX) PLESTERAN DAN ACIAN PAGAR BATA

VOLUME 1.00 VOLUME 1.00

SEMEN 6.80 ZAAK SEMEN 0.21 ZAAK

PASIR BETON 0.54 PASIR PASANG 0.02

SPLIT 0.90

LANTAI KERJA PONDASI SHELTER ( SITE MIX) BETON RABAT ACCESS ROAD

VOLUME 1.00 VOLUME 1.00

SEMEN 0.25 ZAAK SEMEN 6.80 ZAAK

PASIR BETON 0.04 PASIR BETON 0.52

SPLIT 0.07 SPLIT Analisa Mae

PONDASI SHELTER ( SITE MIX) SIRTU ACCESS ROAD

VOLUME 1.00 VOLUME 1.00

SEMEN 6.40 ZAAK SIRTU 1.20

PASIR BETON 0.54

SPLIT 0.90

PONDASI BATU KALI PAGAR BETON JEMBATAN

VOLUME 1.00 VOLUME 1.00

SEMEN 2.72 ZAAK SEMEN 6.40 ZAAK

PASIR PASANG 0.54 PASIR BETON 0.52

BATU KALI 1.20 SPLIT 0.90

TANAH URUGAN BATU KALI JEMBATAN

VOLUME 1.00 VOLUME 1.00

TANAH URUGA 1.20 SEMEN 2.72 ZAAK

M2 M2

M3 M3

M3

M3 M2

M3

M3

M3

M3 M2

M3 M3

M3

M2 M3

M3 M3

M3 M3

M3 M3

M3

M3

M2 M3

M3 M3

M3 M3

M3 M3

M3

Page 2: Analisa Standard Material

PASIR PASANG 0.54

BATU KALI 1.20

PASANGAN CONBLOCK HALAMAN

VOLUME 1.00 URUGAN PASIR PONDASI TOWER

CONBLOCK 36.00 VOLUME 0.05

PASIR BETON 0.04 PASIR 0.05

PASANGAN CONBLOCK ACCESS KANSTEEN ACCESS ROAD

VOLUME 1.00 VOLUME 1.00 M

CONBLOCK 36.00 BATU BATA 25.00 BH

PASIR BETON 0.04 SEMEN 0.05 ZAAK

PASIR 0.005

M3

M3

M2

M3 M3

M3

M2

M3

M3

M3

Page 3: Analisa Standard Material

ANALISA PEKERJAAN

PASANGAN BATU BATA 1/2 BATA 1 ad. 1:4(100% tahun 2008) VOLUME PEKERJAAN 1 m2 TIME 1 MAN POWERHARGA 1M2 HARGA TOTAL Rp 405,000 86%

0 Rp - PASANGAN BATU BATA 1M2 ad. 1:4

JENIS PEKERJAAN KOEF VOLUME SATUAN HARGA SATUAN TOTAL HARGA/1M2 PERSENTASE

BATU BATA 70.000 1 70 70.00 Buah Rp 800 Rp 56,000 PASIR PASANG 0.030 1 0 0.03 M3 Rp 250,000 Rp 7,500 SEMEN 0.030 1 0 0.03 zak Rp 70,000 Rp 2,100 PELAKSANA 1.000 1 1 1.00 org Rp 95,000 Rp 95,000 MANDOR 0.048 1 0 1.00 org Rp 90,000 Rp 90,000 KEPALA TUKANG 0.016 1 0 1.00 org Rp 85,000 Rp 85,000 TUKANG 0.160 1 0 1.00 org Rp 70,000 Rp 70,000 PEKERJA 0.480 1 0 1.00 org Rp 65,000 Rp 65,000

TOTAL Rp 470,600 #DIV/0!

Page 4: Analisa Standard Material

PLESTERAN 1 M2 ad. 1:4, tebal 15 mmVOLUME PEKERJAAN 1 m2 TIME 1HARGA 1M2 HARGA TOTAL Rp - Rp - PLESTERAN 1 M2 ad. 1:4, tebal 15 mm

JENIS PEKERJAAN KOEF VOLUME SATUAN HARGA SATUAN (2008) TOTAL HARGA/1M2 PERSENTASE

SEMEN 6.240 1 6.24 KG Rp 70,000 Rp 436,800 PASIR PASANG 0.024 1 0.02 M3 Rp 250,000 Rp 6,000 PELAKSANA 1.000 1 1.00 org Rp 95,000 Rp 95,000 MANDOR 0.015 1 1.00 org Rp 90,000 Rp 90,000 KEPALA TUKANG 0.015 1 1.00 org Rp 85,000 Rp 85,000 TUKANG 0.150 1 1.00 org Rp 70,000 Rp 70,000 PEKERJA 0.300 1 1.00 org Rp 65,000 Rp 65,000

TOTAL Rp 847,800 #DIV/0!

Page 5: Analisa Standard Material

PEKERJAAN 1M2 LANTAI KERJA TOWERVOLUME PEKERJAAN 1 m2 TIME 1HARGA 1M2 HARGA TOTAL Rp - Rp - PEKERJAAN 1M2 LANTAI KERJA TOWER

JENIS PEKERJAAN KOEF VOLUME SATUAN HARGA SATUAN (2008) TOTAL HARGA/1M2 PERSENTASE

SEMEN 0.250 1 0.25 zak Rp - Rp - PASIR BETON 0.040 1 0.04 m3 Rp 140,000 Rp 5,600 SPLIT 0.070 1 0.07 m3 Rp 140,000 Rp 9,800 PELAKSANA 1.000 1 1.00 org Rp 95,000 Rp 95,000 MANDOR 0.026 1 1.00 org Rp 90,000 Rp 90,000 KEPALA TUKANG 0.026 1 1.00 org Rp 85,000 Rp 85,000 TUKANG 0.026 1 1.00 org Rp 70,000 Rp 70,000 PEKERJA 0.520 1 1.00 org Rp 65,000 Rp 65,000

TOTAL Rp 420,400 #DIV/0!

Page 6: Analisa Standard Material

PEKERJAAN 1M2 BEKISTING PONDASIVOLUME PEKERJAAN 1 m2 TIME 1HARGA 1M2 HARGA TOTAL Rp - Rp - PEKERJAAN 1M2 BEKISTING PONDASI

JENIS PEKERJAAN KOEF VOLUME SATUAN HARGA SATUAN (2008) TOTAL HARGA/1M2 PERSENTASE

TRIPLEK 9mm 0.040 1 0.04 m2 Rp 102,000 Rp 4,080 PAKU 0.300 1 0.30 kg Rp 12,500 Rp 3,750 MINYAK BEKISTING 0.100 1 0.10 ltr Rp 30,000 Rp 3,000 PELAKSANA 1.000 1 1.00 org Rp 95,000 Rp 95,000 MANDOR 0.026 1 1.00 org Rp 90,000 Rp 90,000 KEPALA TUKANG 0.026 1 1.00 org Rp 85,000 Rp 85,000 TUKANG 0.026 1 1.00 org Rp 70,000 Rp 70,000 PEKERJA 0.520 1 1.00 org Rp 65,000 Rp 65,000

TOTAL Rp 415,830 #DIV/0!

Page 7: Analisa Standard Material

PEKERJAAN 1M2 BEKISTING KOLOMVOLUME PEKERJAAN 1 m2 TIME 1HARGA 1M2 HARGA TOTAL Rp - Rp - PEKERJAAN 1M2 BEKISTING KOLOM

JENIS PEKERJAAN KOEF VOLUME SATUAN HARGA SATUAN (2008) TOTAL HARGA/1M2 PERSENTASE

TRIPLEK 9mm 0.040 1 0.04 m2 Rp 102,000 Rp 4,080 PAKU 0.300 1 0.30 kg Rp 12,500 Rp 3,750 MINYAK BEKISTING 0.100 1 0.10 ltr Rp 30,000 Rp 3,000 PELAKSANA 1.000 1 1.00 org Rp 95,000 Rp 95,000 MANDOR 0.026 1 1.00 org Rp 90,000 Rp 90,000 KEPALA TUKANG 0.026 1 1.00 org Rp 85,000 Rp 85,000 TUKANG 0.026 1 1.00 org Rp 70,000 Rp 70,000 PEKERJA 0.520 1 1.00 org Rp 65,000 Rp 65,000

TOTAL Rp 415,830 #DIV/0!

Page 8: Analisa Standard Material

PEKERJAAN 1M2 BEKISTING BALOKVOLUME PEKERJAAN 1 m2 TIME 1HARGA 1M3 HARGA TOTAL Rp - Rp - PEKERJAAN 1M2 BEKISTING BALOK

JENIS PEKERJAAN KOEF VOLUME SATUAN HARGA SATUAN (2008) TOTAL HARGA/1M2 PERSENTASE

TRIPLEK 9mm 0.040 1 0.04 m2 Rp 102,000 Rp 4,080 PAKU 0.300 1 0.30 kg Rp 12,500 Rp 3,750 MINYAK BEKISTING 0.100 1 0.10 ltr Rp 30,000 Rp 3,000 PELAKSANA 1.000 1 1.00 org Rp 95,000 Rp 95,000 MANDOR 0.026 1 1.00 org Rp 90,000 Rp 90,000 KEPALA TUKANG 0.026 1 1.00 org Rp 85,000 Rp 85,000 TUKANG 0.026 1 1.00 org Rp 70,000 Rp 70,000 PEKERJA 0.520 1 1.00 org Rp 65,000 Rp 65,000

TOTAL Rp 415,830 #DIV/0!

Page 9: Analisa Standard Material

PEKERJAAN 1 M2 LANTAI KERJA TOWERVOLUME PEKERJAAN 1 m2 TIME 1HARGA 1M2 HARGA TOTAL Rp - Rp - PEKERJAAN 1 M2 LANTAI KERJA TOWER

JENIS PEKERJAAN KOEF VOLUME SATUAN HARGA SATUAN (2008) TOTAL HARGA/1M2 PERSENTASE

SEMEN 0.250 1 0.25 zak Rp - Rp - PASIR BETON 0.040 1 0.04 m3 Rp 140,000 Rp 5,600 SPLIT 0.070 1 0.07 m3 Rp 140,000 Rp 9,800 PELAKSANA 1.000 1 1.00 org Rp 95,000 Rp 95,000 MANDOR 0.026 1 1.00 org Rp 90,000 Rp 90,000 KEPALA TUKANG 0.026 1 1.00 org Rp 85,000 Rp 85,000 TUKANG 0.026 1 1.00 org Rp 70,000 Rp 70,000 PEKERJA 0.520 1 1.00 org Rp 65,000 Rp 65,000

TOTAL Rp 420,400 #DIV/0!

Page 10: Analisa Standard Material

MAN POWERPELAKSANA Rp 95,000 MANDOR Rp 90,000 KEPALA TUKANG Rp 85,000 TUKANG Rp 70,000 PEKERJA Rp 65,000

BALI

PASIR PASANG 1 M3 Rp 250,000 BATU BATA PRESS 1 BUAH Rp 450 BATU BATA MANUAL/TANGAN 1 BUAH Rp 300 PASIR LAMPUNG 1 M3 Rp 170,000 PASIR BETON 1 M3 Rp 140,000 PASIR MONDU 1 M3 Rp 160,000 PASIR URUG 1 M3 Rp 95,000 PASIR PUTIH BANGKA 1 M3 Rp 175,000 SIRTU 1 M3 Rp 95,000 SPLIT 1 M3 Rp 140,000 BATU KALI BELAH 1 M3 Rp 125,000 SIRDAM 1 M3 Rp 125,000 ABU BATU 1 M3 Rp 125,000 TANAH MERAH 1 M3 Rp 95,000 SEMEN TIGA RODA 1 ZAK Rp 70,000 SEMEN TIGA RODA PUTIH 1 ZAK Rp 18,000 SEMEN GRESIK 1 ZAK Rp 10,500 SEMEN HOLCIM 1 ZAK Rp 53,000

HEBELPANEL 1 M3 Rp 250,000 ANAK TANGGA 1 M3 Rp 2,000,000

BESI BETOND.6mm 1 BH Rp 20,000 D.8mm Rp 32,000 D.10mm Rp 45,000 D.12mm Rp 65,000 D.16mm Rp 110,000

PAKUPAKU TRIPLEK/KAYU 1 KG Rp 12,500 PAKU BETON BIASA 1 DUS Rp 25,000 PAKU BETON MUTU BAGUS 1 DUS Rp 30,500 KAWAT BETON 1 Rp 16,000 PAKU GRC 1 DUS Rp 20,000 MINYAK BEKISTING 1 LITER Rp 30,000

KAYURENGMERANTI 2X3 1 BTG Rp 12,500 MERANTI 3X4 1 BTG Rp 15,000 BORNEO 2X3 Rp 13,000 BORNEO 3X4 Rp 20,000 KAMPER 2X3 Rp 17,000 KAMPER 3X4 Rp 20,000 KASOMERANTI 4X6 Rp 30,000

Page 11: Analisa Standard Material

MERANTI 5X7 Rp 37,500 BORNEO 4X6 Rp 28,000 BORNEO 5X7 Rp 43,000 KAMPER 4X6 Rp 45,000 KAMPER 5X7 Rp 65,000

TRIPLEK3MM Rp 39,500 4MM Rp 52,000 6MM Rp 72,000 9MM Rp 102,000 12MM Rp 140,000 15MM Rp 175,000

Page 12: Analisa Standard Material
Page 13: Analisa Standard Material

BOUPLANK 39000BONGKAR BOUPLANK 3500GALIAN TANAH PONDASI 35000URUGAN PASIR 192000

berat/m = 0.617 kg

Page 14: Analisa Standard Material

m3 0.04 0.06 4 0.0096 105 Rp 30,000 Rp 3,150,000

Page 15: Analisa Standard Material

m3 0.05 0.07 4 0.014 72 Rp 40,000 Rp 4,200,000 m3 0.04 0.06 4 0.0096 105 Rp 25,000 Rp 2,625,000 m3 0.05 0.07 4 0.014 72 Rp 35,000 Rp 3,675,000 m3 0.04 0.06 4 0.0096 105 Rp 40,000 Rp 4,200,000 m3 0.05 0.07 4 0.014 72 Rp 60,000 Rp 6,300,000

Page 16: Analisa Standard Material

Besi D.10panjang = 6 mn = 4 bh

Menghitung kebutuhan besi tulangan pokok :- Volume besi D.10 = 24 m- panjang besi = 11 mmaka besi yang dibutuhkan = 2 kg

- berat per m' besi D.10 = 0.617 total kebutuhan besi D.10 = 14.808 kg

Menghitung sengkang/cincinpanjang = 90 0.9 mjarak pemasangan = 0.15 mbyk sengkang = 40 buah

panjang total sengkang = 36 mkebutuhan besi sengkang = 3 buahberat per m' besi D.8 = 0.395 kgtotal kebutuhan besi D.8 = 14.22 kg

Page 17: Analisa Standard Material